Germany Schenk said, how to measure the blanking amount is the same as the actual amount, and how to correct the deviation.

Physical calibration. First, select the controller panel to be operated, clear the accumulated amount Z2, and then discharge hundreds of kilograms of materials with a belt, about once.

Weigh out how much material is put down with standard pounds, and divide it by cumulative amount Z2, which is the value of calibration correction coefficient D02. If the deviation is too large and D02 is as small as 0.8 or more than 1.2, recalculate B05 value and modify the leverage ratio CO7.