According to the Standard Provisions on the Bidding Scope and Scale of Engineering Construction Projects, if the estimated price of a single project is more than 2 million yuan, it must be publicly invited.
According to the provisions of the Law on Tendering and Bidding, as long as it is an infrastructure project related to public interests and public safety, and a public utility project related to public interests and public safety, regardless of the amount, bidding must be conducted.
Subcontracting the project again depends on whether it exceeds the standard limit.
Article 29 of the Regulations for the Implementation of the Bidding Law stipulates that a tenderer may, in accordance with the law, conduct general contracting bidding for projects and all or part of goods and services related to project construction. Projects, goods and services that are included in the scope of general contracting in the form of temporary evaluation belong to the scope of projects that must be subject to tender according to law, and meet the scale standards stipulated by the state, they shall be subject to tender according to law.
20 15. 12. 10
Question 2: Does professional subcontracting require bidding? Bidding must be invited for the procurement of professional projects and equipment that meet the limits stipulated in the Bidding Law. If it is not convenient for public bidding, it may be invited for bidding after approval by the relevant departments.
In some cases, for example, because the project technology is complex or has special requirements, involving patent protection, limited by natural resources or environment, it is difficult to determine new technologies or technical specifications in advance, and the number of qualified bidders to choose from is limited, so it is not suitable or feasible to conduct public bidding. In this case, the tenderer may choose another bidding method stipulated in Article 10 of the Bidding Law-inviting bidding.
Generally speaking, the general contractor must meet the qualification conditions. If a unit does not have one or several professional qualifications, it can be solved by allowing the consortium to bid and subcontract, or it is clearly listed in the tender announcement that in addition to the general contracting qualification, it must also meet XXX's professional qualifications.
As far as the owner is concerned, there is no legal requirement for bidding when a qualified general contractor subcontracts. As long as the subcontractor's qualification meets the professional qualification requirements and the owner's approval.
The brand library established by your company can be regarded as a qualified supplier in the usual sense. You can achieve your goal by skillfully handling the contents of the tender announcement and auditing subcontractors.
Question 3: Do subcontracted projects have to be tendered according to law? I contracted the 1 project of IFAD. At that time, a lump sum contract was signed and the project was invited for bidding. At the same time, the bidding documents and drawings were provided, and our construction party compiled the bidding price according to the bidding contents and construction drawings, and finally won the bid. 1, I want to ask the audit unit to deduct my engineering quantity according to the physical length measured on site when I bid (because the specific physical length is not given in the bidding drawings, it is only in the bidding quotation), right? When bidding, the physical length is the same as the measurement result. Should I own it all at the bid price? If the physical length of the actual construction is the same as that measured by the audit now, but it is more than that of the bidding at that time, should Party A give it to me? 2. There was no dredging project in the tender offer at that time, but it did exist in the actual construction. Will Party A give me this fee? Please kindly advise! thank you
Question 4: Does subcontracting have to be tendered? Not necessarily, but the conditions required for subcontracting must be stated in the general tender, such as subcontracting to people with corresponding qualifications and subcontracting non-principal projects with the consent of the owner.
Question 5: Does subcontracting require public bidding? 5 points is unnecessary, as long as you reach an agreement with the general contractor to sign the contract. As for whether to invite public bidding or not, it depends on the general contractor himself, and there are enough trustworthy partners to complete the project with good quality and quantity.
Question 6: Is it necessary to bid for the subcontracting of construction projects? If your construction company is not a wholly-owned company, as long as it is a state-owned enterprise, joint-stock company and other companies, the bidding law stipulates that all subcontracted projects above 500,000 yuan must be tendered.
Question 7: Does subcontracting require bidding? "Standard Provisions on the Scope and Scale of Bidding for Construction Projects" "Article 7 All kinds of construction projects within the scope specified in Articles 2 to 6 of these Provisions, including engineering survey, design, construction, supervision and procurement of important equipment and materials related to engineering construction, must be subject to bidding if they meet one of the following standards:
(a) the estimated price of a single construction contract is more than 2 million yuan;
(two) the procurement of important equipment, materials and other goods, the estimated price of a single contract is more than 6,543,800 yuan;
(three) the estimated price of a single contract for the procurement of services such as survey, design and supervision is more than 500,000 yuan; "
Labor subcontracting is a kind of single construction contract, and it is necessary to determine whether to invite tenders according to the above provisions.
Question 8: Does the general contracting of state-owned investment projects require open tendering and subcontracting? All professional projects and equipment procurement that meet the limits stipulated in the Bidding Law shall be subject to tender. If it is not convenient for public bidding, it may be invited for bidding after approval by the relevant department.
In some cases, for example, because the project technology is complex or has special requirements, involving patent protection, limited by natural resources or environment, it is difficult to determine new technologies or technical specifications in advance, and the number of qualified bidders to choose from is limited, so it is not suitable or feasible to conduct public bidding. In this case, the tenderer may choose another bidding method stipulated in Article 10 of the Bidding Law-inviting bidding.
Generally speaking, the general contractor must be qualified. If a unit does not have one or several professional qualifications, it can be solved by allowing the consortium to bid and subcontract, or it is clearly listed in the tender announcement that in addition to the general contracting qualification, it must also meet XXX's professional qualifications.
As far as the owner is concerned, there is no legal requirement for bidding when a qualified general contractor subcontracts. As long as the subcontractor's qualification meets the professional qualification requirements and the owner's approval.
The brand library established by your company can be regarded as a qualified supplier in the usual sense. You can achieve your goal by skillfully handling the contents of the tender announcement and auditing subcontractors.
Question: Does the owner of BOT project have to invite public bidding when awarding contracts to subcontractors such as engineering and design? Does the owner of BOT project who has obtained the franchise need to invite public bidding when choosing the civil engineering or installation contractor during the project implementation?
A: It depends on whether the local development and reform department recognizes the bidding method of this project. The approval of bidding methods can be divided into open bidding and invitation bidding. If it is a confidential project stipulated by the national bidding law, the project is particularly complicated, or there are some special circumstances that do not require bidding.
* * * When examining and approving franchise rights, can all or part of subcontractors be required to choose by bidding? BOT owners have relevant qualifications in engineering construction, can they construct by themselves?
A: According to the regulations of various provinces, contractors in Hunan Province are required to invite tenders. Whether the bot owner has the engineering construction qualification is decided by the local * * * department. You can talk, but you can't talk.
Question 10: Does the subcontracting of non-principal building projects require bidding? It should be decided by the contractor according to the size of the project and the requirements of the local construction administrative department.