The construction unit shall, within 3 months after the completion and acceptance of the project, submit a set of construction project files that meet the requirements to the urban construction archive
The construction unit shall, within 3 months after the completion and acceptance of the project, submit a set of construction project files that meet the requirements to the urban construction archives.
These Provisions shall be adjusted according to the existing laws, regulations and norms. At present, it is not said that the files should be submitted within 3 months after the completion acceptance. However, the project files need to be accepted at the time of joint acceptance, that is, the pre-acceptance of the previous files, and the handed-over files need to be handed over before the completion acceptance and filing. Completion acceptance filing shall be filed within 15 days from the date of completion acceptance. So now the requirements are more stringent. After the completion acceptance is passed, the files need to be handed over and filed.