The qualification standards for construction drawing review agencies are stipulated. According to the different scope of business undertaken by the review agency, the review agency is required to have different qualifications.
With reference to Article 6 of the "Measures for the Review and Management of Construction Drawings and Design Documents of Housing Construction and Municipal Infrastructure Projects", review agencies are divided into two categories according to the scope of business they undertake. The first category of agencies undertakes the construction of housing construction and municipal infrastructure projects. The business scope of drawing review is not restricted; Category II institutions can undertake the construction drawing review of second-level and lower housing construction and municipal infrastructure projects.
With reference to Article 7 of the "Measures for the Review and Management of Construction Drawings and Design Documents of Housing Construction and Municipal Infrastructure Projects", the first-class review agency shall meet the following conditions:
(1) The registered capital does not exceed Less than 1 million yuan.
(2) Have a sound technical management and quality assurance system.
(3) The reviewers should have good professional ethics and have more than 15 years of required professional survey and design work experience; have presided over no less than 5 first-class or above construction projects or large-scale municipal public projects or For the survey and design of corresponding majors in Class A engineering survey projects; for majors that have implemented a professional registration system, the reviewers shall have the qualifications of a first-class registered architect, a first-class registered structural engineer, or a registered survey and design engineer. If the professional registration system has not been implemented, the reviewers shall Should have the title of senior engineer or above.
(4) Those engaged in the review of construction drawings of housing construction projects shall have no less than 6 professional reviewers for structures, and no less than 2 professional reviewers each for construction, electrical, HVAC, water supply and drainage, and surveying. ; Those engaged in the review of construction drawings of municipal infrastructure projects shall require no less than 6 professional reviewers, and other necessary supporting professional reviewers shall be no less than 2 each; those specializing in the review of survey documents, there will be many professional survey reviewers to 6 people.
(5) In principle, reviewers shall not be over 65 years old, and reviewers over 60 years old shall not exceed 1/2 of the prescribed number of reviewers for the professional category. To be responsible for reviewing the construction drawings of over-sized high-rise building projects, in addition to meeting the above conditions, there must also be no less than 3 reviewers who have presided over the professional design of over-sized high-rise building projects or construction projects over 100 meters.
With reference to Article 8 of the "Measures for the Review and Management of Construction Drawings and Design Documents of Housing Construction and Municipal Infrastructure Projects", the second-category review agency shall meet the following conditions:
(1) The registered capital does not exceed Less than 500,000 yuan;
(2) Have a sound technical management and quality assurance system.
(3) The reviewers should have good professional ethics, have more than 10 years of required professional survey and design work experience, and have presided over no less than 5 construction projects of Grade II or above or medium-sized or above municipal public projects Or the survey and design of the corresponding major for Class B or above engineering survey projects; for majors that have implemented a professional registration system, the reviewers should have the qualifications of a first-class registered architect, a first-class registered structural engineer or a registered survey and design engineer. If the professional registration system has not been implemented, The reviewers should have the professional title of engineer or above.
(4) Those engaged in the review of construction drawings of housing construction projects must have at least 2 professional reviewers; those engaged in the review of construction drawings of municipal infrastructure projects must have no less than 4 professional reviewers , other necessary supporting professional reviewers shall be no less than 2 each; if specializing in survey document review, the number of survey professional reviewers shall be no less than 4.
(5) In principle, reviewers shall not be over 65 years old, and reviewers over 60 years old shall not exceed 1/2 of the prescribed number of reviewers for the professional category.
Extended information
With reference to Article 11 of the "Construction Project Quality Management Regulations", the specific methods for reviewing construction drawing design documents shall be formulated by the construction administrative department of the State Council and other relevant departments of the State Council . Construction drawing design documents shall not be used without review and approval.
With reference to Article 5 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", the construction competent departments of the people's governments of provinces, autonomous regions, and municipalities directly under the Central Government shall follow the review agency conditions determined by the state and combine this with Depending on the scale of construction within the administrative region, a corresponding number of review agencies will be identified. The review agency is an independent legal person that is not for profit.
With reference to Article 9 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", the construction unit shall submit the construction drawings to the review agency for review.
The construction unit may independently select the review agency, but the review agency shall not have any affiliation or other interest relationship with the construction unit or survey and design enterprise of the project being reviewed.
With reference to Article 10 of the "Measures for the Review and Management of Construction Drawings and Design Documents of Housing Construction and Municipal Infrastructure Projects", the construction unit shall provide the following information to the review agency:
(1) As a survey , approval documents and attachments from relevant government departments on which the design is based;
(2) A complete set of construction drawings.
With reference to Article 11 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", the review agency shall review the following contents of the construction drawings:
(1) Whether Comply with mandatory standards for engineering construction;
(2) The safety of foundation foundation and main structure;
(3) Whether survey and design enterprises, registered practitioners and relevant personnel are in compliance with regulations The construction drawings shall be stamped with corresponding stamps and signatures;
(4) Other contents that must be reviewed under the provisions of laws, regulations and rules.
With reference to Article 12 of the "Measures for the Review and Management of Construction Drawing Design Documents for Housing Construction and Municipal Infrastructure Projects", in principle, the review of construction drawings shall not exceed the following time limits:
(1) 1 It takes 15 working days for construction projects above grade 1 and large municipal projects, and 10 working days for construction projects of grade 2 and below and medium-sized and below municipal projects.
(2) Engineering survey documents, 7 working days for Class A projects, 5 working days for Class B and below projects.
With reference to Article 13 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", after the review agency reviews the construction drawings, it shall handle them respectively according to the following circumstances:
(1) If the project passes the review, the review agency shall issue a certificate of review to the construction unit and return the complete set of construction drawings stamped by the review agency to the construction unit. The examination certificate shall be signed by the examiners of each profession, signed by the legal representative, and stamped with the official seal of the examination agency. The review agency shall report the review status to the construction competent department of the local people's government at or above the county level where the project is located within 5 working days for filing.
(2) If the review fails, the review agency shall return the construction drawings to the construction unit and explain in writing the reasons for the failure. At the same time, problems found during the review that construction units, survey and design enterprises and registered practitioners violate laws, regulations and mandatory engineering construction standards should be reported to the construction competent department of the local people's government at or above the county level where the project is located.
After the construction drawings are returned to the construction unit, the construction unit shall require the original survey and design enterprise to make modifications and submit the modified construction drawings to the original review agency for review.
With reference to Article 15 of the "Measures for the Review and Management of Construction Drawing Design Documents for Housing Construction and Municipal Infrastructure Projects", the review agency is responsible for the review of construction drawings and assumes review responsibilities.
If after the construction drawings are reviewed and passed, there are still problems that violate laws, regulations and mandatory engineering construction standards, causing losses to the construction unit, the review agency shall bear corresponding liability for compensation in accordance with the law; the construction authority shall The legal representatives and reviewers of the institution, review agency, and reviewers shall handle or punish the case in accordance with the law.
With reference to Article 22 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", if the review agency violates the provisions of these Measures and commits any of the following acts, the local people's government at or above the county level shall The construction department shall order correction and impose a fine of not less than 10,000 yuan but not more than 30,000 yuan; if the circumstances are serious, the construction department of the people's government of the province, autonomous region, or municipality directly under the Central Government shall revoke the recognition of the review agency:
(1) Exceeding Engaging in the review of construction drawings within the identified scope;
(2) Using unqualified reviewers;
(3) Failure to report violations discovered during the review process as required ;
(4) Failure to sign and seal the review certificate and construction drawings as required;
(5) Failure to conduct the review according to the prescribed review content.
With reference to Article 23 of the "Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Infrastructure Projects", if the review agency issues a false review certificate, the construction competent department of the local people's government at or above the county level shall file a 3 A fine of 10,000 yuan will be imposed, and the construction administrative department of the people's government of the province, autonomous region, or municipality directly under the Central Government shall revoke the recognition of the review agency; any illegal gains shall be confiscated.
Shou County People's Government - Measures for the Review and Management of Construction Drawings and Design Documents for Housing Construction and Municipal Facilities Projects
Youyang County People's Government - Construction Project Quality Management Regulations