Implementation plan for publicity of demolition work 1:
Airport Avenue and Xinhe Road are the main roads of Airport Industrial Park in Jingwei New District of Xianyang City. The construction of this project plays a very important role in further improving the infrastructure of the airport industrial park and broadening the urban framework. In order to ensure the smooth progress of the project construction, this scheme is specially formulated.
First, the basic situation of roads
Airport Avenue starts from Dazhai in Zhouling Town in the west and ends at Song Xian Road in the east, with a total length of 4.8 kilometers. This project starts from Yingbin Avenue in the west and ends at Song Xian Road in the east, with a total length of 3.3 kilometers. It is a third-class urban trunk road with a red line of 50 meters and asphalt concrete pavement, covering an area of 247.5 mu. Xinhe Road starts from Airport Avenue in the south and reaches Airport Industrial Park Planning Road in the north, with a total length of 400 meters. It is a third-class urban trunk road with a red line of 40 meters and asphalt concrete pavement, covering an area of 24 mu.
Second, organization.
In order to ensure the smooth progress of land acquisition and demolition of Airport Avenue and Xinhe Road, a leading group for land acquisition and demolition was established.
Team leader: Cheng Guangqian, member of the Standing Committee of the District Party Committee and deputy head of the district.
Rui, Deputy Director of Yingjing New District Development and Construction Management Committee
Member: Zhang Ke, assistant to the district head and director of Jingwei New District Development Service Center.
Deputy Director of Ji District Government Office
Director of Dongqi District Land Branch Bureau
Director of Yaoxichang District Bureau for Letters and Calls
Deputy Director of Liwan District Public Security Bureau
Mayor of Zhouling Town, Gao Yu
There is an office under the leading group, which is located in the Development and Construction Management Committee of Airport Industrial Park in Jingwei New District. The director is concurrently appointed by Comrade Xi Ruiying, who is mainly responsible for the organization, coordination and daily affairs of land acquisition and demolition of Airport Avenue and Xinhe Road.
The leading group consists of two working groups:
1. Working Group on Land Requisition and Demolition: Team leader Dong Qi, deputy team leader Gao Yu, members from the Airport Industrial Park Management Committee of Jingwei New District, Land and Resources Branch and Zhouling Town Government. Mainly responsible for the inventory and measurement of attachments within the scope of land acquisition and demolition, as well as the compensation of demolition objects such as fruit trees and buildings (structures) during land acquisition.
2. Environmental Protection Working Group: Gao Yu, the group leader, and Wei Li, the deputy group leader, with members from the District Public Security Bureau, the Bureau for Letters and Calls, Zhouling Town and the District Development Service Center. Mainly responsible for land acquisition, demolition and road construction in the process of security work; Responsible for handling emergencies and cracking down on illegal acts that unreasonably obstruct and destroy land acquisition and demolition work according to law; Responsible for the investigation and settlement of various contradictions in the process of land acquisition, demolition and road construction.
Three. Responsibilities of all relevant units:
(1) jingwei new area airport industrial park development and construction management committee.
1, responsible for the approval and disbursement of all compensation fees for attachments, land compensation fees and other compensation fees within the scope of land acquisition and demolition;
2, responsible for coordinating the District Bureau of Land and Resources to complete the land acquisition and demolition procedures;
3. Responsible for urging Zhou Ling Town to complete the payment, settlement and land delivery of compensation fees for ground attachments;
4, responsible for urging to solve various problems in land acquisition, demolition and road construction, to ensure the progress of the project.
(2) District Land and Resources Branch
1, responsible for land acquisition and demolition procedures;
2, responsible for the interpretation and publicity of compensation documents for land acquisition and demolition;
3, responsible for the ground attachment inventory and attachment compensation standards;
4. The filter cloth of the filter press is responsible for accounting the compensation expenses for attachments and land expenses within the scope of land acquisition;
5. Be responsible for the location and distribution of the villages to be demolished within the scope of land acquisition;
6, responsible for road red line measurement, demarcation and surveying and mapping results.
(3) District Public Security Bureau
Responsible for land requisition, demolition and road construction, and solve all kinds of problems and contradictions in time.
(4) District Bureau for Letters and Calls
Responsible for the reception of letters and visits and the handling of letters and visits in land acquisition, demolition and road construction.
(5) Zhouling Town
1, responsible for the publicity and education of people in villages within the scope of land acquisition and demolition;
2, responsible for the payment of attachments within the scope of land acquisition and demolition, clearing the table and handing over the land;
3. Cooperate with the District Bureau of Land and Resources to complete the inventory of attachments within the scope of land acquisition and demolition and the site selection and resettlement of the demolished people.
Four. work arrangement
(1) Publicity and mobilization stage (February 10 to February 15)
Zhouling Town and relevant departments should actively and deeply publicize and mobilize villages and groups within the scope of land acquisition, promptly publicize the national land acquisition compensation policies and regulations to households and people, earnestly do a good job in publicity and education, persuasion and explanation of the masses, and actively strive for their understanding and support.
(2) The stage of counting votes and awarding prizes (from 12 to 15+08+02)
All working groups of filter cloth should strictly follow the requirements of documents, carefully check and check, use a ruler and a standard, actively communicate with the masses, and sign for approval after obtaining consent. After the completion of the inventory, timely summary, liquidation, and do a good job of the masses to pay.
(3) Land requisition and demolition stage (18 February 65438+March 3, 20051)
For the people who have paid the fees, Zhouling Town should actively mobilize the removal of attachments. Reward those who have been demolished within the prescribed time limit; For those who refuse to be demolished, we should organize forces to enforce them and ensure that the land acquisition and demolition work is completed on schedule.
Verb (abbreviation for verb) job requirements
First, we must strengthen organizational leadership. Airport Avenue and Xinhe Road are the key projects determined by the city and district this year. The construction time of this project is tight and the task is heavy. Zhouling Town and relevant departments should attach great importance to this work and put it on the important agenda as an important work. ? Number one? It is necessary to personally take overall responsibility and take charge of the leadership. It is necessary to strictly follow the requirements of resettlement work, make careful arrangements, designate special personnel to be responsible, and check the whole process to ensure that all work is carried out in a solid and orderly manner.
Second, we must widely publicize and mobilize. Zhouling Town and relevant departments should adopt flexible and diverse forms, effectively increase publicity, vigorously publicize the significance of the construction of Airport Avenue and Xinhe Road, and publicize laws, regulations and policies related to land acquisition and demolition. Through publicity, the construction of Airport Avenue and Xinhe Road is well-known and deeply rooted in people's hearts.
Third, we must form a joint force. All units and departments should establish a sense of overall situation? A game of chess? Thought, obey the command, obey the command, strengthen cooperation and cooperate closely to form a strong. Work together. At the same time, in the process of land acquisition and demolition, we should conscientiously implement relevant laws, regulations and policies, strictly grasp the policy boundaries and working standards, be realistic and accurate, and ensure the smooth progress of project construction.
Demolition work publicity implementation plan II:
According to "People's Republic of China (PRC) Land Management Law", "People's Republic of China (PRC) Land Management Law Implementation Regulations", "People's Republic of China (PRC) Urban and Rural Planning Law", "Notice of the Provincial People's Government on Promulgating the Unified Annual Output Value Standard of New Land in the Province and the Comprehensive Land Price of All Districts" (official name), and the relevant spirit of the municipal government and the government of Economic Development Zone on examining and approving water conservancy construction projects around the region, combined with the economy,
I. Overview of Land Acquisition and Demolition
(1) Land requisition scope
(2) Demolition scope:
All buildings and accessories (including houses, rural infrastructure and water conservancy facilities, graves, telephone poles, etc.). The land within the scope of land requisition must be demolished.
Second, the compensation standard for land acquisition and demolition
(1) The nature of the expropriated land includes collective agricultural land and state-owned agricultural land. The compensation standard for land expropriation is: the average compensation for collective agricultural land is 20,000 yuan/mu, including land compensation and resettlement subsidies, excluding young crops compensation, ground attachments compensation and social security fees. For specific compensation standards, please refer to the Notice of Economic and Technological Development Zone on Implementing Opinions on Unifying Annual Output Value and Collecting Comprehensive Land Price (see Annex 1). See the relevant documents of the municipal government for the insurance of landless farmers (see Annex 2).
(2) Due to the complexity of the situation, the expropriation of state-owned agricultural land needs to be considered in combination with factors such as farm restructuring, social security, and the placement of farm workers, and with reference to the land acquisition situation of other farms, it is temporarily levied at 1 1.5 million yuan/mu. Compensation fees for attachments and young crops on the ground shall be compensated according to the relevant documents of the Economic Development Zone.
(3) For the compensation standard for rural house demolition, see the Implementation Measures for Rural House Demolition and Resettlement Compensation in Economic and Technological Development Zone (Annex 3), and the compensation standard for rural house demolition shall be implemented with reference to the compensation standard for rural house demolition.
Third, the time requirements for land acquisition and demolition.
According to the requirements of the "Implementation Plan for Water Conservancy Construction Projects around the Region" approved by the municipal government and the development zone government, the land acquisition and demolition of plots A and C implemented in the first phase of the project must be completed before June 30, 2008.
Four. Resettlement methods and principles
(A) the placement method
1, centralized housing allocation; The grave is in the center.
2, the determination of centralized housing resettlement sites, by the development zone government to solicit opinions from the masses, and negotiate with * * * urban construction investment and development co., LTD. (should meet the requirements of the overall planning of the plot); How about a settlement? Three links and one leveling? After that, unified planning, unified design and unified construction procedures, the economic development zone government should closely cooperate with urban construction investment and development Co., Ltd. and support each other.
3 centralized graves are selected by the government of the Economic Development Zone.
(2) the principle of resettlement
For details, please refer to the Implementation Measures for Rural Housing Resettlement Compensation in Economic and Technological Development Zone (Annex 3).
Verb (abbreviation of verb) payment method of compensation for land acquisition and demolition
1. According to the relevant policies, the city investment company signed a land acquisition compensation agreement with the Economic Development Zone Land and Resources Bureau, and transferred the land acquisition funds and land acquisition management fees into the account of the Economic Development Zone Land and Resources Bureau. The Bureau of Land and Resources of Economic Development Zone is responsible for signing a land acquisition compensation agreement with the town and village, transferring the land acquisition funds to the town and village accounts, and then distributing them to the villagers whose land has been expropriated by the town and village committees.
2. The total cost budget for demolition is made by the demolition and resettlement management office of the Economic Development Zone Planning and Construction Bureau according to the demolition area, structure type and compensation standard. The city investment company will transfer the money into the demolition account of the Economic Development Zone in proportion according to the demolition progress, and the demolition office of the Economic Development Zone will transfer the corresponding compensation for demolition to the relevant towns and offices, and then the village Committee will distribute the compensation for demolition to the villagers who have been demolished.
VI. Compensation and Resettlement for Land Acquisition and Demolition
According to the actual number of land acquisition and demolition of this project, and referring to the relevant compensation standards of the municipal government and the Economic Development Zone Government, the settlement will be made.