6. 1.3 is responsible for the disclosure of technology, quality, safety, site capability and progress to party b. ..
6. 1.4 Be responsible for providing Party B with 1 set of construction drawings. If it is necessary to increase the number of copies of construction drawings, Party B may make extra copies at its own expense.
6. 1.5 Be responsible for organizing the blue prints.the design of construction drawings, making disclosure of construction organization design, and reviewing the detailed construction operation plan prepared by Party B. ..
6. 1.6 is responsible for providing commercial concrete, but party b is responsible for the front and back management and sampling of the pumping station.
6. 1.7 Responsible for the external liaison of this project.
6. 1.8 Responsible for organizing the project completion acceptance, and coordinating and coordinating the intermediate acceptance and partial acceptance organized by Party B. ..
6. 1.9 is responsible for transporting steel raw materials to the construction site (Party A is responsible for the unloading expenses of the first truck crane).
6. 1. 10 Organize regular production meetings and comprehensive inspections on a regular basis.
6. 1. 1 1 Changes in drawings shall be subject to Party A's written notice. ..
6. 1. 12 is responsible for technical management and technical data collection, but the self-inspection data and compulsory inspection test data shall be provided to party a after timely inspection by party b. ..
6. 1. 13 has the right to review and supervise the payment method of wages for migrant workers in shifts of Party B..
6.2 Rights and obligations of Party B:
6.2. 1 site representative of party b: fully responsible for all construction matters within the scope of the contract.
Party B shall also provide other 13 project managers, the number of whom is as follows (Party B shall provide the list when entering the site):
Team leader (1), builder (3) and surveyor (2); Security Officers (2 persons); Quality inspector (2 persons); Water and electricity foreman (1); The doorman (at least 2 people) must hold relevant certificates, and the post certificate shall be managed by Party A under pressure. The attendance of the above-mentioned personnel shall be managed by Party A's project department in a unified way, and the number of attendance days per month must be consistent with that of all personnel in the project department, not less than 28 days (not less than 26 days in February).
6.2.2 Party B must ensure the integrity of the project management personnel, and shall not replace the above-mentioned personnel at will before the completion of the project, because Party A has the right to impose an economic penalty of 50,000 yuan/person/time on Party B except for the inaction personnel, force majeure or personal special reasons that Party A requires to be replaced.
6.2.3 Party B guarantees that the project shall not be subcontracted again in any way, otherwise it will be regarded as a breach of contract, and Party B must bear all liquidated damages for breach of contract.
6.2.4 Party B must obey the instructions of Party A, the general contractor, the owner and the supervision unit.
6.2.5 Strictly implement the management regulations formulated by Panzhihua Steel City Jian 'an Company, Sichuan Shulong Construction Labor Group Co., Ltd. and various functional departments.
6.2.6 Party B shall ensure continuous construction during holidays and busy farming periods.
6.2.7 All on-site construction personnel must abide by various rules and regulations such as quality, safety, civilized construction, logistics, health, environmental protection, fire control and security, and set up full-time quality inspectors and safety officers to be responsible for quality and safety work. Bear all responsibilities and losses caused by violating the above provisions. Party B shall submit to the comprehensive inspection organized by relevant departments of Party A. ..
6.2.8 Handle all kinds of construction permits (including all kinds of permits for construction personnel) according to the regulations of Chengdu Construction Committee. In case of violation, all responsibilities shall be borne by Party B.. All kinds of special types of work (including surveyors and large-scale mechanical operators) and self-provided construction personnel of special types of work need to hold relevant certificates.
6.2.9 Ensure that it is completed according to the requirements of monthly project progress, quality, safety and civilized construction. Failure to complete one of them every month due to Party B's reasons will be regarded as a breach of contract and will be treated as a breach of contract. Party A reserves the right to persuade him to leave his post, and the losses caused by his resignation shall be borne by Party B..
6.2. 10 Register the permit and construction personnel and submit them to Party A for filing. Personnel involved in the construction must hold ID cards and work permits. And submit a copy of ID card and work permit to the project contractor for the record.
6.2. 1 1 During the construction process, Party B has the responsibility and obligation to negotiate with Party A, actively cooperate, adopt a reasonable construction scheme and reduce the project cost.
6.2. 12 provides steel bar welding and mechanical connection specimens and concrete specimens. The specimens cured under the same conditions shall be made on site by the contractor according to the specifications and witnessed by the Employer, and the strength grade must meet the design requirements. The expenses for inspection and test shall be borne by the Employer, and the expenses for making and sending samples and re-inspection shall be borne by Party B. ..
6.2. 13 steel bars in this project (including embedded iron pieces, wall rods, etc. ) Party B shall be responsible for it, and its reinforcement scheme shall be submitted to Party A for review 10 days in advance, and shall be processed after being reviewed by Party A. ..
6.2. 14 Enter the site on time according to the time notified by Party A. ..
6.2. 15 The construction shall be carried out in strict accordance with the overall construction organization design and special construction scheme, and the construction scheme shall not be changed without authorization, and the advanced technologies and processes involved in the construction process shall be kept confidential.
6.2. 16 During the construction period, Party B must meet Party A's requirements for image work and complete Party A's corporate image publicity; Bring your own protective equipment that meets Party A's image work and safety requirements, and pay your own expenses.
6.2. 17 Provide monthly image progress report meeting Party A's requirements according to the date required by Party A. ..
Construction engineering labor contract 8 pages
Owner: Construction Co., Ltd., hereinafter referred to as Party A.
Contractor: _ _ _ _ _ _ _ _ _ _ _ _, hereinafter referred to as Party B.
In accordance with the Contract Law of People's Republic of China (PRC), the Construction Law of People's Republic of China (PRC) and the Interim Provisions of the Company on the Management of Labor Contracts of Engineering Projects. Party A decides to subcontract the labor services of _ _ _ _ _ _ Project Department of _ _ _ _ Company to Party B. In order to standardize the management and clarify the responsibilities, this contract is hereby signed by both parties through consultation for mutual compliance.
1. The scope of labor service construction projects contracted by Party A to Party B is as follows:
All brick and stone masonry and plastering subdivisional work in the construction drawings of this project; Steel production, binding subdivisional work; Template production and installation of subdivisional work; Scaffolding operation.
Two. Term of contract:
From _ _ _ _ _ _ _ to _ _ _ _ _ _.
Third, the engineering quality standards:
The quality of all subdivisional work is guaranteed to be excellent.
IV. Payment and payment method of labor management fee:
1. Payment standard: The labor management fee of this project is RMB100000 Yuan only, which shall be paid by Party B. If Party B can meet the quality and progress requirements in the contract signed between the project department and the owner, Party A will return the management fee to Party B as a reward.
Payment method: Labor management fee will be paid in two phases, namely, 50 yuan before the main body is completed and 50 yuan before the renovation is completed.
Verb (abbreviation of verb) Party B's responsibility
1. Party B shall provide relevant certificates and qualifications and cooperate with Party B to handle relevant formalities.
Coordinate the handling of labor disputes and industrial accidents in the construction process.
The responsibility of intransitive verb Party B:
1, fully perform the engineering construction contract signed by _ _ _ _ Company and _ _ _ Construction Co., Ltd., and assume all the responsibilities and obligations that Party B shall bear under the terms of this contract.
2. Ensure that the quality, progress and safety of all subdivisional works meet the contract requirements signed by the project department and the owner. If not, the penalty will be 50% of the management fee.
Seven. For matters not covered in this contract, both parties can sign supplementary terms through consultation, which have the same legal effect as this contract.
Eight. This contract is made in sextuplicate, with each party holding three copies. This agreement shall come into force after being signed by both parties, and shall become invalid after the project is completed and the labor management fees are settled by both parties.
Party A:
Party B:
Representative of Party A:
Representative of Party B:
Construction engineering labor contract 9 pages
Employer: (hereinafter referred to as Party A)
Contractor: (hereinafter referred to as Party B)
According to the relevant spirit of People's Republic of China (PRC) Contract Law and Regulations on Construction Project Contracting, Party A agrees to contract out the labor service of this project to Party B through negotiation between Party A and Party B. In order to clarify the rights and obligations of both parties, the following clauses of this agreement are hereby signed for both parties to abide by.
I. Name and location of the project:
This project is a project located at.
Second, the contracting methods and requirements:
This project is contracted by Party A to Party B in the form of tax, labor and accommodation by combining the division of labor and unit price into the total price. The contracting team is required to have the qualification of labor contract, and the main types of work should have the certificate of appointment, and the roster of personnel should be compiled and submitted to Party A for filing for future reference.
Three. Unit price and contents of the project contract: through negotiation between both parties, the project is contracted by Party B, and the contract unit price is RMB /(m2, m3, t), which includes the following contents: complete the full set of construction drawings, disclosure minutes and all contents related to construction changes provided by the owner; Site planning and cleaning, etc. Before Party A makes payment, Party B shall provide Party A with the corresponding invoice in advance.
Fourth, the project quality and safety:
According to Party A's requirements, the project quality is excellent, and the single contract must be guaranteed to be excellent. If a single contract is judged unqualified, Party B will rework it until it is qualified, and all economic losses caused by rework shall be borne by Party B and deducted from Party B's labor settlement.
Party B's construction personnel must obey the arrangement of Party A's management personnel and strictly abide by the safety operation rules. In order to enhance workers' safety awareness, the team leader and the team leader should arrange the workload every day, conduct safety disclosure education, emphasize safe operation, wear safety helmets, install safety nets, fasten safety belts, and do all kinds of safety protection work to prevent safety accidents. All safety accidents caused by Party B shall be borne by Party B, and Party A shall not bear any economic and legal responsibilities. Previous1.45 678 910112.15 Next page