Time limit for supervisor to review contractor's design documents

In construction projects, according to the Regulations on Quality Management of Construction Projects, the supervisor shall complete the review within 15 days after receiving the design documents submitted by the construction unit. If it cannot be completed on schedule, it shall promptly notify the undertaker and explain the reasons.

According to the Regulations on Quality Management of Construction Projects, the supervisor shall comprehensively supervise the construction process and review the design documents submitted by the construction unit. Among them, the supervisor's review period for the contractor's design documents is fifteen days. Specifically, after receiving the design documents submitted by the construction unit, the local supervision agency shall complete the review and put forward its review opinions within fifteen days. If it is not completed within the time limit, the supervisor shall promptly notify the contractor, explain the reasons and re-establish the review schedule. In addition, the supervisor should be serious and responsible when reviewing the design documents, including the rationality of the design scheme, the feasibility of technology and economy, and whether it complies with laws and regulations. The review results shall be notified to the contractor and the construction unit in time to ensure that the construction project can be built safely, with high quality and high efficiency while meeting the design requirements.

If the supervisor fails to review the design documents within the specified time, will it have an impact on the project construction? If the supervisor fails to review the design documents within the specified time, it will have a certain impact on the project construction. First of all, the audit opinion of the supervisor is an important basis for the construction unit to further carry out the construction work. If the audit opinion is not put forward within the specified time, the progress of the construction unit will be delayed. Secondly, if there are problems in the design documents, which are not found and corrected in time, it may bring security risks and quality problems to the project construction. Therefore, the supervisor should complete the review of design documents within the specified time to ensure the smooth progress of the project construction.

The construction project supervision unit shall review the design documents of the contractor within fifteen days. The supervisor shall be responsible for the rationality, technical and economic feasibility and compliance with laws and regulations of the design scheme, and inform the review results in time. If the review work is not completed within the time limit, the supervisor shall promptly notify the contractor and re-establish the review schedule to ensure the smooth progress of the project construction.

Legal basis:

Article 32 of the "Building Law of People's Republic of China (PRC)", construction project supervision shall, on behalf of the construction unit, supervise the contractor in terms of project quality, construction period and the use of construction funds in accordance with laws, administrative regulations, relevant technical standards, design documents and construction scale contracts. If the supervisor thinks that the project construction does not meet the engineering design requirements, construction technical standards and contract stipulations, he has the right to ask the construction enterprise to correct it. If the engineering supervisor finds that the engineering design does not meet the quality standards of the construction project or the quality requirements agreed in the contract, he shall report to the construction unit and ask the design unit to correct it.