1. What are the main law enforcement bases for engineering bidding activities?
"Tendering and Bidding Law of the People's Republic of China", "Construction Tendering and Bidding Measures for Engineering Construction Projects" and "Construction Enterprise Qualification Management Regulations"
2. What are the types of project contracting methods?
Open bidding, invitation to bid and direct contracting.
3. What is the definition of project contracting method?
Public bidding means that the bidder invites unspecified construction (supervision) companies to bid in the form of a bidding announcement. Invitation to bid means that the bidder invites specific construction (supervision) companies to bid in the form of a bid invitation. Direct contracting means that the contractor directly entrusts the project to a construction (supervision) enterprise with corresponding qualification level for contracting.
4. Which projects must be put to public tender?
Construction: Projects that are fully invested with state-owned funds or in which state-owned funds occupy a controlling or dominant position, and the one-time contracting cost is more than 2 million yuan. Supervision: Projects that are entirely invested with state-owned funds or in which state-owned funds occupy a controlling or dominant position, with a total project cost of more than 20 million yuan or a single supervision service contract with an estimated price of more than 500,000 yuan.
5. Which projects can be invited to bid?
Construction and supervision: Projects that are entirely invested by collective funds, invested and controlled by collective funds, or the cumulative total of collective funds exceeds 50% and state-owned funds do not dominate; projects approved by the municipal national security agency, confidentiality agency or corresponding Projects involving national security and state secrets that are not suitable for public bidding and are confirmed by military agencies in accordance with the law. Construction: All projects are invested with state-owned funds or state-owned funds occupy a controlling or dominant position. The total project cost is more than 20 million yuan, but the contracted project cost is more than 1 million yuan and less than 2 million yuan.
6. Which projects can be contracted directly?
Construction and supervision: Projects that are entirely invested by foreign investors or private investors, controlled by foreign investors or private investors, where the cumulative foreign or private investment exceeds 50% and where state-owned capital investment does not dominate. Construction: All investments are made with state-owned funds or state-owned funds occupy a controlling or dominant position. The one-time contracting cost is between 1 million yuan and less than 2 million yuan and the total project cost is less than 20 million yuan. The one-time contracting project cost is less than 1 million yuan. project. Supervision: Projects that are entirely invested with state-owned funds or where state-owned funds hold a controlling or dominant position, the total project cost is less than 20 million yuan, and the estimated price of a single supervision service contract is less than 500,000 yuan. It must go through public bidding, but the legal number of units participating in the bidding cannot be reached twice due to non-tendering responsibility.
7. Which projects can be exempted from bidding after being approved by the construction administrative department?
① A project that is resumed after construction has been suspended or postponed, and the contractor has not changed;
② A project that is self-built by a construction (supervision) enterprise for its own use, and the construction ( (Supervision) enterprise qualification level meets the project requirements; ③ For housing construction projects developed and constructed by real estate development enterprises, the enterprise has a directly controlled construction (supervision) enterprise, or the enterprise is directly controlled by a construction (supervision) enterprise, and the corresponding construction (supervision) enterprise ) The qualification level of the enterprise meets the project requirements;
④ The project under construction is an additional small-scale ancillary project or main layer addition project that is inseparable from the construction of the main project, and the contractor has not changed;
⑤ Construction projects whose main construction technology adopts specific patents or proprietary technologies;
⑥ Recognized by the emergency and disaster relief agencies established by the municipal and district governments for the purpose of fighting sudden disasters or dangerous situations, protecting Emergency and disaster relief projects that must be constructed urgently to protect the country and people from losses of life and property.
8. What are the regulations for special project contracting?
① For construction projects involving national security and secrets, the winning bidder shall be determined through public bidding among the pre-selected contractors identified by the municipal security agency as capable of undertaking confidential project tasks; for projects that are not suitable for public bidding, The winning bidder can be determined by invitation to bid.
② For emergency construction projects, the winning bidder shall be determined by drawing lots from the list of pre-selected contractors for construction projects that meet the bidding registration conditions.
③ Emergency and disaster relief construction projects shall be undertaken by the emergency and disaster relief command agency directly designating qualified contractors from the pre-selected contractor list.
9. How to identify special projects?
① Construction projects involving national security and state secrets shall be identified by the municipal national security agency, confidentiality agency or corresponding military agency in accordance with the law. If the municipal national security agency, confidentiality agency or corresponding military agency itself is a project construction unit, its superior competent authority shall conduct review and determination in accordance with the law.
② Emergency construction projects shall be reported to the municipal government office meeting for approval by the project construction unit.
③ Emergency and disaster relief construction projects shall be certified by the emergency and disaster relief command agencies established by the municipal and district governments.
10. What matters need to be reported to the construction administrative department for record in project bidding?
There are 4 items: bidding announcement (tender invitation) and bidding organization form filing, bidding document filing, and bidding report filing.
11. What are the minimum conditions required for government investment project bidding?
① The planning and project approval procedures have been completed in accordance with the regulations or the approval document on fund arrangement has been obtained from the financial department;
② If construction bidding is planned, the construction project planning permit has been obtained in accordance with the regulations Certification documents; if supervision bidding is planned, at least the construction project land planning permit certification documents have been obtained in accordance with regulations;
③ Design documents and other technical information that meet the needs of the bidding are available;
④ Have the ability to handle bidding matters on their own or have entrusted a bidding agency;
⑤ Bidding documents have been prepared;
⑥ The project expansion has been approved and construction funds have been secured.
12. What are the types of bidding organization forms?
Handle the bidding by yourself or entrust a bidding agency to do the bidding.
13. What are the requirements for handling a tender on your own?
① Have project legal person qualifications (or legal person qualifications);
② Have no less than 3 full-time personnel with registered professional qualifications for engineering construction or intermediate professional and technical titles or above, including There should be no less than 1 full-time person with registered professional qualifications as a cost engineer;
③ Have engineering bidding experience in similar engineering construction projects with a cumulative cost of more than 50 million yuan in the past five years;
④ There is a special bidding agency with no less than 5 members.
14. Under what circumstances is agency bidding required?
If the tenderer is not qualified to handle tendering matters on his own, he must entrust a tendering agency to conduct tendering. The tenderer is qualified to be a bidding agent on his own, or he can entrust a bidding agency to conduct bidding.
15. What are the qualifications for engineering bidding agencies?
The qualifications of engineering bidding agencies are divided into two levels: A and B. Project bidding agencies that have obtained Class A qualifications can undertake various project bidding agency services. Project bidding agencies that have obtained Class B (tentative) qualifications can only undertake project bidding agency business with a project investment amount (excluding land acquisition fees, major municipal supporting fees and demolition compensation fees) of less than 60 million yuan.
16. What are the categories of bidding procedures? How long does it take to complete a project tender process?
The bidding procedures are divided into general procedures, simplified procedures and special procedures according to the nature of the project. The general procedure refers to the bidding procedure in which the bid is determined directly after the bid opening without pre-qualification (applicable to the lowest price method) or the winning bidder is determined through bid evaluation. The bidding cycle generally takes 15 to 25 days. The simplified procedure refers to the bidding procedure in which the winning bidder is determined by drawing lots without prequalification. The simplified procedure is applicable to project bidding other than simple projects that can draw lots and determine the bid.
The bidding cycle generally takes 5 to 10 days. Special procedures refer to the bidding procedures that conduct pre-qualification and determine the winning bidder through bid evaluation. Special procedures apply to tenders for projects approved for prequalification. The bidding cycle generally takes 25 to 35 days. In the above-mentioned procedures, all the steps that need to be filed with the construction administrative department can be done immediately.
17. What should be at least stated in the bidding announcement (tender invitation)?
① The name and address of the tenderer;
② The content, scale and source of funds of the bidding project;
③ The implementation location and construction period of the bidding project; < /p>
④ The place and time to obtain the bidding documents or pre-qualification documents;
⑤ The fees charged for the bidding documents or pre-qualification documents;
⑥ The fees for the bidders Qualification level requirements.
(According to the provisions of the Tendering and Bidding Law) The invitation to bid shall also state the name of the invited bidder.
18. What are the requirements for pre-qualification in project bidding?
Pre-qualification is generally not allowed for project bidding. If the tenderer believes that pre-qualification is indeed necessary, it must submit an application to the municipal government office meeting for approval. For project bidding approved by the municipal government office meeting for prequalification, the prequalification activities must be conducted in the construction project transaction service center in accordance with the prescribed procedures and methods.
19. How to set bidder qualifications?
For bidding projects that are not included in the professional directory of pre-selected contractors, the bidder can generally only set bidder qualifications from two aspects: enterprise qualifications and project manager (project director) professional qualifications. For bidding projects listed in the professional directory of pre-selected contractors, the bidder can generally only set bidder qualifications from two aspects: the category and group of pre-selected contractors and the professional qualifications of the project manager (project director).
20. What are the requirements for setting bidder qualifications?
① Unreasonable conditions shall not be used to restrict or exclude potential bidders.
② Enterprise qualification level requirements can only be set according to the minimum qualifications required for bidding projects. However, for projects that adopt legal tendering by lottery, the minimum qualifications required for bidding projects can be raised by one level.
③ Project manager qualification level requirements can only be set according to the minimum qualification requirements required for bidding projects.
21. Among the bidding registration conditions, for which project bidding can the construction (supervision) experience of similar projects be set?
For construction projects with huge investment scale, particularly complex technology, and special construction requirements, such as bridges, tunnels (culverts), municipal gas pipeline networks, soft foundation treatment, high slope support, and deep foundation pits Support, large steel structures (referring to individually contracted steel structure projects that meet the first-level qualification standards for professional steel structure engineering contracting enterprises), ports, electric power, SMA asphalt concrete pavement surfaces, large public housing buildings (referring to For housing construction projects that are open to the public and have a one-time contracting cost of more than 100 million yuan or a construction area of ??more than 50,000 square meters), experience in the construction (supervision) of similar projects can be set in the bidding registration conditions. For general bidding projects that do not include similar project construction (supervision) experience in the bidding registration conditions, construction (supervision) experience in Shenzhen should be set. This experience is not limited to any project, except for those that adopt the pre-selected contractor system.
22. What are the requirements for setting up construction (supervision) experience for similar projects?
① Unreasonable conditions shall not be used to restrict or exclude potential bidders.
② The construction (supervision) experience of similar projects is limited to similar project scale, similar special structural form, and similar special construction technology to the bidding project.
③ The quantitative indicators set for the construction (supervision) experience of similar projects cannot be higher than the bidding project itself.
④ The number of projects with similar construction (supervision) experience is limited to one.
⑤ The time range of projects with similar construction (supervision) experience shall not be less than 3 years.
23. Under what circumstances can the setting of construction (supervision) experience for similar projects be reduced or cancelled?
If the number of applicants for bidding, the number of people participating in the bidding meeting, and the number of people submitting bids are less than 11, the construction (supervision) experience requirements for similar projects should be reduced until cancelled. If the tenderer believes that it is not appropriate to reduce or cancel, with the approval of the construction administrative department, no less than 5 technical experts may be randomly selected from the bid evaluation expert database to conduct demonstrations, and the opinions of the expert evaluations shall be followed. Expert demonstration activities should be conducted in the trading center.
24. What materials do applicants with construction (supervision) experience or experience in construction (supervision) of similar projects need to provide for inspection?
Tender applicants shall submit performance certification materials such as construction (supervision) contract, construction subcontract filing receipt, construction license, completion acceptance filing receipt, etc. when registering for bidding. The tenderer or the bidding agency entrusted by it shall review and confirm the performance certification materials related to construction (supervision) experience submitted by all applicants during the bidding registration period in the transaction service center. The transaction service center is responsible for providing corresponding places.
25. Can the registered capital of an enterprise be used as a condition for bidding registration?
The registered capital of the bidding applicant shall comply with the "Construction Enterprise Qualification Management Regulations", but the tenderer cannot make any requirements for the registered capital of the bidding applicant in advance in the bidding registration conditions. During the bidding process, if a bidder's bid price exceeds the limit of the project cost that the bidder can undertake according to law, his bid shall be invalidated.
26. What are the requirements for publishing a bidding announcement (tender invitation)?
① The bidding announcement (tender invitation) and bidding organization form have been filed with the construction administrative department.
② The bidding announcement (tender invitation) shall be published on the Exchange Center Information Network, and the continuous publication shall be no less than 5 working days. The tenderer may also publish it on other media at the same time, but the content shall be consistent with that published in the trading center.
27. What are the requirements for the number of applicants for public bidding projects?
The number of bidders who meet the bidding registration conditions shall not be less than 3, otherwise the tenderer shall suspend the bidding process, and at the same time adjust the contents of the bidding announcement from the following three aspects before re-issuing the bidding announcement:
① Relax bidder qualifications to the minimum requirements required for bidding projects;
② Those with similar project construction (supervision) experience should be reduced or eliminated;
③ Adopt For "the lowest reviewed bid price method without limiting the range (1-A), the lowest reviewed bid price method with limited range (1-B)", the bid evaluation method should be changed to the "lotting method"; p>
④ If the "pre-selected contractor system" is adopted, the original registration qualification conditions for projects that require Group II and Group III contractors to participate in bidding will be relaxed to allow Group I, II, and III contractors to participate in bidding; the original registration conditions Projects that require Group I, or Group I and Group II contractors to participate in bidding will be relaxed to include not only contractors in the pre-selected contractor list; the content of the bidding announcement has been adjusted in accordance with the above requirements, and the bidding announcement has been re-released for many consecutive years. After 5 working days, if the number of bidding applicants still cannot meet the corresponding requirements, the next step of the bidding process can be carried out. If the number of responding or qualified bidding applicants is less than 3, the bidding may no longer be conducted with the approval of the construction administrative department.
28. When there are more than 7 applicants that meet the bidding registration conditions, can 7 companies be randomly selected to participate in the bidding?
When there are more than 7 applicants who meet the bidding registration conditions, 7 companies can be randomly selected to participate in the bidding.
29. What are the requirements for the number of applicants invited to bid for projects?
The tenderer shall invite more than three bidders who meet the qualifications required for the bidding project to participate. The following will be modified later:
30. What does the bidding document include? Do they all need to be registered?
The bidding documents include the main body of the bidding document, bill of quantities, supplementary clauses, addendum, Q&A minutes and other components, all of which must be reported to the construction administrative department for record.
31. For supervision bidding, what are the requirements for the number of applicants who meet the bidding registration conditions?
The number of bidders who meet the bidding registration conditions for the supervision of bidding shall also not be less than 3, otherwise the tenderer shall relax the bidding registration conditions.
32. What bidding evaluation methods can be chosen for different types of project bidding?
(1) In supervision bidding, the winning bidder is generally determined by drawing lots; however, if the project construction bidding is approved by the municipal government office meeting and the "comprehensive evaluation method" can be used to evaluate and determine the bid, the supervision Bidding can also determine the winning bidder through bid evaluation.
(2) For construction bidding, different bid evaluation and bidding methods are used according to the classification of project types. The specific classification standards and requirements are shown in the table below and the following instructions: Note:
① If the lowest price winning bid method is adopted, a fixed-price contract shall be adopted.
② If the lottery method is used to determine the bid, the winning price shall refer to the average decline rate of the winning bid price of similar bidding projects in our city in the previous year relative to the approved bid base, and shall be determined based on the specific conditions of the bidding project. The lottery activity shall be conducted publicly at the construction project transaction service center.
③ Method 1-A, that is, the lowest bid price method after review - without limiting the range; Method 1-B, that is, the lowest bid price method after review - with a limited range.
33. What are the regulations for preparing bidding documents for project construction bidding?
For construction bidding using different bid evaluation and determination methods, the bidding documents shall be prepared in accordance with the following provisions:
(1) If the lowest price legal bid is adopted, the bidder does not need to prepare a technical bid. Whether the bidder prepares a commercial bid shall be determined by the tenderer in the bidding document. However, regardless of whether the bidder is required to prepare a commercial bid, the bidder must submit a bid letter and a bid guarantee to the tenderer.
(2) If the 1-A method, 1-B method or the quadratic average method of the reviewed lowest bid price is used, whether the bidder prepares a technical bid shall be determined by the tenderer in the bidding document.
(3) If the comprehensive evaluation method is adopted, the bidder shall prepare the bidding documents (including commercial bids and technical bids) according to the normal procedures according to the requirements of the bidding documents.
34. Under what circumstances will a bid document be considered invalid?
(1) The bid documents are delivered after the deadline or fail to arrive at the designated location;
(2) The bidder fails to submit the originals of relevant certificates for review when opening bids as required in the bidding documents;
(3) The bidding documents are not sealed, marked and stamped with the official seal of the bidder in accordance with the provisions of the bidding documents (note: different bid evaluation and bidding methods have different requirements);
(4) The construction period promised in the bidding document exceeds the construction period requirement in the bidding document;
(5) There is no original bid guarantee or original certificate of receipt of the bid deposit issued by the tenderer in the sealed bag of the bid letter , or the content of the bid guarantee does not meet the substantive requirements of the bidding documents;
(6) The bidding documents are not stamped with the seal of the bidder in accordance with the format requirements stipulated in the bidding documents, or the bid documents are not stamped with the seal of the bidder in accordance with the format requirements of the bidding documents, or the bid documents are not stamped with the seal of the bidder or by the legal representative or The authorized agent signs (seals), or the authorized agent signs (seals) but does not provide the original "Power of Attorney for Signing Bid Documents" along with the bidding documents;
(7) Bidding documents The bill of quantities in the commercial bid is not signed and approved by the cost engineer (or cost clerk) and stamped with a professional seal;
(8) The bid letter (or bid commitment letter) shall be in accordance with the provisions of the bidding documents. It should be filled in but has not been filled in;
(9) The bidders form a consortium to bid, but the bidding documents do not include the bidding agreement signed by all parties in the consortium as required; (10) Bidding documents It is required to submit electronic documents of bidding documents, but they are not submitted or the submitted electronic documents do not meet the requirements. 35. Under what circumstances will a bidder’s bid be invalidated?
(1) The bidder bids in the name of others or is suspected of colluding in bidding or committing fraudulent bidding as follows:
① The members of the project management team specified in the bidding document are not related to the bidding project The relevant persons listed in the bidding documents of other bidders include the same person;
② The cost engineer who signed and stamped the commercial bid document in the bidding document is the same as the bidding document of other bidders;< /p>
(2) The bid price is higher than the published minimum bid price or the maximum price limit of the bid price;
(3) The bidder refuses to clarify, explain, make corrections to the bid documents as required, Or after the bid evaluation committee corrects the calculation errors in the bid documents in accordance with the provisions of the bidding documents, the bidder does not accept the revised bid quotation;
(4) There are obvious inconsistencies in the bidding documents that do not meet the technical specifications, The contents of technical standards;
(5) The bidding documents are accompanied by conditions that are unacceptable to the tenderer;
36. Who are the members of the bid evaluation committee? Can the tenderer appoint representatives to participate in the bid evaluation committee?
The bid evaluation committee shall be composed of intermediate and above professional and technical personnel related to the type and requirements of the bidding project. The tenderer may appoint representatives to participate in the bid evaluation committee.
37. What information should the tenderer provide to the bid evaluation committee? The tenderer shall provide relevant information to the bid evaluation committee for bid evaluation:
(1) Recorded bidding documents, including addendum documents, minutes of Q&A meetings, bill of quantities, etc.;
(2) Main construction drawings, geological exploration reports and other engineering technical materials;
(3) Written introduction of project overview and key points of bid evaluation not included in the bidding documents. Including project scale, structural type, project characteristics, technical requirements, construction key points and difficulties, new methods, new processes and new materials used in construction, clauses with significant changes in bidding documents and model texts, and bid evaluation methods, etc.;
(4) Evaluation form and other necessary information for bid evaluation.
38. What conditions should a bid evaluation expert have?
(1) Possess intermediate or senior professional titles in engineering technology or engineering economics, or hold professional qualification certificates for registered architects, structural engineers, cost engineers, and supervision engineers issued by relevant national departments, or have equivalent professional qualifications Qualification certificate;
(2) Familiar with laws, regulations, rules, technical specifications and standards related to project construction, familiar with project bid evaluation business, and capable of performing bid evaluation work;
(3) Adhere to principles, act impartially, have a decent style, be honest and self-disciplined, have no bad records, and enthusiastically serve the bid evaluation work; (4) Observe disciplines, obey management, and consciously accept supervision.
39. How to hire bid evaluation experts?
(1) Self-recommendation or recommendation from the unit;
(2) The construction administrative department shall conduct qualification review, organize training and assessment;
(3) Experts The assessment and supervision committee puts forward employment opinions;
(4) The construction administrative department issues a letter of appointment for experts and enters them into the bid evaluation expert database.
40. What types of construction project guarantees are there? Construction project guarantees include bidder bid guarantees, contractor performance guarantees and owner payment guarantees.
41. How many days before publishing a bidding announcement or issuing a bidding invitation, the tenderer should file a record with the construction administrative department or the relevant administrative department?
The days before the tender notice is published or the tender invitation is issued.
If public bidding is adopted, the tenderer shall publish a bidding announcement on the Exchange Center Information Network. How many consecutive working days should the bidding announcement be published?
5 working days.
42. If invitation bidding is adopted, how many qualified construction companies should the bidder issue invitations to bid and at the same time publish the bidding information on the Trade Center Information Network? 3 or more.
43. Once the bidding documents are issued, the tenderer shall not change the contents or add additional conditions without authorization; if changes are really necessary, all bidders shall be notified in writing a number of days before the bidding deadline, and shall be reported to the Construction Administration at the same time. The competent department or relevant administrative department shall file the record. 15 days ago.
44. How many days should generally not be less from the date the bidding documents are issued to the deadline for submission of bid documents?
On the 20th.
45. The bid guarantee can be in the form of a bid guarantee or a bid deposit. Generally, the guarantee amount shall not exceed the total bid price. The maximum limit cannot be more than RMB 10,000?
2%; 800,000 yuan.
46. What are the forms of performance guarantees? Guaranteed by a bank or a professional guarantee company.
47. How many base bids can be prepared for a bidding project? Only one bid base can be prepared.
48. What is the procedure for opening bids? The bid opening shall be carried out in accordance with the following provisions: the bidder or its elected representative shall inspect the sealing condition of the bid documents. After confirmation, the tenderer will open the envelope in public and read out the name of the bidder, the bid price and other main contents of the bid document. All bid documents received by the tenderer before the deadline for submission of bid documents shall be opened and read out in public during the bid opening. The tenderer shall record the bid opening process and keep it on file for future reference.
49. Who is responsible for the bid evaluation work?
The bid evaluation work shall be carried out by the bid evaluation committee established by the tenderer in accordance with the law.
50. What main contents should the bid evaluation report include?
The bid evaluation report should include the following main contents and be signed by all members of the bid evaluation committee:
(1) Bid evaluation status. Including the formation process of the bid evaluation committee, the list of members, and the comprehensive review opinions of the bid evaluation committee on the bid documents;
(2) Bid evaluation results. Including the ranking of bidders, the recommended winning candidates or the winning bidder determined according to the authorization of the tenderer; (3) Original bid evaluation materials and other attachments of each member of the bid evaluation committee during the bid evaluation process.
51. For projects that use bid evaluation methods, how will the tenderer determine the winning bidder?
The tenderer determines the winning bidder based on the written bid evaluation report submitted by the bid evaluation committee and the recommended winning candidates.
52. How many days before the bid validity deadline should the tenderer determine the winning bidder?
At the latest thirty working days before the end of the bid validity period.
53. The tenderer shall submit a written report on the bidding situation to the construction administrative department or the relevant administrative department within a certain number of days from the date of determining the successful bidder, and at the same time, the winning bid result shall be announced in the trading center for a certain number of working days. ?
7 days; 3 working days.
54. Under what circumstances should the tenderer return the bidder's bid security within 7 days?
If any of the following circumstances occurs, the tenderer shall return the bidder's bid security within 7 days:
(1) The bid winning notice is issued;
( 2) The bid guarantee of the winning bidder is after signing the project contract contract;
(3) The bidding process is suspended by the tenderer for legitimate reasons;
(4) The bidding fails and needs to be reorganized Bidding;
(5) The bid validity period expires but the bidder does not agree to extend it.
55. What content should be included in the preparation of construction bidding documents?
Construction bidding documents shall include the following main contents:
(1) Bidding instructions, including project overview, bidding scope, qualification review conditions, project fund sources or implementation status, and division of bid sections , construction period requirements, quality standards, on-site inspection and Q&A arrangements, requirements for preparation, submission, modification, and withdrawal of bid documents, bid quotation requirements, payment method of project payment, bid validity period, time and place of bid opening, bid evaluation methods and standards, Bidding guarantee and performance guarantee requirements, contract award conditions, etc.;
(2) Technical specification requirements and design documents and construction drawing catalog of bidding projects;
(3) Bill of quantities ( (Except for special projects where a bill of quantities cannot be provided);
(4) Description of the bill of quantities price and the tabular format of the price (except for non-bill of quantities prices)
(5) The format and appendices of the bid letter and bid quotation form;
(6) The format and main terms of the contract to be signed;
(7) Other materials required for bidding.
56. What content should be included in the preparation of supervision bidding documents? Supervision bidding documents shall include the following main contents:
(1) Bidding instructions;
(2) Comprehensive description of the project: including project overview, site conditions, surrounding environment, geological conditions, etc.;
(3) Scope of supervision bidding, including supervision project scope and supervision work content;
(4) Supervision fee valuation, payment and settlement methods;
( 5) Supervision period and supervision work quality requirements;
(6) Qualification requirements for chief supervisory engineers and supervision agency members;
(7) Bid closing, bid opening, and bid evaluation time;
(8) Bid evaluation methods and standards;
(9) Compliance requirements for bids;
(10) Main contract terms;
p>
(11) Design documents;
(12) Other contents.
57. Who will preside over the bid opening, bid evaluation and bid determination of the supervision project?
Hosted by the tenderer or agent.
58. When a bidder encounters those circumstances, the tenderer has the right to cancel his bid or winning bid qualification, and confiscate his bid guarantee. If the loss caused to the tenderer exceeds the amount of the bid guarantee, the excess amount may be levied. Demand compensation?
If a bidder has any of the following circumstances, the tenderer has the right to cancel its bid or winning qualification, and confiscate its bid guarantee. If the loss caused to the tenderer exceeds the amount of the bid guarantee, the tenderer may claim for the excess amount. compensation.
(1) Withdraw the bidding documents within the validity period of the bid;
(2) Refuse to sign a contract with the tenderer after winning the bid;
(3) Failure to do so after winning the bid Submit a performance bond.
59. What should be stated in the bidding announcement or bidding invitation for supervision bidding?
The bidding announcement or bidding invitation for supervision bidding shall state the name and address of the bidder, the basic requirements for the bidding project, the qualification requirements of the bidder, and the method for obtaining bidding documents.
For more information about engineering/service/purchasing tender document writing and production to improve the bid winning rate, you can click on the official website customer service at the bottom for free consultation: /#/?source=bdzd