Take Beijing as an example:
Beijing fire record is divided into two types: more than 300 square meters and less than 300 square meters (including 300 square meters).
Dongcheng, Xicheng, Chaoyang, Fengtai, Shijingshan, Haidian, Mentougou, Fangshan, Tongzhou, Shunyi, Changping, Daxing, Huairou, Pinggu, Miyun and Yanqing have the same specific steps.
The fire protection filing process below 300 square meters is as follows:
1. Search and open the website of Beijing Fire Bureau.
2. Click on the integrity platform of Beijing building fire protection design and construction quality.
3. Click on the online application procedure.
4. login ID number
5. Click Next
6. Fill in the fire supervision institution, street, project name and project location.
7. Upload a scanned ID card or photo.
8. Select the construction unit
(It must be a formal decoration company registered by Beijing Fire Bureau and qualified to audit the project)
9. Fill in the qualification grade, legal name, telephone number, contact person and contact person of the decoration construction unit.
Telephone, on-site project manager or project leader, fire safety manager
10. Building-Add
1 1. Fill in the building name, building (or decoration area) (㎡).
Building height, building floors, selection and use nature, fill in building floors,
The main building selected was (not) 98 years ago.
12. Select the commencement time, estimated completion time, peak number of workers, peak number of welding, certificate type (acceptance opinion) and fill in the certificate number.
13. Upload the floor plan for decoration.
14. Upload the construction organization design (including floor plan)
15. Upload the fire and electricity system on the construction site.
16. Upload the fire control plan of the construction site.
17. Upload the fire safety measures at the construction site.
18. Upload the construction safety fire control agreement.
19. Select temporary housing on the construction site
20. Please reconfirm whether the above information is clear and accurate, and whether it is consistent with the declared items.
You cannot change the declaration information after reconfirmation!
2 1. Submit after confirmation.
22. The fire record audit department audit
23. Review and approval
24. Download or print fire safety instructions for small interior decoration projects.
25 Beijing small interior decoration engineering fire online filing procedures.
(If you don't understand, you can contact the service hotline for voice notification: escape, check-in, escape, phase II and phase III. Or click on the avatar to get contact information)
The fire protection filing process for projects exceeding 300 square meters is as follows:
First of all, a complete set of drawings, divided into four parts: fire protection, electrical, HVAC and exhaust, including:
1, cover
2. Contents
3. Design description
4. List of main materials
5. Original structural drawing
6. Schematic diagram of wall positioning
7. Layout plan
8. Schematic diagram of ground pavement
9, ceiling layout
10, lighting equipment drawing
1 1, fire alarm diagram
12, emergency evacuation and fire extinguisher layout
13, comprehensive ceiling layout
14, high-voltage socket layout
15, weak current socket layout
16 fire control system diagram
17, fire sprinkler layout
18, air conditioning tuyere layout
19, fire smoke exhaust layout
20, fire control system diagram
After generating drawings, search:
Beijing housing construction engineering construction drawing multi-examination integrated declaration platform
choose
Statement of the construction unit
Fill in the following:
Name of the construction unit (full name) * Note: The full name of the unit should be filled in, and the words used in the name should be consistent with the organization certificate of the unit.
Unified social credit code *
Place of registration of the construction unit *
Name of enterprise legal person or legal representative * Note: The legal representative is used to build non-enterprise units, such as administrative institutions.
ID number of enterprise legal person or legal representative *
The current office location of the construction unit Note: The address should be detailed to meet the mailing and contact needs.
Name of the person filling in the declaration form or contact person.
Declare the ID number of the applicant or contact person.
Telephone number of the applicant or contact person Note: The telephone number should be valid for effective contact.
Construction project information (project * is a control item, and cannot be changed once it is filled in and confirmed, please check it carefully).
Project name * Note: The full name should be filled in, and the words used in the name should be consistent with the name of the project construction planning permit.
Project category internal conversion project
The original function of the building *
Functions of the renovated building *
Transformation type * Renovation, external thermal insulation and energy saving, seismic strengthening and structural transformation.
Building scale (m2) * Example: 2350.5 Note: It refers to the indoor renovation area.
Project investment (budgetary estimate, budget) 10,000 yuan Note: It refers to housing construction costs, excluding non-construction and installation costs such as land. The investment amount should be true and consistent with the figures reported to the relevant departments.
Please choose Dongcheng District Xicheng District Chaoyang District Fengtai District Mentougou District Fangshan District Tongzhou District Shunyi District Changping District Huairou District Pinggu District Yanqing District Economic Development Zone Qinghe Beijing Municipal People's Government Office (Tianjin).
Remarks on project construction site: fill in according to the actual construction site of the project, and the text is consistent.
Property Ownership Certificate or Planning Permit *
Does it include civil air defense works? No, it is.
Area of civil air defense works (square meters)
Design organization information (* is required, please check and confirm it carefully)
Name of design unit * Note: The full name should be filled in, which is consistent with the name of the unit in the design qualification certificate.
Number of qualification certificate of design unit * Note: The certificate number should be completely filled in and consistent with the certificate (A or AW starts with +9 digits, and other characters are not supported).
Name of project leader of design unit *
ID number of the project leader of the design unit *
Telephone number of project leader of design unit *
Mobile phone of the project leader of the design unit *
Description of testing unit: If structural reinforcement is involved, it needs to be filled in.
When the login authentication password is not filled in, it will be automatically set as the enterprise organization code.
After the above contents are filled in, wait for the company to call or email to make an appointment.
After the appointed time, pay the 5 yuan drawing examination fee per square meter (starting from 5,000 yuan) and start drawing examination (preliminary examination, drawing examination, review, drawing examination and approval).
After passing the examination, he obtained the qualification certificate of Beijing construction drawing design document review, and stamped with the qualification certificate of drawing review company.
End of design review
Online construction filing shall be carried out before commencement, and the filing certificate shall be obtained. The method is similar to obtaining the Notice of Small Interior Decoration Fire Safety. If you don't understand anything, please call my avatar phone and let me know one by one.
The specific steps for online processing of fire protection record certificates of more than 300 square meters are as follows:
Search and open the website of Beijing Fire Bureau.
. Click on the integrity platform of Beijing building fire protection design and construction quality.
Click online declaration.
Select the social unit to log in.
Enter the name and login password of the construction company.
Select project type: reconstruction (maintenance, building insulation, change of use)
Whether the interior decoration is more than 300 square meters, the choice is yes.
Click Next.
Fill in the fire supervision institution, street, project name and project location.
Select the construction unit (company)
Fill in the qualification grade, legal person name, telephone number, contact person and telephone number of the decoration construction unit, and the on-site project manager or project leader and fire safety manager.
Buildings-Add
Fill in the building name, building (or decoration area) (㎡) building height, number of floors, nature of use, number of floors, and whether the main building was (no) 98 years ago.
Select the start time, estimated completion time, peak number of workers, peak number of welding, certificate type (acceptance opinion) and fill in the certificate number.
Upload the floor plan of the decorated floor.
Upload the construction organization design (including scheme)
Upload the construction site fire power system.
Upload the fire plan of the construction site.
Upload the fire safety measures at the construction site.
Upload the construction safety fire control agreement.
Choose temporary housing on the construction site.
Please reconfirm whether the above information is clear and accurate, and whether it is consistent with the declared items. You cannot change the declaration information after reconfirmation!
Submit after confirmation.
Log in again after cancellation, click on my record to download or print the fire safety record certificate of the construction site of Beijing Public Security Bureau Fire Bureau.
At this point, the online filing procedures for fire protection of decoration projects over 300 square meters have all been completed.
The above is a personal summary, complete and comprehensive. If you have any questions, please contact my avatar number and answer them one by one to ensure your approval.