Operation steps of epoxy floor
Preparatory work/about to start work
1. floor cleaning: before construction, the floor needs to be cleaned to remove impurities such as oil and dust.
2. Foundation treatment: For the old ground, foundation treatment is needed, such as polishing, repairing and joint filling.
3. Environmental requirements: the construction environment needs to be kept dry, well ventilated and at a suitable temperature.
construction sequence
1. Primer painting: Paint the primer on the ground and paint it evenly with a roller to ensure the uniform thickness of the primer.
2. Intermediate coating: After the primer is dried, the intermediate coating should be evenly brushed to ensure the uniform thickness of the intermediate coating.
3. Mortar spreading: After the intermediate coating is dried, spread the mortar, and spread the mortar evenly on the ground with a spatula.
4. Paint the color paste: After the mortar is dried, paint the color paste evenly to ensure the uniform thickness of the color paste.
5. Cover flour brush: After the color paste is dried, the cover surface should be painted evenly to ensure the uniform thickness of the cover surface.
maintain
1. The epoxy floor needs to be cleaned regularly, and can be cleaned with clean water or neutral detergent.
2. Avoid squeezing and scraping heavy objects, and avoid using acidic or alkaline cleaners.
3. If there is any local damage, it should be repaired in time.