Does the new regulation require no bidding for projects under 4 million yuan?

Does the new regulation require no bidding for projects under RMB 4 million?

Article 7 of the "Provisions on Bidding Scope and Scale Standards for Engineering Construction Projects"

The second step of this regulation Various engineering construction projects within the scope stipulated in Articles to Article 6, including project survey, design, construction, supervision and the procurement of important equipment and materials related to project construction, must be tendered if they meet one of the following standards: (1) The estimated price of a single construction contract is more than RMB 2 million;

(2) The estimated price of a single contract for the purchase of important equipment, materials and other goods is more than RMB 1 million;

(3) For the procurement of survey, design, supervision and other services, the estimated price of a single contract is more than RMB 500,000;

(4) The estimated price of a single contract is lower than that of (1), The standards specified in items (2) and (3), but the total project investment is more than 30 million yuan.

Article 8 If the survey and design of a construction project uses specific patents or proprietary technologies, or if the architectural artistic shape has special requirements, bidding may not be conducted with the approval of the project authority.

The provincial standards are: a total investment of 10 million yuan, a single supervision contract of less than 300,000 yuan, and no bidding is required if both conditions are met. How many *** projects under 10,000 yuan do not require bidding?

Depending on the level, it is 100,000 for towns and cities, and more than 300,000 for counties and cities. How to bid for projects under RMB 500,000

1. Engineering construction projects that must be bid (mandatory)

1) Large-scale infrastructure related to social public interests and public safety Projects

2) Public utility projects related to public interests and public safety

3) Projects invested entirely or partially with state-owned funds

4 ) Projects that use state financing in whole or in part

5) Projects that use loans from international organizations or foreign countries

If it is not within this scope, it can be directly contracted, or it can be tendered for less than 5 million Does project supervision require bidding? "Provisions on Standards for Bidding Scope and Scale of Engineering Construction Projects"

Article 7 All types of engineering construction projects within the scope of Articles 2 to 6 of these regulations, including the If the survey, design, construction, supervision and the procurement of important equipment and materials related to project construction meet one of the following standards, bidding must be conducted:

(1) The estimated price of a single construction contract is 2 million More than RMB 1 million;

(2) Procurement of important equipment, materials and other goods, the estimated price of a single contract is more than RMB 1 million;

(3) Survey, design, For the procurement of supervision and other services, the estimated price of a single contract is more than RMB 500,000;

(4) The estimated price of a single contract is lower than the standards specified in items (1), (2), and (3) , but the total project investment is more than 30 million yuan.

Do projects with an investment scale of less than 50,000 yuan in Chuxiong Prefecture require bidding?

I personally understand that the bidding you are talking about refers to public bidding. Projects that must be publicly bid have the source of funds and investment. There are two conditions for the total amount of funds. Generally speaking, public bidding is required for public utilities, infrastructure construction, and projects using state funds and foreign financing. Public bidding is not required for construction projects with a single contract valuation of less than 2 million yuan.

Reference: Engineering construction project bidding scope and scale standards: baike.baidu./link?url=UwVgCgugs2ir88mGN5pAtAk2svGolHj19Mn2BEKxHJT6WgzJMGvxJtgq-qjFTRT9WrXwWlk7LIBRCrmfDIRfRq Hot water projects below 300,000 *** Can you not bid?

Engineering bidding agency quality level Application standards: (Ministry of Construction Order No. 154)

1. General conditions:

1. It is an intermediary organization established in accordance with the law and has independent legal personality;

2 . Have no administrative affiliation or other interest relationship with administrative agencies and other state agencies;

3. Have a fixed business location and the necessary facilities and office conditions to carry out project bidding agency business;

4. Have a sound organizational structure and internal management rules and regulations;

5. Have the corresponding professional capabilities to prepare bidding documents and organize bid evaluation;

6. Have the ability to serve as an evaluator A database of technical, economic and other experts for the selection of members of the bidding committee;

7. Other conditions stipulated by laws and administrative regulations.

2. Qualification conditions:

1. Tentative level: registered capital of not less than 1 million yuan.

2. Class B: Obtained the qualification of tentative grade project bidding agent for one year; the registered capital is not less than 1 million yuan.

3. Class A: Obtained Class B project bidding agency qualification for 3 years; registered capital is not less than 2 million yuan.

3. Performance conditions:

1. Tentative grade: None

2. Grade B: The cumulative project bidding agency winning amount in the past 3 years is 800 million Above RMB 1.6 billion;

3. Class A: The cumulative project bidding agency winning amount in the past three years is more than RMB 1.6 billion (based on the bid winning notice);

4. Personnel Conditions:

1. Tentative level: There should be no less than 12 full-time staff of an engineering bidding agency with intermediate professional titles or above, including no less than 6 people with registered professional qualifications in engineering construction (including registered cost There should be no less than 3 engineers), and no less than 6 people who have been engaged in engineering bidding agency business for more than 3 years; the technical and economic person in charge is a full-time staff of the agency, with more than 8 years of experience in engineering management, and has senior technical and economic professional titles and engineering Registered professional qualifications for construction;

2. Class B: A project bidding agency with intermediate professional titles or above shall have no less than 12 full-time staff, of which no less than 6 shall have registered professional qualifications for engineering construction ( Among them, there are no less than 3 registered cost engineers), and no less than 6 people who have been engaged in engineering bidding agency business for more than 3 years; the technical and economic person in charge is a full-time staff of the agency, with more than 8 years of experience in project management, and a senior technical and economic person Professional titles and registered professional qualifications for engineering construction;

3. Class A: There shall be no less than 20 full-time staff of an engineering bidding agency with intermediate professional titles or above, including no less than 20 persons with registered professional qualifications for engineering construction. 10 people (including not less than 5 registered cost engineers), and no less than 10 people who have been engaged in project bidding agency business for more than 3 years; The technical and economic person in charge is a full-time staff of the agency, with more than 10 years of experience in project management, and Senior technical and economic professional title and engineering construction registered professional qualification;

5. Business that can be contracted:

1. Tentative grade: can only undertake projects with a total project investment of less than 60 million yuan Engineering bidding agency business.

2. Class B: Can only undertake bidding agency business for projects with a total project investment of less than 100 million yuan

3. Class A: Can undertake general bidding agency business for various projects How many days does it take to complete the fire protection project with a contract price of around 4 million?

The duration of construction projects is the most unpredictable, mainly due to the funds and attitudes of real estate developers. Funding is a prerequisite. If the funds are not in place, the project will not start quickly. A direct condition of attitude, Party A's attitude (whether in a hurry or not) directly affects the progress of the project.

A 4 million fire protection project normally takes 5-6 months to complete, but our company has completed a 1,000 million project in 5 months and passed the fire protection acceptance. Do projects worth less than 300,000 yuan require bidding?

According to the bidding law, projects worth more than 2 million yuan, goods worth more than 1 million yuan, and services worth more than 500,000 yuan must invite bids. A project worth RMB 300,000 does not fall into the category that requires bidding according to law. It just depends on the specific situation of your company.

If you have other questions about bidding, you can search

China Tendering and Tendering Company*** Service Platform

The contents of the bidding documents in the above transaction think tank There are many files that are updated in real time and can be downloaded directly for free. How to bid for maintenance and renovation projects under 200,000 yuan?

"Standard Regulations on the Scope and Scale of Bidding for Engineering Construction Projects"

Article 7

Various engineering construction projects within the scope of Articles 2 to 6 of these Regulations, including project survey, design, construction, supervision and the procurement of important equipment and materials related to engineering construction, If one of the following standards is met, bidding must be carried out:

(1) The estimated price of a single construction contract is more than 2 million yuan;

(2) Important equipment, materials and other goods For procurement, the estimated price of a single contract is more than RMB 1 million;

(3) For the procurement of services such as survey, design, supervision, etc., the estimated price of a single contract is more than RMB 500,000;

>

(4) The estimated price of a single contract is lower than the standards specified in items (1), (2), and (3), but the total investment in the project is more than 30 million yuan.

According to the above regulations, maintenance and renovation projects below 200,000 yuan can be invited to bid. What are the reasonable regulations for bidding for projects below 2 million yuan? "Tendering and Bidding Law of the People's Republic of China"

Article 7: Various engineering construction projects within the scope of Articles 2 to 6 of these regulations, including project survey, design, and construction , supervision and the procurement of important equipment and materials related to project construction, if they meet one of the following standards, bidding must be conducted:

(1) The estimated price of a single construction contract is more than 2 million yuan;

(2) Procurement of important equipment, materials and other goods, the estimated price of a single contract is more than 1 million yuan;

(3) Procurement of survey, design, supervision and other services , the estimated price of a single contract is more than 500,000 yuan;

(4) The estimated price of a single contract is lower than the standards specified in items (1), (2), and (3), but the total investment of the project Above RMB 30 million.