Bidding fee

The charging standard of bidding fee is a progressive charging method according to the difference quota rate. The charging standard shall be implemented in accordance with the provisions of the annex to these Measures, and the floating range shall not exceed 20%. The maximum limit of engineering projects is 4.5 million yuan, the maximum limit of goods projects is 3.5 million yuan, and the maximum limit of service projects is 3 million yuan. The service fee of bidding agent is calculated by the progressive method of differential fixed rate. For example, the bidding amount of a project bidding agency business is 60 million yuan, and the charging amount of bidding agency service is calculated as follows: 6,543.8+0,000 yuan × 654.38+0.0% = 6,543.8+0,000 yuan; (500

100) ten thousand yuan × 0.7% = 28,000 yuan; ( 1000

500) ten thousand yuan × 0.55% = 27,500 yuan; (5000

1000) ten thousand yuan × 0.35% =140 thousand yuan; (6000

5000) 1 10,000 yuan× 0.2% = 20,000 yuan; Total charge =1+2.8+2.75+14+2 = 225,500 yuan. A bidding agent is a person with professional bidding knowledge. When bidding, entrusting an agent to bid can ensure the bidding quality and the smooth progress of the bidding procedure. The bidding agency shall charge the bidding agency service fee in strict accordance with the bidding agency service standard, and shall not charge other irrelevant fees. The tenderer shall also pay the corresponding agency fee to the tendering agency according to the service agreement. Bidding activities will produce certain transaction costs. For bidders, in order to get the bidding opportunity, they will organize relevant personnel to collect and analyze the procurement information, which will lead to transportation, accommodation, personnel salary, or need to pay consulting fees and information fees to intermediary agencies; In the process of bidding, it is necessary to purchase bidding documents, make bidding documents, organize on-site reconnaissance, pay bid bond and participate in bidding. These activities will also generate transportation, accommodation, staff salaries, printing fees, consulting fees and other expenses. These fees are collectively referred to as bidding fees.

First, how to calculate the tender fee?

1. Cost of purchasing bidding documents: In general, the cost of bidding documents (tenders) is calculated at cost. Generally 100.

2000 (reference).

2. The cost of making the tender: If you write and print the tender yourself, there will be almost no cost in the future except the cost of purchasing the glue machine in the early stage. If the bidding documents and printing need to be completed by another party, the cost may be thousands, which is charged according to the specific situation.

3. Printing fee for bidding documents. At least one original and two or more copies with binding, cover, etc. Color: about 300 copies, black and white: 100 yuan. If there are two copies of one original, it will add up to about 500 yuan.

4. Qualification fee: If someone borrows the qualification of others to bid, the relevant fee (usually several thousand yuan) should be agreed with others. If you win the bid, you will also have to pay the comprehensive service fee of the trading center (about 0.06% of the bid price).

5. Bid bond: generally 2% of the control price, with a maximum of 800,000 yuan. If you don't win the bid, it will be returned without interest within one week. At present, various localities have issued documents one after another, explicitly canceling "bidding registration" and "no bid bond". The bid bond may be omitted.

6. Quality deposit: 65,438+00% of the contract amount. If the warranty period is as long as three years, the amount of work is huge, which is an expensive expense. The recovery of quality guarantee money varies from one year to three years, and the occupation cost is high.

7. Installation and debugging costs: the installation and debugging of instruments will involve handling fees, hoisting fees, accessories fees, site engineering renovation fees, special tool rental fees, third-party service fees, etc. If complex services are involved, such as special inspection, 3Q verification, measurement, etc. There will be a lot of expenses. If you don't consider this expense in advance, you may lose thousands or even tens of thousands of profits.

8. Other miscellaneous expenses: meals, cars and other consumption.

Second, the tender documents refer to the corresponding documents prepared by the bidder according to the requirements of the tender documents, which are generally composed of technical documents, business documents, quotation documents and other parts.

(1) The business part includes a series of contents such as company qualification and company introduction. , as well as other documents and other related contents required by the tender documents, including company performance, various certificates and reports, etc.

(2) The technical part includes project description, design and construction scheme, bill of quantities, staffing, drawings, tables and other technical schemes and other technical related materials.

(3) The price part includes the description of bid quotation, total bid price, price list of main materials, etc.

Legal basis:

Interim Measures for the Administration of Bidding Agency Service Charges

Article 9

The bidding agent service fee adopts the differential fixed rate progressive charging method. The charging standard shall be implemented in accordance with the provisions of the annex to these Measures, and the floating range shall not exceed 20%.