How much is the project supervision fee to be tendered? Let's see.

Engineering supervision refers to the professional service activities that Party A entrusts a qualified supervision unit to supervise Party B's engineering construction on behalf of Party A according to the engineering construction documents approved by the state, relevant laws and regulations on engineering construction, engineering construction supervision contracts and other engineering construction contracts. So what is the project supervision fee for bidding? Let's have a look!

How much is the project supervision fee to be tendered?

For the procurement of services such as survey, design and supervision, if the estimated price of a single contract is more than 500,000 yuan, bidding must be conducted. The estimated price of a single contract is less than 500,000 yuan, but the total investment of the project is over 30 million yuan.

The following construction projects in People's Republic of China (PRC), including engineering survey, design, construction, supervision and procurement of important equipment and materials related to engineering construction, must be subject to tender:

(a) large-scale infrastructure, public utilities and other projects related to social interests and public safety;

(2) Projects that are wholly or partially invested with state-owned funds or financed by the state;

(3) Projects that use loans or aid funds from international organizations or foreign governments.

Engineering supervision bidding process

A, the tenderer shall provide the tender information in the tender preparation stage.

2. Admission registration and tender announcement (5 working days).

3. Submission and filing of qualification documents.

Four, the issuance of pre-qualification documents (5 working days from the date of submission of documents).

Verb (abbreviation of verb) receives the prequalification application documents (8 working days) to carry out bidding agency work.

Six, the organization of expert review, registration of bidding prequalification results.

Seven, the bidding documents for the record, distribution and organization of site reconnaissance.

8. Make an appointment for the bid opening time and room.

Nine, select bid evaluation experts and organize bid evaluation.

Ten, the bid-winning results and bid-winning notice for the record (5 working days).

For more information about project/service/procurement bidding, and to improve the winning rate, please click on the bottom of official website Customer Service for free consultation:/#/? source=bdzd