How to construct the electrical installation project?

The following is the related contents about the construction method of electrical installation project brought by Zhong Da Consulting Company for your reference.

1. Construction procedure of electrical installation project

Civil structure construction stage: welding grounding grid, lightning protection downlead, reserved holes and embedded parts, embedded pipelines and boxes are fixed in place.

Civil decoration stage: lack of embedded pipes, embedded parts, maintenance boxes, supports, installation of trough plates, wiring, cable laying and testing. As well as distribution cabinet in place, distribution box installation, various lamps and lanterns, switch socket installation, wiring and all power equipment wiring, lighting system debugging, equipment debugging and joint debugging.

The whole construction process is divided into two stages, the main body coordination and installation stage.

2. Steel pipe laying and reservation

According to the design drawings, prefabricate steel pipes with a certain size, and set the threads with a set of silk machines to make the threads clean and clear. The steel pipe is bent by cold simmering, and there can be no wrinkles, holes and cracks at the bend to meet the requirements of bending radius.

Before embedding the pipeline, prefabricate the length of steel pipe according to the drawing, and cooperate immediately once the civil engineering conditions are met. If the length of the prefabricated fixed-length steel pipe is insufficient or slightly longer during the matching process, it will be supplemented by appropriate movable joints (prefabricated in advance).

According to the requirements of design drawings, determine the box, box axis position, based on the civil pop-up 50 lines, hang the line for leveling, find the main line drop, mark the actual size position of the box, box, understand the ground structure of each room (hall), and leave a margin, so that the box, box cover, bottom edge and final height from the ground meet the specification requirements.

Wires and pipelines buried in dusty and humid places should be sealed, and the joint between nozzle and pipeline should be sealed. Buried wires and pipelines should not pass through basic equipment. When they must pass through the foundation of the building, they must be protected with protective pipes. Compensation measures should be taken when crossing the expansion joints of buildings.

3. Cable laying

(1) Before laying the cable, carefully check whether the model, specification and design of the cable are consistent. The appearance of the cable should be intact and the insulation is good. If necessary, make an ultra-wet judgment. Directly buried cables shall be tested and qualified before use.

(2) The cable shall be tightly sealed, and insulation test shall be conducted as required; AC withstand voltage and DC leakage test shall be conducted for cables above 6KW; For cables below 1KW, use megger to test the insulation resistance between lines and between lines and ground, and make records.

(3) When laying, there should be no crossing, cables should be neatly arranged and fixed, and fashion signs should be set. There should be obvious point marks or firm marks along the directly buried cables and their joints. High and low voltage power cables and high and low voltage control cables should be configured in layers in order, generally from top to bottom. If the cable and the control cable are laid on the same side bracket, the power cable should be placed on the control cable. The control cable should not be more than one layer on the ordinary bracket; There should be no more than three floors on the bridge. Ac three-core power cable should not be more than one layer on ordinary supports and hangers; The bridge should not exceed the second floor.

(4) Cable terminal heads and intermediate joints shall be made by trained personnel who are familiar with the process; In the production process, we must strictly abide by the production process regulations; When making cable heads outdoors, it should be done under good weather conditions, and measures should be taken to prevent dust and foreign dirt.

The above construction methods of electrical installation engineering are collected and sorted by Zhong Da Consulting Company. For more information about "Construction Method of Electrical Installation Project", please visit the dynamic column of Zhong Da Consulting Industry. For information about winning the bid, industrial and commercial information, the honor and qualification of the construction engineer under construction and the national construction enterprise, you can log in to the "Easy Winning Bid" Zhong Da Consulting & Construction link, or follow the official account of WeChat, and Zhong Da will consult the official website of WeChat.