Time: XX, XX, XX, XXXX.
Venue: XXXX port
Participant: XXXX port co., ltd.
Xx Bureau XX Engineering Co., Ltd.: XXX XXX
Meeting topic: project settlement of XXXX port
Summary: Settlement of yard, road, wharf, discharge pit and levee in XX Port.
This meeting was convened by the construction unit XXXX Port Co., Ltd., presided over by the general manager XXX, and recorded by XX. The meeting lasted two hours. The meeting listened to the report of XXX, the project manager of XX Port of XX Bureau X Engineering Co., Ltd., the construction unit, studied and discussed matters related to the settlement of XX Port, and deployed relevant settlement work. The summary is as follows:
The matters discussed are as follows:
First, the audit of engineering quantity Because the construction party of engineering quantity has completed the verification with the relevant personnel of the owner and reached an agreement, it only needs the signature of the relevant personnel. If Party A needs to re-audit, the construction unit will only provide the bill of quantities and will not check with the owner. If no audit is required, the original auditor (XXX, XXX, XXX) shall sign to confirm the engineering quantity.
Second, the unit price adjustment consultation and confirmation of quantities outside the contract
1, the unit price of the wharf part basically does not need to be adjusted, and the projects designed in the drawings are all reflected in the contract;
2. The unit price of unloading pit has been adjusted according to XXXX year. During the construction of the unloading pit, the prices of reinforced concrete raw materials and commercial mixtures rose sharply. The construction unit requires to adjust the price of reinforced concrete materials and commercial mixtures. After negotiation by both parties, the prices of some steel bars, cement and commercial mixture in the construction unloading pit will be adjusted only after the market price of materials rises. Relevant construction image progress can refer to the monthly construction report, and the material price can refer to the cost information released by Jining quota station.
3, yard, road unit price adjustment
1), the water is stable, and the unit price of interlocking block is adjusted. The unit price adjustment method is the same as the unloading pit;
2) The contract unit price of the material yard and road backfill project has included the expenses of excavation, leveling and rolling within 65,438+0 km. As the materials are provided to us at the site and transported to the place designated by the construction party, the excavation and transportation of the 65,438+0 km project shall be deducted at the time of settlement, and only the actual site leveling and rolling costs shall be calculated. Because the original soil was taken within the range of 1km, it is now used for stone slag and large stones, and the owner's feeding is carried out by surprise at night, which increases the disapproval of the construction unit. After consultation, the price is recalculated with the relevant quota of leveling and rolling;
3) The quantities increased outside the contract shall be signed by relevant personnel on site;
4) The confirmation material price of the unit price outside the flood control wall and dock landing contract shall be carried out with reference to the cost information released by XX quota station during construction;
5), dike unit price adjustment, during the meeting, the construction unit requirements to adjust the dike unit price;
Three. work arrangement
1. Provide the cost information during the construction of the project that needs price adjustment, and the second company collects this information as the basis for price adjustment;
2. The quantities that need price adjustment should be refined and divided according to the progress of the project. The price should be adjusted according to the relevant image progress of the monthly project report, and the quantities beyond the price adjustment time will not be adjusted;
3. The owner's problem of delaying the work put forward by the construction unit will not be confirmed by the construction unit without correct and complete basis; The construction party does not agree. According to the business contact list of the construction party, the owner did not reply and agreed to handle it within 5 days. Manager Li agreed to negotiate with the general manager of Tibet.
4. The unit price of the new project will decrease by 10% after being paid in full according to the relevant terms of the contract (No.16.2-B of the special terms of the contract), and the existing projects in the original tender offer will be implemented according to the decline rate when bidding, and both parties reach an agreement;
5. At the end of XXXXX, it is required to dismantle the temporary housing of the construction unit;
Four. In the disputed price meeting between the two parties, the construction unit questioned the unit price quoted by some construction units. Examples are as follows:
1, the unit price of interlocking block needs to be re-examined when it is reported to 80 yuan /m2 by the construction unit;
2. The cost of coal gangue leveling and rolling needs to be re-examined.
3, other similar subdivisional work comprehensive unit price.
XXXX port co., ltd. engineering department
XXXX-XX-XX
;