What is the standard of engineering cost consulting service fee?

After two years' trial implementation, the document [2005] No.248 of Sichuan Price and the actual situation of construction in our province. According to the Price Law of People's Republic of China (PRC), Regulations of Sichuan Province on Price Management, Measures for the Administration of Engineering Cost Consulting Enterprises (OrderNo. 149 of the Ministry of Construction), Measures for the Administration of Intermediary Service Fees (No.2255 of the State Planning Commission) and relevant national and provincial laws and regulations, the relevant provisions on the charging of engineering cost consulting services in our province are hereby notified as follows:

1. All engineering cost consulting units within the administrative area of our province (such as Sichuan Chuangxin Engineering Consulting Co., Ltd.) face the society, accept the entrustment, provide professional services for the determination and control of construction project cost, and undertake engineering cost consulting services for construction projects such as project budget estimate, budget (tender control price or pre-tender estimate), interim payment, completion settlement, compilation and audit of bill of quantities, and whole-process engineering cost control, etc., according to the provisions and requirements of this notice.

Two, the project cost consulting unit to implement the charges must meet the following conditions:

1, approved by the administrative department for industry and commerce, registered and obtained the business license of legal person;

2, approved by the national or provincial construction administrative departments, and obtained the "qualification certificate of engineering cost consulting unit";

3. Carry out tax registration according to law and obtain a tax registration certificate;

4, to apply for the "license fee" to the price department.

Three, the project cost consulting unit to provide paid services should follow the principles of openness, justice, honesty and credit, fair competition, voluntary compensation, and the principle of client payment. The entrusting party and the consulting unit shall, in accordance with the requirements of the Contract Law of People's Republic of China (PRC), adopt the model contract for project cost consultation, sign a written agreement or contract according to law, specify the charging items (contents) and charging standards, and provide qualified services in strict accordance with business procedures. No department, unit or individual may in any way designate a cost consulting unit to serve the relevant parties, and may not force services or charge fees.

Four, the project cost consulting unit should be strictly in accordance with the national and provincial project cost policy in accordance with the law, it is strictly prohibited to resort to deceit. And bear the corresponding economic and legal responsibilities for the project cost consultation results provided by it.

Five, the project cost station to explain the quota, the bidding agency to review the pre-tender estimate, the investment department to review the project settlement shall not charge. Design institutes (institutes) shall not charge extra fees for compiling the budget of engineering design projects.

Six, in line with the above conditions of engineering cost consulting units by the Provincial Association of Cost Engineers after the audit, to the Provincial Price Bureau to apply for a "license fee". The engineering cost consulting unit shall publicize the charging items, service contents, charging methods and charging standards in a prominent position in strict accordance with the charging items and standards approved by the charging license. Except for post-earthquake reconstruction, all charges below the 80% lower limit of this standard are malicious competition, which shall be handled by the Provincial Association of Cost Engineers according to the industry self-discipline convention.

Seven, the price and construction administrative departments at all levels should strengthen the supervision and management of the engineering cost consulting service charges, to engage in engineering cost consulting services without qualification and charge fees, or compulsory service charges and other illegal acts, respectively, by the price and construction administrative departments at the same level severely punished.

Eight, this notice shall be implemented as of August 1 2008. Yuan Chuan Jia Fa 2005 No.248 shall be abolished at the same time. The state has new charging regulations, which shall be followed.

July 24(th), 2008

Attachment:

Charging standard of engineering cost consulting service in Sichuan Province

Description:

A, the bill of quantities, project budget (tender control price or pre-tender estimate), the preparation and review of reinforcement in completion settlement shall be carried out according to the quota content. If lofting is carried out according to other 1 1 items, the cost shall be calculated.

Two. Calculation of differential fixed-rate progressive charges: If the final settlement cost of Item 5 is 30 million yuan, the service fee is calculated as follows:

1 10,000 yuan ×3.5‰=0.35 million yuan.

(500- 100) ten thousand yuan ×3.2‰= 1.28 million yuan.

(1000-500) ten thousand yuan × 3.0 ‰ =1.500 million yuan.

(3000- 1000) 1 ten thousand yuan × 2.7 ‰ = 54,000 yuan.

A total of 85,300 yuan

Three, the preparation of the bill of quantities includes the budget control price, the charging coefficient multiplied by 1.25.

Four, this standard is based on housing construction and municipal infrastructure projects, such as roads, railways, water conservancy, dams and other civil works, the charging standard should be reduced by 50%.

Five, when the audit is completed, all the basic audit fees shall be borne by the entrusting unit. In addition, an audit fee of 3-5% can be charged according to the audit increase or decrease (the specific scope is agreed by both parties in the cost consultation contract), and the audit increase or decrease rate is within 5% (including 5%), and the audit fee shall be borne by the entrusting unit; If the reduction is more than 5%, the audit fee within 5% (including 5%) shall be borne by the entrusting unit, and the excess shall be borne by the compiling unit; The audit fee for increasing the audit shall be borne by the preparation unit.

Six, the project cost dispute case appraisal shall be borne by the unit with the corresponding project cost consulting qualification (except for the provisional qualification). If the case is retried due to an error in the appraisal conclusion, it shall be re-appraised by the provincial engineering cost station, and if the error of the original conclusion is more than 3%, the original appraisal unit shall return the original appraisal fee in full.

Seven, the whole process of engineering cost consulting service cycle, according to the construction contract period plus 2 months for the normal service period; If the overdue service is caused by reasons other than the cost consulting unit, the overdue service fee shall be calculated according to the monthly average service volume calculated during the normal service period and the service fee agreed in the service contract multiplied by the overdue service time.

Eight, the decoration engineering, installation engineering and technical transformation engineering entrusted separately shall be increased by 20% on the basis of the above expenses.

Nine, this charge is calculated according to a single project, where the amount of a single charge is less than 3000 yuan, it will be charged at 3000 yuan.

Ten, non engineering cost consulting unit caused the same project duplication or increase the consulting workload by more than 20%, the cost of increasing the workload shall be calculated separately according to this charging standard.

XI。 This charging standard is the charging standard under reasonable construction period and normal working days. The consulting fee will be increased by 20-30% if the client requests to rush to work or take up the national statutory rest time.