Introduction of Christina Railway Line?

Christina Line is a national railway with 1 grade, which is built on a single track and used for both passenger and cargo. It starts from Haitian Station of Delong Tobacco Railway in Changyi City in the north, passes through nine towns (streets) such as Xinhe, Huibu, Zhangshe, Tianzhuang, Mencun, Tonghe, Liaolan, Wanjia and Landi in pingdu city, and connects with Zhilanzhuang Railway Station in gaomi city, the transportation hub of Qingdao Railway. The total length of the main line is about 90.3 kilometers, and the supporting construction and Ji Jiao Railway Relief Line is about 4.5 kilometers, with 5 stations.

Engineering introduction

On August 17, 2009, the Ministry of Railways and the Shandong Provincial Government formally wrote and jointly approved the Christina Railway Project Proposal, which marked a major breakthrough in Pingdu Railway Project. Christina Railway, also known as Pingdu Blue (Village) Railway, officially entered the feasibility study stage.

Christina Railway Line has five stations in Pingdu: Xinhe Station, Pingdu Station, Liaolan Station, Landi Station and Zhangshe Station, of which two stations, Liaolan Station and Zhangshe Station, are reserved. The total length of the planned railway line is 90.3 kilometers, and the estimated total investment of the project is 3.326 billion yuan, covering an area of 693 1 mu, of which the Pingdu section is about 64 kilometers long, with a total land area of 4,300 mu, of which the land area in Pingdu is 3,880 mu. Christina Railway has six stations: Haitian, Xinhe, Pingdu, Landi, Gaomi East and Zhilanzhuang.

After the project is completed, it will connect Ji Jiao, Jiaoxin and Dalonglong, and form a coastal corridor connecting Delongyan, Huang Da, Jiaohuang and Qingdao.

work progress

On the morning of June 27th, 2009,165438+1October 27th, Wang Zhong, secretary of Pingdu Municipal Party Committee, presided over a dispatch meeting to speed up the railway construction in Christina, asking all departments at all levels to further enhance their sense of urgency and responsibility, push forward all work with extraordinary efficiency, and ensure the construction of Christina Railway will start before the end of the year.

On February 29th, 2009, the Ministry of Railways and the Shandong Provincial People's Government approved that Christina Railway could start construction, and the construction plan was finalized. It is reported that the total investment of Christina Railway is 3.326 billion yuan, with a total length of 90.3 kilometers, and five stations will be set up in Pingdu. It is expected that in June this year, the construction unit will officially move in, and the project construction time will be one and a half years.

On March 2010/7, Christina Railway started construction.

20 10 in July, Christina made new progress in railway construction, and the construction drawing audit began to be invited by public bidding. It is reported that the foundation stone of Christina Railway was laid on March 20 18 10. The designer of the newly-built Haitian-Qingdao railway project is China Railway Engineering Consulting Group Co., Ltd., which once designed Qingdao Railway Station and won the Zhan Tianyou Prize for Engineering.

20 10 In September, China Railway Electrification Bureau won the bid for ZH-Ⅰ section of the newly-built Haitian-Qingdao railway project (Christina railway is divided into comprehensive sections), with a contract amount of 2.06 billion yuan. Christina Railway Project will connect Delongyan Railway and Ji Jiao Railway in Jiaodong Peninsula, expand the radiation range and intensity of Shandong Peninsula to Beijing-Tianjin-Hebei region to the north, and connect Rizhao and Lianyungang to the south, thus forming a convenient passage between the Peninsula and Beijing-Tianjin-Hebei-Suzhou-Shanghai region, greatly shortening the time and space distance of relevant areas, effectively promoting the economic and social development of the surrounding areas of Laizhou Bay, and making Pingdu truly a hub city of Jiaodong Peninsula. At the same time, it plays an important role in eliminating the imbalance of internal economic and social development in Qingdao, accelerating the regional economic integration of the peninsula and building a new socialist countryside.

20 10 10, Christina railway Pingdu section completed the table clearing and counting work.

20 10 1 1 month, the renovation and demolition of zhilanzhuang station of Christina railway and the construction of the original facilities of zhilanzhuang station of Ji Jiao railway started.

2010165438+19 October, the first bored pile of Haitian-Qingdao railway was successfully poured. This grouting is the No.57 pier No.3 pile of the cross-Qingxin Expressway Bridge undertaken by the Railway Engineering Branch of China Railway Electrification Bureau Group. The design length of the pile foundation is 38.5m, the design hole depth is 4 1.5 17m, the pile diameter is 1m, and the design length of the reinforcement cage is 23.35m The geological conditions are: silty clay in the upper layer, medium sand and fine sand in the middle, argillaceous sandstone in the lower part, and the bearing capacity of the foundation at the bottom of the pile is 350kpa.

2010165438+122 On October, the work of clearing and releasing meters in the high-density section of Christina Railway began, and the work of clearing and counting meters began.

2010165438+1October 23rd, the first bridge and culvert pile foundation project of Christina Railway was started, and six construction sites including Zhangshe, Huibu, Mencun, Tonghe, Liaolan and Wanjia were set up in Pingdu city.

On February 6th, 20 10, the first piece of prestressed concrete simply-supported T-beam of Jiaozhou Beam Factory, a Haitian-Qingdao railway project undertaken by the first bid section of China Railway Electrification Bureau Group An Railway Engineering Company, was successfully poured, marking the trial production of Jiaozhou Beam Factory. Yu Renpei, the stationmaster of Beijing Tiecheng Railway Engineering Construction Supervision Station, and related personnel, members of the certification guidance group of JIAOZHOU Railway Beam Factory, section chief Huang Tonghua, main leaders of Zhu Baosheng Project Department, all cadres and workers and migrant workers witnessed this important moment.

20 1 1 In March, Christina Railway started construction in succession across Qing Ji expressway Bridge (more than 4,000 meters), Weijiao Highway Bridge (408 meters) and Ji Jiao Railway Bridge.

20 1 1 July, Christina railway Gaomi Mohe Bridge started construction (more than 700 meters). On August 20th,11,16, 10: 25, Christina Railway Zhilanzhuang Station was opened. 16, August 10: 25, the signal reconstruction project of Zhilanzhuang Station of Christina Line, which was undertaken by China Railway Electrification Bureau No.3 Company, was successfully opened 12 minutes ahead of schedule. Since the project started on April 6, 20 1 1, the workers involved in the construction have overcome the influence before the war. The hot weather, construction at night, delay of drawings and other difficulties, overtime, fighting day and night, completed the construction tasks of 20,000m cable trench excavation, 50,000m cable laying, 1 1 switch installation, 23-way signal installation and so on safely and with high quality, which laid the foundation for the smooth opening. Zhilanzhuang Station, which was opened this time, is the connecting station between Christina Railway and Ji Jiao Railway, and the first station of railway construction in Christina. The smooth opening of the station will directly provide track laying and transportation channels for materials and equipment for the future construction of Christina Railway, greatly speeding up the subsequent construction efficiency.

2011At 8: 40 on September 20th, after 16 days' efforts, the third turnout was added in Zhilanzhuang Station of Christina Railway, and the work of inserting and transforming the main line of eight groups of turnout and placing three groups of turnout in situ was successfully completed, which marked the staged victory of this high-risk project of Christina Railway.

2013101710: 28, Christina Railway will be newly built across 309 and Zehe Bridge site in pingdu city, Shandong. With two160t cranes putting the T-beam with a length of 24m and a weight of 99t in place, the task of bridging the main line of Christina Railway has been fully completed, and the whole track has been laid.

20 13 10 3 1 afternoon 14: 40, after 335 minutes of intense construction, the signal interlocking and reverse connection of Haitian station and the opening of the new signal building of Haitian (Qingdao) line, which were undertaken by the third company of China Railway Electrification Bureau, went smoothly 15 minutes ahead of schedule. Haitian Station is an existing station, including four existing tracks and 10 turnouts. The whole station needs to be turned over and transformed into five tracks, and 16 sets of turnouts. Although the engineering quantity is not large, it has been intermittent due to the influence of the construction in front of the station, and no big situation has been formed. Haitian Station is the starting station of Christina Railway, the interface station between Christina Railway and Dalailong Local Railway, and the second station opened for railway construction in Christina. The smooth opening of the station will directly provide track laying and transportation channels for materials and equipment for the future construction of Christina Railway, greatly speeding up the subsequent construction efficiency.

201165438 On October 20th, 2003/kloc-0, the track-laying project of the main line and stations of Christina Railway was declared successful, which provided a strong guarantee for realizing the goal of opening at the end of the year.

20 13, 12, 13, Christina railway is electrified, and the trial operation plan is 12, 26. At that time, the train will run at160 km/h.

It is understood that the engineering construction of Christina Railway has been basically completed, and it is about to enter the stage of comprehensive joint debugging and joint testing, such as track fine adjustment and trimming, static acceptance and dynamic acceptance. According to the person in charge of the railway construction party, after the power transmission, all power supply lines, contact networks, equipment and facilities within the range from Zhilanzhuang (including) to Haitian Station (including), Wu Han Tunxian Station, Gaomi East Station, Pingdu Station and xinhe town Station are electrified.

In order to ensure the safety of power transmission and train operation, and to ensure the safety of the country and people's lives and property, Christina Railway Co., Ltd. recently issued "Instructions for Christina Railway Power Transmission", requiring contractors and people along the railway to inform each other about the electrification of Christina Railway, remind each other, consciously abide by the Railway Law, Regulations on the Safety Protection of Railway Transportation and other laws and regulations, enhance safety awareness, and avoid personal injury and property loss.

20 13, 13 At 8: 58 a.m. on February 26th, Christina railway was delivered as scheduled, and the first thermal sliding test of 17 locomotive was successfully completed. The successful realization of this milestone indicates that Christina Railway is fully prepared for the final sprint stage before opening to traffic. In the process of power transmission, the Third Company of China Railway Electrification Bureau, which undertook the construction, successfully started the Zhangshe traction substation for the first time on the 25th through related tests such as main transformer impact. In the early morning of 26th, after testing that everything was running normally, the full catenary was electrified successfully at 8: 58 by cross-substation power supply, and the thermal sliding test of the first locomotive officially started on the same day 10 and ended successfully on 17. According to the on-site construction personnel, the traction power supply system is the core project in railway construction, and its smooth progress plays a key role in the completion and operation of the project as soon as possible. The dynamic acceptance of Christina Railway will be fully launched on the 27th, and will be officially opened after passing the dynamic acceptance.

Speed up the process

As the weather gets warmer, the progress of Christina Railway accelerates. On April 8th, 20 12, in Liaolan construction section of Christina Railway, it can be seen that the construction workers are busy building the pier of highway bridge, looking north along the pier, and the subgrade filling layer about 2m above the ground is extending into the distance.

It is understood that the land requisition and demolition work of Christina Railway has been basically completed, with 473 construction sites and a total investment of 65.438+0.25 billion yuan, including 875 million yuan for Pingdu section, 9,886 linear meters for bridge and culvert works and 3.55 million cubic meters for subgrade works.

Construction significance

Pingdu city, where Christina Railway passes, is an agricultural city with a large population. With the rapid development of Qingdao's economy, pingdu city has also formed an industrial system dominated by chemical fertilizers, automobiles and machinery manufacturing, and supported by household appliances, food processing, textiles and clothing, and rubber chemicals. Rich in mineral resources and huge potential transportation space.

After the completion of Christina Railway, it will fill the gap that there is no railway in this area, close the links between Shandong Peninsula urban agglomerations, connect Ji Jiao Railway and Delong Tobacco Railway, strengthen the radiation function of Qingdao's central city and promote regional economic integration.