1580mm hot rolling project broke ground on June 8th, 2007 and was undertaken by MCC Jingtang Company. By April 29, 2008, the joint hot test was successful, and now the variety debugging, function maintenance and fine-tuning are being carried out. It will be put into production in June and reach the design output in September. 1580mm hot rolling project is a mixed rolling project of stainless steel and plain carbon steel. After completion, the annual production capacity is 2.5 million tons, including 600,000 tons of stainless steel. The thickness of the product is 1.2 ~ 12.7mm and the width is 800 ~1450 mm. The total investment of the project is 65.438+0.5 billion yuan. It is estimated that the annual profit after the project is put into production will be 456 million yuan, and the payback period will be 8.3 years.
The 600,000-ton stainless steel slab continuous casting project broke ground on March 8, 2007, was undertaken by MCC Jingtang Company, and was officially put into production on September 23, 2008. The investment is 940 million yuan. The equipment includes 100t dephosphorization converter,10t aod refining converter,1/0t lf ladle refining furnace, 1 10t VOD vacuum refining furnace and primary1. The equipment of AOD refining converter and VOD vacuum refining furnace is designed by Siemens Weiyi, with world-class technology and equipment, with an annual output of 600,000 tons of stainless steel.
After the completion of the 600,000-ton stainless steel smelting project, the company will form an annual production scale of 2.65 million tons of iron, 3 million tons of steel and 3 million tons of steel.