Examination outline for consulting engineer:

The first section "Introduction to Engineering Consulting" examination outline

Examination purpose

Through the undergraduate purpose examination, students' understanding, familiarity or mastery of the concept, nature, characteristics, functions and trends of engineering consulting, the contents, objects and methods of engineering consulting services, the conditions, rights and obligations of registered consulting engineers (investment), and the basic knowledge of engineering consulting industry management, risk management, laws and regulations are tested, so that students can have an overall understanding of the engineering consulting industry and establish a sound understanding.

Examination content

I. Overview

(a) to understand the origin, domestic and international status, development and trend of engineering consulting industry.

(two) to master the concept, nature, principles, characteristics, business scope and status and role of engineering consulting in economic construction.

(three) familiar with the object and method of engineering consulting services, and the relationship between engineering consulting and projects.

Second, registered consulting engineer (investment)

(a) to understand the concept of registered consulting engineer (investment) and the conditions and procedures for applying for registered consulting engineer (investment).

(two) master the scope of practice of registered consulting engineers (investment).

(three) familiar with the registration, obligations and rights of registered consulting engineers (investment).

(four) to master the necessary professional quality conditions and professional ethics of registered consulting engineers (investment).

Third, the engineering consulting company

(a) to understand the establishment, functions, qualifications, organization and management of engineering consulting companies.

(two) familiar with the market development and management of engineering consulting companies and the quality requirements for engineering consulting.

Four, the content of engineering consulting services

(a) familiar with the basic purpose and requirements of macroeconomic construction consulting and project construction consulting at all stages.

(two) to master the requirements of the main tasks of consulting at all stages of project construction.

Verb (abbreviation of verb) engineering consulting service procurement

(a) familiar with the internationally accepted procurement methods and rules of engineering consulting services.

(two) master the steps, methods and procedures of engineering consulting bidding and the preparation and skills of bidding documents; Provisions and calculation methods of engineering consulting fees.

Six, the organization and management of engineering consulting industry

(1) Understand the engineering consulting industry at home and abroad-and the management system of engineering consulting industry in China.

(two) familiar with the professional ethics of engineering consulting industry.

Seven. Risk management of engineering consulting service

(A) to understand the concept and content of engineering consulting service risk.

(two) familiar with the risk identification and prevention of engineering consulting services; Familiar with engineering consulting professional liability insurance knowledge.

Eight, the legal responsibility of engineering consulting

(a) to understand the concepts of laws and regulations, technical specifications and intellectual property rights related to engineering consulting.

(two) familiar with the legal responsibility in the process of engineering consulting services.

Examination Outline of the Second Section "Macroeconomic Policy and Development Planning"

Examination purpose

Through the undergraduate purpose examination, the degree of knowledge, familiarity or mastery of national macroeconomic policies and development planning necessary for engineering consulting business is tested, so as to promote the participants to consciously implement national policies and improve their professional level.

Examination content

I macroeconomics and management

(1) Understand the basic concepts of macroeconomics, the basic principles of economic growth and the growth mode.

(two) familiar with the national macroeconomic management objectives and main control means, the three-step development strategy, and the main objectives of China's national economic and social development during the Tenth Five-Year Plan period.

(three) to master the composition and function of China's macroeconomic policy system, the structure of the planning system and the principles of planning.

Second, investment policy.

(1) Understand the concept and classification of investment and its position in the operation of national economy.

(two) familiar with the basic principles of investment in fixed assets, the main objectives of macro-control of investment, the basic direction of China's investment and financing system reform.

(3) Master the basic systems of investment project management in China, including: investment project capital system, project legal person responsibility system, bidding system, project supervision system and contract management system.

Third, industrial policy.

(a) to understand the national industrial organization's policies on restricting monopoly, promoting enterprises to improve their international competitiveness and supporting the development of small and medium-sized enterprises.

(two) familiar with China's economic division of labor, as well as the direction of industrial restructuring in the eastern, central and western regions.

(three) to master the national industrial structure adjustment objectives, main technical and economic policies, the development direction of key industries and policies and measures, as well as foreign investment industrial policies.

Fourth, the financial system and monetary policy

(1) Understand the basic objectives and main policy tools of China's monetary policy.

(two) familiar with the classification of financial markets and their functions and functions.

(three) to master the classification, characteristics and functions of financial institutions in China.

Verb (abbreviation of verb) fiscal policy

(a) to understand the basic concepts and main functions of the national fiscal policy, and the coordinated use of fiscal policy and monetary policy.

(two) familiar with China's tax system, fiscal expenditure management, tax-sharing financial management system.

(three) to master the basic concepts and main categories of national budget, taxation, fiscal expenditure, national debt and state-owned assets management.

Other management policies of intransitive verbs

(a) to understand the main contents of the state policies on price management, population and employment, foreign trade and foreign exchange management.

(two) to master the relevant policies and regulations on the utilization of foreign capital and the management of foreign investment in China at this stage.

Seven. Industrial development planning

(a) familiar with the strategic objectives and main measures of the state to adjust the rural economic structure, promote agricultural industrialization and increase farmers' income; The guiding ideology and main measures of the country to accelerate the development of service industry.

(two) to master the main principles and basic tasks of China's industrial structure adjustment and enterprise technological transformation at this stage, and to master the direction and focus of China's high-tech industry development.

VIII. Infrastructure Construction and Urban Development Planning

Master the guiding ideology and strategic policy of the state on water conservancy construction, transportation construction, energy construction and promoting urbanization construction.

IX. Regional Development and Resources and Environment Planning

(a) to understand the basic concept of sustainable development strategy, as well as the guiding ideology and basic principles of the state on the protection and utilization of land, forests, grasslands, oceans, minerals and other resources.

(two) familiar with the national strategic principles and main tasks of strengthening ecological construction and environmental protection and governance.

(3) Grasp the key points of China's sustainable development action plan in the 2 1 century, the objectives, policies and key tasks of western development, and the main tasks of the development of eastern coastal areas and central areas.

X. Social Development Planning

(a) to understand the overall requirements of the state for the development of various social undertakings.

(two) familiar with the main contents of China's science and technology and education development plan.

The third section "project organization and management" examination outline

Examination purpose

Through the undergraduate purpose examination, the students' understanding, familiarity and mastery of the basic theories, contents and methods of engineering project management are tested, and their ability to use this knowledge to strengthen project management and solve practical problems is improved.

Examination content

I. Overview

(A) understand the development trend of project management.

(two) familiar with the meaning and characteristics of the project, the stage and cycle of the project, the goal of project management, the main stakeholders, the basic principles of project management, and the project management model.

Second, the parties involved in the project management

(a) all participants in the project understand the meaning, main purpose and characteristics of project management.

(two) familiar with the project owners, contractors, financial institutions and the government's main tasks for project management.

(three) to master the main tasks of consulting engineers in project management and the general working procedures of consulting engineers.

Third, the comprehensive management of the project

(a) familiar with the comprehensive management of engineering projects, engineering project performance evaluation, engineering project communication and coordination purposes and basic principles.

(two) to master the process of comprehensive management of engineering projects, the formulation, implementation and control of project plans.

Fourth, the scope of project management

(1) Be familiar with the concept, basis and achievement of scope definition, basis, method and result of scope confirmation, basis of scope change control and project scope change control system.

(2) Grasp the method of scope definition.

Five, the project management organization

(a) to understand the role and influencing factors of the project management organization, the composition of the project management organization system and technical support.

(two) familiar with the basic principles of project management organization, organizational structure to determine the basis and principles.

(3) Master the establishment steps of management organization and the basic form of project management organization structure.

Six, the human resource management of engineering projects

(A) to understand the characteristics and processes of human resource management in engineering projects, and to build project teams.

(two) familiar with the basic content of human resources management of engineering projects, the role of project managers, and the selection of project managers.

(3) Master the main work of the project manager.

Seven, project bidding management

(a) to understand the basic principles, legal basis and agency system of bidding management.

(two) familiar with the scope and procedures of construction bidding management, as well as the principles of goods bidding management.

(three) to master the role of consulting engineers in bidding management, the main work of project bidding and goods bidding.

VIII. Project Contract Management

(a) to understand the system and model text of the project contract.

(two) familiar with the basic principles and characteristics of project contract management, familiar with the main contents of the project contract and goods procurement contract.

(three) to master the role of consulting engineers in contract management, the performance of goods procurement contracts, the performance of construction contracts and risks.

Nine, the project schedule management

(A) to understand the optimization method of schedule.

(2) Be familiar with the basis, methods and results of work definition, work sequence arrangement and working time estimation.

(three) to master the basis, methods and achievements of the project schedule system, the basis and methods of schedule control, and the methods of schedule adjustment.

X. Project Cost Management

(A) to understand the project cost management procedures, the characteristics of resource consumption plans at various stages.

(two) familiar with the cost structure of the project, resource consumption plan, design budget, construction drawing budget, pre-tender estimate and tender offer basis, methods and results.

(three) to master the basis, methods and results of project cost planning, as well as the basis, steps, methods and results of cost control.

XI。 Project quality management

(a) to understand the purpose and characteristics of quality management of engineering projects, as well as the responsibilities of all participants in quality management.

(two) familiar with the quality management work in the survey and design stage and the construction stage.

(three) to master the quality management and quality standards of consulting results in the decision-making stage of the project, and the basic methods of quality evaluation of consulting results.

Twelve. Project risk management

(a) to understand the basis, methods and results of quantitative risk analysis.

(2) Be familiar with risk factors, objectives and contents of project risk management, basis, methods and achievements of risk management plan, basis, methods and achievements of risk identification, basis, methods and achievements of qualitative risk analysis, basis, methods and achievements of risk response plan and basis, methods and achievements of risk monitoring.

The fourth section "project decision analysis and evaluation" examination outline

Examination purpose

Through the undergraduate purpose examination, students are tested to understand, be familiar with and master the concept, basic principles, basic contents, basic requirements and working procedures of project decision analysis and evaluation. Master the contents, methods, steps, functions and characteristics of market analysis and prediction, scheme design, investment estimation, project financing, financial evaluation, national economic evaluation and risk analysis in project decision analysis and evaluation, and improve the ability and evaluation level of examinees to make decision analysis on projects.

Examination content

I. Overview

(A) to understand the purpose of project decision analysis and evaluation.

(two) familiar with the basic requirements of project decision analysis and evaluation.

(three) to master the basic contents and working procedures of project decision analysis and evaluation.

Second, market analysis and project (enterprise) investment strategy

(a) to understand the purpose and function of market analysis and project (enterprise) investment strategy.

(2) Master market research and forecast, comprehensive analysis of competitiveness and marketing strategy research, and market risk analysis.

Third, the optimal allocation of resources and the evaluation of resource conditions.

(a) understand the optimal allocation and rationality analysis of resources, and understand the general principles of resource utilization.

(two) familiar with the purpose of resource condition evaluation of resource development projects, the basic requirements of resource development and utilization and the content of resource condition evaluation.

Fourth, the construction scheme design

(a) to understand the content, function and requirements of the construction scheme design. Understand the preparation of project schedule.

(two) familiar with the project site selection (factory), production technology, technical route, general plane traffic and public, auxiliary engineering and off-site engineering design of the basic content and requirements.

(three) to master the contents of the overall project plan; Master the content and requirements of product scheme, construction scale, raw material supply and scheme design of main production devices; Master the principles, contents and requirements of energy saving, water saving and environmental protection measures.

Verb (abbreviation of verb) investment estimation

(a) familiar with the scope, content and requirements of investment estimation, and the preparation of the total investment and annual investment plan of the project.

(two) to master the composition and estimation of construction investment (excluding construction period interest), construction period interest and liquidity.

Project financing of intransitive verbs

(1) Understand various financing methods of investment projects and the credit guarantee structure in financing.

(2) Familiar with capital financing and various debt financing methods.

(3) Master the contents and methods of financing scheme design and optimization.

Seven. Financial evaluation

(A) to understand the content and role of financial evaluation.

(two) familiar with the principles, methods, steps and price system of financial evaluation, and familiar with the financial analysis methods of non-profit projects.

(three) to master the determination, estimation and analysis of the basic data of financial evaluation, and to master the content, report preparation, index calculation and judgment of financial profitability analysis. Master the content, report preparation, index calculation and judgment of solvency analysis.

Eight, the national economic evaluation

(1) Understand the concept, function and basic principles of national economic evaluation.

(two) familiar with the national economic evaluation parameters and cost-benefit analysis.

(three) to master the identification of costs and benefits, the estimation of costs and benefits, and the national economic evaluation report and indicators.

Nine. Social assessment and environmental impact assessment

(a) to understand the characteristics, functions and scope of social evaluation. Understand the benefit-cost evaluation method of environmental impact.

(two) familiar with the management framework, objectives, requirements, procedures and contents of environmental impact assessment in China. Familiar with the content and steps of social evaluation.

X. Uncertainty analysis and risk analysis

(1) Understand the concepts of uncertainty and risk and their relationship.

(two) familiar with the identification of project risk factors, project risk estimation and project risk countermeasures.

(3) Master sensitivity analysis and break-even analysis.

XI。 Comprehensive evaluation conclusions and suggestions

(1) Understand the outline and framework of comprehensive evaluation.

(two) familiar with the project decision analysis and evaluation conclusions and suggestions.

The fifth subject "Modern Consulting Methods and Practice" examination outline

Examination purpose

Through the undergraduate purpose examination, students are tested to understand, be familiar with and master the types, characteristics, contents and scope of application of modern consulting methods for engineering consulting. Use cases to assess the ability of candidates to comprehensively use these modern consulting methods to solve practical problems.

Examination content

First, the introduction of modern consulting methods

(a) to understand the types, characteristics and methods of modern consulting methods.

(two) familiar with the collection of information needed for modern consulting.

(three) to master the identification method of information and data needed for consultation.

Second, the project strategy analysis method

(a) to understand the product life cycle and PEST (political, economic, social and technical) analysis methods.

(2) Familiar with competitiveness analysis and matrix analysis methods.

(3) Master SWOT (strengths, weaknesses, opportunities and threats) analysis methods.

Third, the market forecasting method

(1) Understand Delphi method, expert meeting method and analogy prediction method.

(two) familiar with the moving average method, exponential smoothing method, growth curve model method and seasonal fluctuation analysis method.

(3) Master the methods of linear regression, consumption coefficient and elasticity coefficient.

Four. Investment estimation and financing

(a) familiar with the classification estimation method of project investment estimation.

(2) Master the simple estimation method of project investment.

V cash flow analysis and financial evaluation methods

(a) familiar with the basic concepts and basic formulas of the time value of funds.

(two) master the cash flow analysis and financial evaluation methods.

Evaluation method of national economy with intransitive verbs

(A) to understand the method of determining the national economic evaluation price.

(two) familiar with the types and identification methods of national economic expenses and benefits.

(3) Master the analysis methods of national economic benefits and cost flow.

Seven, social evaluation methods

(A) to understand the purpose of social evaluation and participatory social evaluation methods.

(two) familiar with the main methods of social evaluation and social investigation.

(C) Master the application of logical framework analysis method in social evaluation.

Eight, scheme comparison and optimization method

(A) understand the comprehensive evaluation method.

(2) Familiar with value engineering methods.

(C) to master the comparative method of planned economy.

Nine, risk probability analysis method

(1) Understand the Monte Carlo method.

(two) familiar with the risk probability estimation method.

(3) Master the probability tree analysis method.

Ten, the project bidding consultation method

(1) Understand the bid evaluation method of mechanical and electrical equipment.

(two) familiar with the construction bidding evaluation method.

(three) to master the evaluation method of consulting service bidding.

XI. Project Management Methods

(a) to understand the responsibility matrix method, control chart method and program evaluation and review technique.

(2) Familiar with the earned value method in expense management.

(3) Master ABC method in quality management, fishbone diagram analysis method, relationship path method (CPM) and S curve method in time schedule management.