Do you have detailed information about the sewage treatment plant in Dingshan Reclamation Area of Wenzhou Economic and Technological Development Zone?

Construction site: North of the intersection of Liu Jing Road and Weisan Road in Piandingshan Reclamation Area, Wenzhou Economic and Technological Development Zone, Wenzhou Private Economic and Technological Industrial Base. The long-term total land area of the third sewage treatment plant is 1.64 hectares (25 mu).

Construction scale: one-time planning and phased implementation. The construction scale of the first phase project is 654.38+500,000 tons/day, and the long-term total scale is 60,000 tons/day.

Total investment of the project: the total investment of the first phase project is 52.82 million yuan. (Note: Wenzhou Hongze Environmental Protection Technology Co., Ltd. is the construction unit)

Jiangxi Hongcheng Water Industry Environmental Protection Co., Ltd. (hereinafter referred to as "Hongcheng Environmental Protection") and Wenzhou Hongze Environmental Protection Technology Co., Ltd. (hereinafter referred to as "Wenzhou Hongze") jointly invested to establish Wenzhou Hongxiang Sewage Treatment Co., Ltd. (hereinafter referred to as "Wenzhou Hongxiang"), and used this to build and operate the third sewage treatment plant project in Wenzhou Binhai Park with a registered capital of 20.4 million yuan.

Among them, Hongcheng Environmental Protection contributed 6.5438+0.0404 million yuan, accounting for 5.65438+0% equity;

Wenzhou Hongze contributed 9.996 million yuan, accounting for 49% of the shares.

Both parties shall enjoy the rights and interests in proportion to their capital contributions, and assume corresponding responsibilities and obligations. The project company will sign a franchise agreement with the government for the third sewage treatment plant (BOT) project in Wenzhou Binhai Park, with the operating period of 26 years (including the construction period).

Introduction to the main body of investment agreement

1, Basic information of Jiangxi Hongcheng Water Industry Environmental Protection Co., Ltd.:

Name: Jiangxi Hongcheng Environmental Protection Co., Ltd.

Address: Room 30 1, North Building, No.998 Torch Street, High-tech Zone, Nanchang

Legal Representative: Shi Xiaohua, with a registered capital of RMB 750 million only.

Company type: limited liability company (sole proprietorship)

Scope: Urban domestic sewage and industrial wastewater treatment. (unless there are special provisions of the state)

Jiangxi Hongcheng Environmental Protection Co., Ltd. has a registered capital of 750 million yuan and a total investment of over 2.6 billion yuan. Mainly engaged in the treatment of urban domestic sewage and industrial wastewater (Grade A qualification for the operation of environmental pollution control facilities), 78 sewage treatment plants under its jurisdiction are located in 77 counties (cities, districts) of Nanchang, Jiujiang, Shangrao, yingtan, Ganzhou, Fuzhou, Ji 'an, Yichun and Pingxiang, with a total designed treatment capacity of 10. The sewage treatment capacity of the first phase is 998,000 cubic meters/day, and the first-class B standard of Pollutant Discharge Standard for Urban Sewage Treatment Plants (GB 189 18-2002) is implemented. 20 1 1 March, Hongcheng's environmental sewage treatment scale reached1258,000 cubic meters/day.

2. Basic information of Wenzhou Hongze Environmental Protection Technology Co., Ltd.:

Name: Wenzhou Hongze Environmental Protection Technology Co., Ltd.

Address: Room 5 108, Office Building of Binhai Park Management Committee, Wenzhou Economic and Technological Development Zone.

Legal Representative: Xu Weiwen, with a registered capital of 20 million yuan.

Company type: limited liability company

Scope of business: design, construction, operation and technical consulting services of sewage treatment projects; Research and development of water treatment technology and products (operating by qualification).

Wenzhou Hongze Environmental Protection Technology Co., Ltd. is a professional scientific and technological environmental protection enterprise. Founded in June 2004, the company was formerly known as Wenzhou Zhong Qing Environmental Protection Technology Co., Ltd., and was renamed Wenzhou Hongze Environmental Protection Technology Co., Ltd. in June 2006. The company is located in Wenzhou Economic and Technological Development Zone, a national development zone. The company was established by capital contributions made jointly by four shareholders, Xu Weiwen, Li Xiangying, Li Shengfang and Jin Yixian. The original registered capital was 1 00,000 yuan, and the newly-increased registered capital was100,000 yuan in April 2008, of which, Xu Weiwen contributed16,600,000 yuan, accounting for 83% of the total share capital. III. Basic information of the investment target: Hongcheng Environmental Protection and Wenzhou Hongze * * * jointly established Wenzhou Hongxiang Sewage Treatment Co., Ltd. to build and operate Wenzhou.

1, business scope: design, construction, operation and technical consulting services of sewage treatment projects; Research and development of water treatment technology and products (operating by qualification). (subject to the approval of the company registration authority)

2. Mode of contribution: All shareholders of Wenzhou Hongxiang contributed in cash, with a registered capital of 20.4 million yuan. Hongcheng Environmental Protection is funded by its own funds.

3. Shareholding ratio Hongcheng Environmental Protection contributed 654.38+004.04 million yuan in cash, accounting for 565.438+0% of the company's registered capital; Wenzhou Hongze contributed 9.996 million yuan in cash, accounting for 49% of the company's registered capital;

Wenzhou Binhai Park No.3 Sewage Treatment Plant (hereinafter referred to as "Binhai No.3 Plant") is an engineering project developed by Wenzhou Economic and Technological Development Zone Municipal Environmental Protection Bureau. The site is located on the north side of the intersection of Liu Jing Road and Weisan Road in Dingshan Reclamation Area. According to the plan, the total land area of the project is 2.67 hectares (40 mu), of which the reclaimed water recycling facilities land is 14 mu, and the first and second phases land is about 20.30 mu. The land for the fourth phase of the project is 5.7 mu. The total design capacity of Binhai No.3 Plant is 60,000 tons/day, including 65,438+500,000 tons/day in Phase I and 65,438+500,000 tons/day in Phase II. The treatment process adopts hydraulic clarifier and two-stage improved biological aerated filter, and the total investment in the first and second phases is estimated to be 68 million yuan.