I. Methods
1, can search for small ant calculation factory, can do engineering quantity calculation and budget, high quality and high efficiency;
2. You can search the budget cost units online, and some units do better.
3. You can go to a third-party platform and entrust others to do it. Pay attention to fraud prevention on the platform. You can find a unit or someone to do it.
Second, the cost budget charging standard
1, and part of the charge is 0.2-0.5% of the cost budget (assuming the project cost is 1 10,000 and the cost is 2000-5000);
2. Professional companies charge, and the factory charge calculated by Xiao Ant is about 0. 1% of the cost budget (assuming the project cost is 1 10,000, and the engineering quantity calculation cost is 1000-2000, depending on the drawings);
3. Some of them are suggested to be charged according to the cost budget quota of each province and city.
Third, the charging standard of engineering quantity calculation
1. The fees charged by general consulting companies are calculated according to the budgeted cost, because the calculation of engineering quantity is one of the most tiring and troublesome tasks in the budget.
2. Some companies charge about 0.05% of the cost budget, depending on the drawings.
Four. suggestion
1. If only the quantities are calculated, it is cost-effective to choose the quantity company.
2. If you want the cost and save money, you can now find a professional quantity company to calculate the engineering quantity, and then let people set the price, so the price is much lower (the second point mentioned above is the most cost-effective).
3. The accuracy of engineering quantity calculation and engineering budget is very important, and accuracy is the key.