Backfilling construction of back culvert top of frame culvert?

After the culvert construction is completed, it will be compacted and backfilled symmetrically in layers within the range of more than twice the aperture on both sides of the culvert body.

Backfill materials shall be permeable materials that meet the design requirements, such as gravel and crushed stone, and the gradation of permeable materials shall be reasonable. In granular materials smaller than 2cm, the content of fine materials passing through 0.074mm sieve hole is not more than 10%, and the maximum particle size of filler is not more than 50 mm

Backfilling is carried out by combining manual and mechanical methods, the part near the culvert is compacted by small machinery, and the part far away from the culvert is compacted by roller.

Subgrade filling at the top of culvert: the concrete strength of culvert can reach 100%, and when the thickness of covering soil at the top of cave is less than 1m, heavy machinery is not allowed to pass.

For more information about project/service/procurement bidding, and to improve the winning rate, please click on the bottom of official website Customer Service for free consultation:/#/? source=bdzd