One-layer hoisting method of insulating glass

The method for hoist that first layer of hollow glass comprise the following steps:

(1) transport the equipment to the construction site by crane, and fix the location according to the drawing requirements. Note: The lifting height of the crane should be less than or equal to 2.5 meters. ..

If the width of the equipment is greater than 1.5m, it is recommended to adopt double-machine pole lifting operation. If it is necessary to operate on the ground, an operating platform or bracket should be set on the ground.

(2) Determine the weight and size of insulating glass according to the equipment model and put it on a flat ground.

(3) Locate the equipment according to its model, specification and instruction, and adjust the level meter to a horizontal position; At the same time, the stability of equipment and foundation should be ensured.

If necessary, you can increase the stability of the ground with blocks and other items. If the above conditions cannot be met, a layer of wood strips can be padded on the foundation to stabilize it.

(4) After confirmation, put the equipment into the embedded bolt hole, and then tighten the fixing bolt to use.