In 20 12, the teaching building and living building of chengdong primary school in wenling city were completed, but the overall project of the school was not completed at that time, so it was impossible to carry out the planning acceptance, and finally failed to pass the completion acceptance. However, it is urgently needed to be put into use. Therefore, before the school started to use, in June of 20 12 and 1 year, Wenling Education Bureau, Chengdong Sub-district Office, Chengdong Primary School, Hangzhou Huaqing Architectural Design Institute, Zhejiang Nonferrous Construction Co., Ltd., Wenling Construction Engineering Supervision Co., Ltd., Zhejiang Dingxing Construction Co., Ltd., Wenling Quality and Safety Station and other main units held meetings at the project site to conduct on-the-spot investigation of the project site. In the form of meeting minutes, five years after it was put into use, from 2065438+2007, 65438+February 2007, Zhejiang Benyuan Testing Technology Co., Ltd., a third-party organization, issued an appraisal report, believing that the safety of the primary school met the use requirements. The whole primary school project was completed in 20 18, but it could not pass the formal project completion acceptance due to the loss of relevant information.
The project completion acceptance shall comply with the relevant laws and regulations and the corresponding engineering construction specifications, standards and contract requirements. The construction unit shall organize the project completion acceptance after obtaining the acceptance documents of the project construction quality, fire protection, planning, urban construction and other units, and issue the corresponding acceptance report.
The State Council Decree No.279 "Regulations on Quality Management of Construction Projects" stipulates in Article 49 that the construction unit shall, within/0/5 days from the date of completion and acceptance of the construction project, report the completion and acceptance report of the construction project and the approval documents or permission documents of the planning, public security, fire protection and environmental protection departments to the construction administrative department or other relevant departments for the record. If the construction administrative department or other relevant departments find that the construction unit has violated the relevant state regulations on the quality management of construction projects during the completion acceptance, they shall be ordered to stop using it and reorganize the completion acceptance. Article 56 stipulates that those who fail to submit the completion acceptance report, relevant approval documents or use license documents for the record in accordance with state regulations shall be ordered to make corrections and be fined from 200,000 yuan to 500,000 yuan.
Before the construction project is put into use, it must be completed and accepted. Now this situation in Wenling Chengdong Primary School is illegal.
Wenling Chengdong Primary School has been put into use for 8 years, but there has been no formal completion acceptance. Although the relevant departments replied that there were no quality problems, there was no formal acceptance report. In case something goes wrong, how to divide the responsibilities and who will bear them may be controversial.
Who should bear the responsibility for the quality problems in the building? Article 3 of the Regulations on Quality Management of Construction Projects clearly stipulates: "Construction units, survey units, design units, construction units and project supervision units are responsible for the quality of construction projects according to law." Therefore, if the house fails to pass the acceptance due to the reasons of the above-mentioned units, they should bear corresponding responsibilities according to their respective professional fields.