Completed and opened to traffic
201010 On the morning of February 26th, the groundbreaking ceremony from Neixiang to expressway in Dengzhou was held in dengzhou city. The project investment is estimated to be 3.5 billion yuan, and the construction period is 3 years.
201212 On February 30th, a press conference was held in Nanyang, Henan Province, announcing two great news: the completion and opening to traffic of expressway, the inner (township) city, and the construction of expressway, the border of Dengzhou-Henan-Hubei Province. City leaders, He, and Liu attended the press conference.
As of August 20 13 and 17, five toll stations temporarily opened two toll stations, Qutou and Longyan, and the employees of the other three stations did not receive the work notice.
Exposure problem
20 14, 14, CCTV focus interview exposed the results of Neideng Expressway. It left a mess: poor quality, impassable roads, unclear accounts and constant disputes.
Rectification and reform
2065438+On May 7th, 2005, Zhao Jiancai, Vice Governor of the provincial government, presided over a special coordination meeting on the construction of Neideng expressway. The meeting decided to implement the government agreement trusteeship model, and the provincial finance lent 620 million yuan to Nanyang Municipal Government without interest, all of which were used to complete the remaining project of Neideng Expressway and realize the goal of completion and opening to traffic as soon as possible.
2065438+On June 6th, 2005, the Municipal Transportation Bureau held a seminar on the Neten expressway Trusteeship Agreement, in which the principal responsible person of Wanda Xin Company, the president of Inner Mongolia Group and its main creditors attended. At the meeting, preliminary opinions were formed on the main contents of the Trusteeship Agreement, and relevant meeting minutes were formed. In accordance with legal procedures and relevant regulations, it is necessary to improve the relevant procedures for injecting government financial funds into the private real economy. At present, the municipal government and the municipal transportation department are actively operating, making every effort to promote the co-management and custody of projects, starting the remaining projects as soon as possible, making a good assessment of the financial funds for toll repayment, preventing investment risks, and managing and using the financial funds well. At the same time, the municipal government urged the entrusted party to organize scientifically, standardize the construction, ensure the quality, and strive to achieve the goal of early opening of Neideng expressway.
20 15 10 On October 20th, Cheng Zhiming, deputy secretary of Nanyang Municipal Party Committee and mayor, stressed at the mobilization meeting of the remaining projects of Neideng Expressway that Neideng Expressway is a key project of transportation infrastructure construction in provinces and cities, and it is necessary to proceed from the overall situation of opening to traffic, act quickly, create a good environment, organize scientifically, and work hard for two months to ensure the smooth progress and timely completion of the project construction by decisive battle.
Neideng Expressway was put into trial operation on 2065438+200665438+1October 24th.
The above is the introduction of Zhong Da Consulting on the construction of Neideng expressway. For more information about expressways, please pay attention to the architectural knowledge column of Zhong Da Consulting.