House and building demolition agreement

Demolition contract of demonstration building

Employer:

Contractor:

Party A entrusts Party B with the demolition of its own house and the removal of muck. In order to clarify the rights and obligations of both parties, through consultation, * * * unanimously agreed to sign this agreement.

One,

Construction content and quantity:

1. Construction content: building demolition, muck removal.

2. Demolition standard: buildings and houses within the scope of demolition shall be demolished, and muck shall be removed to indoor level.

3. pay attention; All kinds of wastes generated in the construction process shall be owned by Party B, and shall be disposed of by Party B itself. ..

Second, the project price and settlement method:

1. Project price: total project price agreed by both parties: RMB.

2. Settlement method: from the date of signing the contract to the completion of the demolition of buildings and houses within the scope of demolition, the muck will be removed to the indoor level, and the project payment will be paid in one lump sum.

Third, the construction date:

1. The contract project is planned to start on and finish on.

2. If the project cannot be started or completed on time due to force majeure or weather, Party A and Party B can reschedule the start or completion date.

Four. Responsibilities and powers of both parties:

Party A:

1. After Party B enters the site, Party A shall make a construction disclosure to Party B, explain the underground obstacles around the construction site and construction precautions, and provide relevant technical data.

2. Responsible for coordinating and cutting off the water supply, power supply, heat source, gas and communication lines leading to the demolition area.

3. Cooperate with Party B to conduct safety education for construction personnel.

4. Party A is appointed as the person in charge of the project, responsible for coordinating related matters in the construction and supervising the whole construction process of Party B. ..

Party B:

1, responsible for the preparation of construction scheme, safety and environmental protection measures.

2. Actively cooperate with Party A's work.

3. Seriously implement the requirements and regulations put forward by the relevant state departments for building construction, so as to achieve civilized construction, safety and timely completion of construction tasks.

4. The construction work must be carried out in strict accordance with relevant laws and regulations, and pay attention to environmental protection requirements: control noise and avoid unsafe factors.

5, responsible for the safety of machinery and personnel, strengthen the safety education and preventive measures for construction personnel, to ensure that the construction is foolproof; And be responsible for the safety insurance of its construction personnel, and Party B shall be responsible for the safety accidents caused by poor management.

6. Obey the command of Party A's on-site management personnel and respect Party A's management system.

7. Party B is appointed as the person in charge of the project, who is fully responsible for the demolition of the project and informs Party A in time.

Information related to project demolition.

Verb (abbreviation of verb) liability for breach of contract:

1. In case of violation of the provisions of this contract, Party A and Party B shall bear their respective responsibilities. All losses caused shall be borne by the responsible party (including economic losses).

2. In case of any dispute during the execution of this contract, both parties shall settle it through negotiation. If negotiation fails, they can bring a lawsuit to the local people's court.

Other intransitive verbs:

1. After the signing of this contract, if both parties have any unfinished matters or modify the terms of the contract, both parties shall reach an agreement through consultation and sign a supplementary agreement.

2. This supplementary agreement and its annexes have the same legal effect as the text of this contract, and both parties shall abide by it.

3. This contract shall come into effect as of the date when the legal representatives or authorized agents of both parties sign and affix their respective official seals.

4. This contract is made in quadruplicate, and each party holds two copies, which have the same legal effect.

Party A: Party B:

On behalf of:

time

Representative: year, month, day and month.

House and building demolition agreement [2]

Project Name: Demolition Project of Zhongzhou Auditorium of Henan Zhongzhou Enterprise Development Co., Ltd.

Date of signing:

Demolition contract year month day

Construction responsibility contract for engineering contracting

Party A: Henan Zhongzhou Enterprise Development Co., Ltd. (hereinafter referred to as Party A)

Party B: Jiaozuo Hong Zhong House Demolition Co., Ltd. (hereinafter referred to as Party B)

In accordance with the Contract Law, Construction Law, Work Safety Law and Demolition Management Regulations, in order to clarify the responsibilities of both parties and ensure the safety and progress of demolition, Party A and Party B have reached the following terms through consultation, which both parties shall abide by.

1. Project name: demolition project of Zhongzhou Auditorium of Henan Zhongzhou Enterprise Development Co., Ltd.;

2. Project location: Zhongzhou Family Courtyard;

Third, the demolition area: about 343 square meters;

Four. Scope of contract: Demolition of the second-floor platform, wing, doorway and stage (within one meter and two meters).

Except;

Verb (abbreviation of verb) Contract term: 2011March17-201April 2;

Contract price of intransitive verbs: RMB 3,000.00 Yuan only;

Seven, engineering quality requirements:

Party B is responsible for dismantling the designated buildings and attachments required by Party A, and cleaning up the dismantled construction waste in time. It is strictly forbidden to throw or dump garbage at will.

Seven. Responsibilities and obligations of both parties

1. Responsibilities and obligations of Party A:

1), Party A is responsible for emptying the items within the demolition scope for demolition.

2) Party A shall be responsible for coordinating the relationship between the relocated households and their surroundings related to demolition, so as to ensure the safe and smooth construction of Party B. ..

3) Party A is responsible for providing accurate underground pipeline information within the scope of demolition.

4) If the construction period is delayed due to Party A's reasons or force majeure, the construction period can be postponed accordingly.

Eight. Responsibilities and obligations of Party B:

1), Party B will pay the deposit (eight thousand yuan) to the account designated by Party A before the construction, and Party A will refund it in full after the completion acceptance.

2) Demolition shall be carried out in a safe and orderly manner according to the construction plan approved by Party A. ..

3) Warning signs should be hung during construction, safety protection measures should be taken, safety isolation belts should be set up, and special personnel should be assigned to patrol to ensure the safety of construction personnel, pedestrians and construction equipment. All safety accidents caused by Party B's responsibility shall be borne by Party B. ..

4), in accordance with the relevant provisions of the state and technical standards, take feasible safety and civilized construction measures to ensure the construction progress.

5), demolition site materials piled up neatly and orderly, to ensure that the demolition site people go by car.

Nine, the project payment method

After the project is completed and accepted by Party A, all the project funds shall be paid within half a year.

X. others

1. Matters not covered in this contract shall be settled by both parties through consultation.

2. This contract shall come into effect after being signed by both parties. After the project is completed, the contract content is executed, and the project price and various expenses are settled, the contract will automatically become invalid.

3. This contract is made in quadruplicate, with Party A and Party B holding two copies respectively, and shall come into effect as of the date of signature and seal by both parties.

Party A: (Seal) Party B: (Signature)

Legal representative: (signature) Legal representative: (signature)

Year, month, sun, moon, sun.

House and building demolition agreement [3]

written agreement

Party A: (hereinafter referred to as Party A) Legal Representative:

Party B: the owner of the demolished house: (hereinafter referred to as Party B) In order to speed up the construction of small towns and improve the living conditions of urban residents.

Environment, improve the comprehensive service function of market towns, promote the economic development of market towns and the construction of public welfare undertakings, and improve people's living standards. According to the overall planning of the market town, the houses in the street control line in the planning area will be demolished, and the buildings of your household will be demolished according to the relevant laws, regulations and documents of the state and Yunnan Province, and compensation will be made according to the document No.2001. * * * * Issued by the People's Government Office [20 15] 10. In order to clarify the rights and interests of both parties, Party A and Party B reached an understanding on the compensation of the house and the attached objects on the ground through consultation, and reached the following agreement:

I. Compensation for Buildings and Appendices

2. Party A shall pay all compensation fees to Party B in one lump sum according to the compensation method, totaling.

RMB in words: whole (in figures: RMB).

3. After both parties sign, Party B shall not interfere with Party A's normal construction and make trouble without reason. If Party B interferes or prevents it, all responsibilities shall be borne by both parties.

Four. Demolition time of the house, building and accessories: from (20 15) to (20 15), Party B will demolish the house by itself; If it is not dismantled within the time limit, Party A will organize relevant department personnel to dismantle it.

Verb (abbreviation of verb) Party A reminds Party B that safety must be paid attention to when houses, buildings and accessories are demolished, and any safety accidents related to demolition shall be borne by Party B. ..

6. Party A promises that if Party B completes the new building on the homestead plot outside the street control line after house demolition before 20 16 12 3 1, the supporting fee for village building infrastructure will be charged by half.

7. Party B's family members unanimously agree that the signatory is the representative of Party B's family members, who will sign and seal the agreement document, and all expenses paid by Party A to Party B will be collected by Party B's representative, and Party A will not be responsible for all disputes between Party B's family members.

Eight. This agreement is made in duplicate, one for each party. This agreement shall come into effect as of the date of signature by both parties. After this agreement comes into effect, neither party may modify or terminate this agreement without authorization.

Party A:

Legal Representative: Representative of Party B:

Signature of participants:

Date and month of 20 15 year