1. What is the meaning of finished product partition and the difference from traditional partition?
Answer: The finished partition is a new customized partition wall with factory and modular production and installation. With installation and after-sales service. On-site assembly, can be used many times, and has the characteristics of morphological transformation after installation.
Compared with the traditional partition, in addition to the above aspects, our finished partition also has the advantages of short construction period, diverse colors, environmental protection, no damage to the original decoration style, and authoritative test report issued by a third party (including fire resistance limit, sound insulation effect, safety and stability, acid and alkali corrosion resistance).
2. What is the material, width and color of the louver used by the sun? If there is something wrong with the shutter, how to fix it?
Answer: The blinds used by Sun Company are aluminum blinds, with toughness H 19, thickness 0.2 1mm and various colors 100. The commonly used louver is 25mm, and there are also special louvers of 15mm and 35mm.
Basically, the blinds we use are not easily damaged. If there is a problem, it may be that the knob has fallen off due to long-term mechanical twisting, so simply handle it. If the inner louver rope is broken, the louver needs to be replaced.
3. At what stage do you usually start ordering finished partitions in engineering? Can I use it outdoors?
A: Generally, the partition will be set at the beginning of the ceiling and the ground, just after the construction of the ceiling and the ground is completed, which just meets the production cycle of the profile. At the same time, Taiyang finished partition also has the construction ability before the ground and ceiling are untreated.
Under normal circumstances, our partition can't be used outdoors, because our partition is a finished partition, which is assembled and is not conducive to anti-theft.
4. What are the spraying forms of finished solar partition finishes? How to choose the appropriate spraying form?
A: There are four kinds of subarea spraying of the sun. 1). Oxidation scrubbing 2). Electrostatic powder 3). Acrylic acid 4). Fluorocarbon spraying. In general, it is recommended to use electrostatic powder indoors, which has high cost performance, smooth surface and easy cleaning. Fluorocarbon spraying is generally used outdoors, which can withstand the harsh environment of wind, rain and sun, and the surface has obvious graininess. In addition, their prices are different: oxidized matt.
Therefore, we suggest that customers choose our electrostatic spraying indoors, which can fully meet the needs of office.
5. According to the size of the area, what is the construction period of our finished product partition?
A: Generally speaking, the production cycle of our finished partition is about 10 days (the decoration color is commonly used), and it takes about 2 days to install it below 100 square meters, 500 square meters and 6 days to install it below 100 square meters. Under normal circumstances, it is 100 m2/day, and the glass louver is customized for 7 days. The installation of the glass louver is the same as that of the partition. According to the specific location of the project and the time of the porter. Generally speaking, it takes about 30 days to be below 500 meters, 40 days to be below 500- 1000 meters and 60 days to be below 1000 meters. The specific situation can be shortened or extended.
6. What kind of material can be used in the door side functional area?
Answer: Fire-proof boards are generally installed in the functional area beside our doors. According to the requirements of customers, we can also use several forms of plates, such as steel plates, aluminum-plastic plates, fire-proof plates and solid wood plates.
7. What door series can match aluminum alloy partitions, and what are their prices?
A: Generally, there are four kinds of doors that can match our partition. 1: glass door 2: aluminum alloy door 3: wooden door. Glass doors are divided into hinged doors without glass frames, floor-to-floor bouncing doors and glass doors supporting aluminum alloy doorframes. Aluminum alloy doors are generally divided into single-glass aluminum alloy doors and double-wave louver aluminum alloy doors. Wooden doors are divided into solid wood composite doors and fire-proof board doors.
8. What are the forms of finished solar partition? What is the approximate price? Are there any restrictions?
A: Solar finished partitions are generally divided into three series. 1).25 series 2).80 series
3). 1 10 series.
Series 25 is only suitable for glass handling under the premise of 2.6 meters, and is divided into aluminum alloy columns and transparent columns.
Series 80 can be widely used in offices, generally divided into single-layer glass series, double-layer glass series and double-layer glass louver series.
1 10 series is less used in the north because of its higher price.
9. What conditions do you need to meet when installing the finished partition on site? What are the methods for processing and other operation surface nodes?
A: Generally, when installing partitions, the site should be a suspended ceiling. After the grounding is completed, if wiring is needed, the position of the conductor must be determined before it can be carried out.
When dealing with other working face nodes, it depends on the environment of the installation site. Usually, expansion bolts are driven on the ground, and self-tapping nails are used as the standard for elevated tracks. If the ceiling is a mineral wool board ceiling, we suggest using a fake hanging beam at the joint with the partition, which will increase the stability of the partition. If the floor is marble floor or geothermal pipeline, we will treat it with glue, which will not damage the decoration. When there are pipes on the wall, we suggest making fake wall treatment, because our tempered glass cannot be processed into the opposite sex.
10. Can the finished solar partition be wired? When should the customer make the request?
Answer: The profile of the finished solar partition can be wired internally, or the panel can be placed by raising the ground rail. Customers should reserve thread ends before the ceiling is completed, and put forward requirements before the framework construction.
1 1. What is the general module size of the finished solar partition? What conditions should be met if a large module is needed?
A: In general, we recommend customers to adopt a module size of around 1.2m, because the module size of this specification is ideal in both visual sense and maneuverability. If you need to choose a large module, it depends on what the site construction environment is like. If you can meet the requirements of glass installation, you can add modules, but try not to be too big. If it is too large, it will involve the safety and stability factor.
12. What is the safety, stability, fire resistance limit, sound insulation effect and corrosion resistance of the finished solar partition?
Answer: Taiyang finished partition wall has the inspection report issued by the authoritative department, and our fire resistance limit is 1.45 hours.
The sound insulation effect of double-layer glass louver series can reach 55 decibels.
Safety and stability are reflected in the anti-slip coefficient in the test report. The national requirement is 3 times, and we successfully reached 10 times, far higher than the national standard.
Acid and alkali corrosion resistance also fully meets the national requirements.
13. Besides glass partition, what other materials are there for the finished solar partition?
A: In addition to glass partitions, there are also steel plates, aluminum-plastic plates, fire-proof plates and solid wood composite plates.
14. What glass did the sun use when installing the partition? According to the different shapes, which specifications of glass should be selected?
Answer: Sun's glass is all-toughened automobile-grade glass, with fine grinding on all sides. Clean and transparent is like the windshield of a car. According to different forms, 10mm thick is selected for series 25, 8㎜ or10mm thick tempered glass is generally selected for single-layer glass, and 5㎜ or 6㎜ thick tempered glass is enough for double-layer glass, because the fixation of our finished partition depends on the structure of the profile, not the thickness of the glass.
15. What suggestions should we make if customers want to apply a film or scrub?
A: In general, we suggest using frosting treatment when the whole block is needed. If it is local, it is recommended to film it. Because the film is flexible, the height and size can be adjusted freely. The matte treatment is not easy to adjust, and there will be a height difference.
16. What is the after-sales commitment of the finished solar partition? How long will it take to get there if there is an emergency?
Answer: Sun Company guarantees that the paint will not change color or peel for 0/5 years, and the hardware will be replaced free of charge for 2 years. Guaranteed lifetime free maintenance. If anything happens, we will be on standby 24 hours a day in the city and will arrive as soon as possible outside the city.
17. Can the double glass series of the finished solar partition achieve the sealing effect, and will there be dust?
Answer: Sun Company's double glass series adopts patented three-phase soft connection, so that particulate dust will not enter between the profile and the glass. As a user, the possibility of dust entering can be completely ruled out.