What approval procedures do you need to go through when a construction project starts?

I. Shenzhen City

On May 27th, 2020, Shenzhen Housing and Urban-Rural Development Bureau issued the Notice on Doing a Good Job in the Examination and Reform of Construction Drawings in Shenzhen.

1

From July 1 day, the construction drawing review of new, expanded and rebuilt houses and municipal (including water and transportation) projects in Shenzhen was cancelled, and the notification commitment system was implemented. All administrative licenses shall not be based on qualified construction drawing review documents. Major projects in the fields of transportation, water conservancy and energy that need to be submitted to the provincial and national authorities for examination and approval, except for major hazard projects such as oil and gas depots, long-distance oil and gas pipelines, civil explosive warehouses, security projects and rail transit projects.

2

The construction unit is mainly responsible for the quality and safety management of survey and design. Survey and design units are the main responsible persons for quality and safety management of survey and design. Construction, survey and design units shall implement the project leader system.

three

From 0: 00 on July 1 2020, the Shenzhen survey, design and construction drawing review system will be closed, and the documents and materials in the system will be automatically transferred to the management system.

Second, Shandong Province

On March 19, 2020, the CPC Shandong Provincial Committee and the Shandong Provincial People's Government issued the Guiding Opinions of the CPC Shandong Provincial Committee and the Shandong Provincial People's Government on Deepening System Innovation and Accelerating Process Reengineering, proposing "optimizing the approval process of engineering construction projects".

1

Precisely optimize the approval process of engineering construction projects by region and category, streamline the relevant approval items and technical review links, and the approval of simple and low-risk projects in the province will not exceed 20 working days.

2

Reform the review mechanism of engineering drawings, explore canceling the review of construction drawings or narrowing the scope of review in China (Shandong) Pilot Free Trade Zone, China-SCO local economic and trade cooperation demonstration zone and Qingdao West Coast New District, cancel it in the whole province according to law before the end of 65438+February in 2020, implement the notification commitment system and the designer's lifelong responsibility system, and implement the survey and design liability insurance system.

Third, Nanjing City.

2065438+On September 3, 2009, Nanjing Urban and Rural Construction Committee issued a notice on printing and distributing the Implementation Opinions on Optimizing the Examination and Approval Service for Newly-built Simple and Low-risk Social Investment Projects in Nanjing, and carried out the following reforms on simple and low-risk social investment projects:

1

Cancel the construction drawing review;

2

Except for special construction projects and crowded places, fire inspection and filing shall be cancelled;

three

Cancel the design review;

four

Cancel the acceptance of civil air defense, transportation and completion files, as well as the acceptance of water, electricity and gas projects.

Fourth, Qingdao.

On September 20 12 19, the Administrative Committee Office of Qingdao West Coast New District issued the Notice on Further Improving the Efficiency of Administrative Examination and Approval of Project Construction, proposing that:

1

From September 20 19 12, all construction projects within the jurisdiction of Qingdao West Coast New District will implement the quality and safety commitment system for survey and design.

2

When the construction unit handles the administrative examination and approval procedures such as fire protection, civil air defense and construction permit, it is no longer necessary to submit the quality and safety commitment letter of survey and design signed by the construction, survey and design unit.

Verb (abbreviation of verb) Shanxi Province

2065438+July 2009, Shanxi Provincial Housing and Construction Department issued the Notice on Further Deepening the Reform of Construction Drawing Review System and Strengthening the Quality Management of Survey and Design (Trial), proposing:

1

From July 1 2009, the quality commitment system for construction, survey and design units and the expert demonstration system for important engineering construction drawings were implemented, the lifelong responsibility system for quality was strictly implemented, the existing construction drawing review link of social intermediary agencies for housing construction and municipal infrastructure projects was cancelled, and provincial construction drawing review institutions stopped undertaking new review business, and those that had been undertaken were completed according to the original procedures.

2

Implement the quality commitment system of survey and design. The province's housing construction and municipal infrastructure projects apply for construction permits and submit a letter of commitment on survey and design quality.

Intransitive verb Guangzhou city

2065438+On August 26th, 2009, the Guangzhou Municipal Government issued the Notice on Printing and Distributing the Implementation Plan for Further Deepening the Reform of the Examination and Approval System of Engineering Construction Projects in Guangzhou, proposing that:

1

Explore the cancellation of government investment in housing construction projects and municipal infrastructure projects construction drawing design document review, strengthen the main responsibility of the construction unit. The construction unit may decide whether to entrust a third party to review the construction drawing design documents according to the actual situation of the project. The construction unit may issue a letter of commitment and submit the construction drawings signed by qualified design units and registered designers, and may apply for construction permit approval.

2

The preliminary design of large-scale housing construction projects and large and medium-sized municipal infrastructure projects invested by the government (including budget estimates) shall be examined and approved by the competent department of industry; Government investment in small and medium-sized housing construction projects and small municipal infrastructure projects, the construction unit shall organize preliminary design review and issue technical review opinions, without reporting to the competent department of industry for approval.

Seven. Zhejiang Province

2065438+July 2009, Zhejiang Provincial Housing and Construction Department issued "Guiding Opinions on Deepening the Reform of Construction Drawing Examination System for Housing Construction and Municipal Infrastructure Projects (Draft for Comment)";

1

Laws, regulations, rules and the State Council administrative requirements are not clearly defined as the contents of the construction drawing review, and shall not be used as the contents of the review;

2

In addition to the following three types of projects, other housing construction and municipal projects implement the self-examination and filing system: construction projects with higher structural safety requirements; Special construction projects, civil air defense projects and construction projects that require fire protection design review as stipulated by the state shall be independently reviewed for lightning protection device design; Residential, commercial and office buildings (including affordable housing) are sold or rented after completion.

three

For the construction projects that implement the self-examination and filing system, the construction departments of cities and counties (cities, districts) shall conduct a comprehensive post-examination of the construction drawings before the foundation pit excavation;

four

For the construction projects that implement the self-examination and filing system, the construction departments of cities and counties (cities, districts) shall conduct a comprehensive post-examination of the construction drawings before the foundation pit excavation;

five

For housing construction projects that are not suitable for self-examination, the underground and aboveground parts (bounded by the top surface of a certain floor) can be examined in stages.