Precautions for installing copper-aluminum composite radiators
There are many types of radiators, including different materials and shapes, vertical, horizontal, sheet, tubular, and water inlet and outlet methods. They are also different. There are top in and bottom out, side in and out, bottom in and bottom out, and bottom in and bottom out. However, different ways of water in and out have different requirements for radiator installation. Let’s take a look at the editor of Ruihuat. Various radiator installation methods compiled.
1. Installation and storage method of steel finned tube convection radiator (vertical bottom-in and bottom-out type)
1. The radiator should be handled with care during transportation , to avoid damage, pay special attention to protecting the mask from scratches. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.7 meters, and the bottom should be stored with a height of 20cm.
2. There are two types of installation methods for vertical radiators: bottom in and bottom out and top in and top out.
3. Before installing the radiator, the inlet protection material should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened, and the mask should be 5cm away from the ground.
4. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
5. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
2. Installation and storage method of steel finned tube convection radiator (side-in and side-out type)
1. The radiator should be handled with care during transportation to avoid Cause damage, pay special attention to protect the mask from scratches. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.7 meters, and the bottom should be stored with a height of 20cm.
2. Side-entry radiators are divided into three types: same-side connection, opposite-side connection and horizontal series connection.
3. Before installing the radiator, the entrance and exit protection materials should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened, and the mask should be 15cm away from the ground.
4. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
5. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
3. Installation and storage method of copper tube and aluminum radiator (vertical bottom-in-top-out type)
1. The radiator should be handled with care during transportation to avoid Cause damage, pay special attention to protect the mask from scratches. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. There are two types of installation methods for vertical radiators: bottom in and bottom out and top in and top out.
3. Before installing the vertical radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened, and the mask should be 5cm away from the ground.
4. After the radiator core is installed and before the mask is hung, the fins may fall due to impact. Please pay attention to protection; if the fins fall, please use needle-nose pliers to repair them.
5. The radiator threads are manufactured strictly in accordance with the standards of the Ministry of Construction J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
6. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
IV. Installation and storage method of copper tube and aluminum radiator (side in and side out)
1. The radiator should be handled with care during transportation to avoid damage. , pay special attention to protecting the mask from scratches. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. Side-entry radiators are divided into three types: same-side connection, opposite-side connection and horizontal series connection.
3. Before installing the radiator, the entrance and exit protection materials should be removed, the pendant should be installed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened, and the mask should be 15cm away from the ground.
4. After the radiator core is installed and before the mask is hung, the fins may fall due to impact. Please pay attention to protection; if the fins fall, please use needle-nose pliers to repair them.
5. The radiator threads are manufactured strictly in accordance with the standards of the Ministry of Construction J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
6. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
5. Installation and storage methods of copper-aluminum composite radiators (vertical bottom-entry type and side-entry type)
1. The radiator should be handled with care during transportation. to avoid damage, and pay special attention to protecting the sprayed surface from being scratched. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. The installation method of the copper-aluminum composite radiator can be bottom-in and bottom-out type or side-in and side-out type according to the design requirements.
3. Before installing the radiator, the inlet and outlet protection should be removed, and the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened. The radiator should be 25cm away from the ground.
4. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
5. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
6. Installation and storage methods of steel-aluminum composite radiators (vertical bottom-entry type and side-entry type)
1. The radiator should be handled with care during transportation. Put it down to avoid damage, and pay special attention to protecting the sprayed surface from being scratched. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. The installation method of steel-aluminum composite radiator can be made into bottom-in and bottom-out type or side-in and side-out type according to the design requirements.
3. Before installing the radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened. The radiator should be 25cm away from the ground.
4. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
5. During system experiment and operation, please note that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
7. Installation and storage methods of steel column radiators
1. The radiators should be handled with care during transportation to avoid damage, and special attention should be paid to protecting the sprayed surface. Got scratched. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. The installation methods of steel column radiators are divided into two types: hanging installation and floor installation.
3. The radiator threads are manufactured strictly in accordance with the standards of the Ministry of Construction J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
4. For system testing and operation, please note that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
8. Installation and storage methods of bathroom radiators
1. The radiator should be handled with care during transportation to avoid damage. Pay special attention to protecting the sprayed surface from scratches. . Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. Before installing the radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened.
3. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
4. For system testing and operation, please note that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
9. Installation and storage methods of steel flat tube radiators
1. The radiator should be handled with care during transportation to avoid damage, and special attention should be paid to protecting the sprayed surface. Got scratched. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. Before installing the radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened.
3. The radiator threads are manufactured strictly in accordance with the Ministry of Construction standard J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
4. For system testing and operation, please note that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
10. Installation and storage method of steel string radiator (closed type) radiator
1. The radiator should be handled with care during transportation to avoid damage. Pay special attention to Protect the sprayed surface from scratches. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. Before installing the radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened.
3. The radiator threads are manufactured strictly in accordance with the standards of the Ministry of Construction J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
4. For system testing and operation, please be careful that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.
11. Installation and storage methods of steel arc tube radiators
1. The radiator should be handled with care during transportation to avoid damage, and special attention should be paid to protecting the sprayed surface Not scratched. Radiators should be stored in a ventilated and dry warehouse and classified according to model and size. The height should not exceed 1.5 meters, and the bottom should be stored with a height of 20cm.
2. Before installing the radiator, the inlet and outlet protection should be removed, the pendant should be placed according to the position of the fixing hole, and then the radiator should be hung, adjusted and tightened.
3. The radiator threads are manufactured strictly in accordance with the standards of the Ministry of Construction J/T6-1999, and generally use conical pipe threads or cylindrical pipe threads.
4. For system testing and operation, please note that the hot water does not exceed the rated working pressure value. The steam should not exceed 0.3MPA (gauge pressure), and an automatic pressure reducing valve should be installed.