Installation steps:
Face basin installation
1. By measuring the installation height of ceramic washbasin marked on the wall, the recommended installation height is 820mm;;
2. Put the ceramic washbasin and vertical washbasin in the installation position, and mark the horizontal position on the wall and the ground with a pen;
3, remove the washbasin and column, determine the hook installation position through measurement, and mark it on the wall with a pen;
4. Punch holes at the mark with an impact drill and install the expansion tube;
5. Install the washbasin hook;
6. Install faucets and drainage components according to the requirements and steps in the manual;
7. Install the washbasin on the hook and install the washbasin fixing piece;
8. The column is connected with the fixed part, and the contact surface between the column foot and the ground is sealed with mildew-proof silica gel.
Toilet installation
1. Before installation, the depth of the pit reserved for squatting toilets under the ground is greater than the height of the toilet, and there are tool belts, adhesive tapes and glue;
2. Insert the connecting rubber plug into the water inlet hole of the toilet and clamp it to connect the water inlet pipe;
3. Coat a layer of glass glue or putty on the edge of the squatting pan outlet and sew it;
4. Open the water inlet system and check whether the joints are leaking;
5. After checking the joints for water leakage, fill the squatting pan with filler, and then lay the floor tiles;
6. After the installation is successful, don't test the water immediately, and then test the water when the cement mortar is dry.