Summary of completion work
District Party Committee and District Government:
In order to implement the "four aspects" of water environment management in the "one lake and two rivers" basin, further deepen the management of Dianchi Lake, do a good job in the collection and treatment of urban domestic sewage in Dianchi Lake basin, effectively control and manage the source of sewage, improve the level of sewage resource utilization, and reduce the pollution load entering the lake. Wuhua District Urban Domestic Sewage Collection and Treatment Leading Group Office (hereinafter referred to as "District Sewage Office") has completed the collection and treatment of urban domestic sewage in Wuhua District in strict accordance with the spirit of the Notice of Kunming Municipal People's Government on Approving the Work Plan for the Construction of Comprehensive Sewage Interception Collection and Treatment Facilities in Dianchi Lake Basin and a series of requirements of the municipal party committee and municipal government, through careful and effective arrangements, effective work measures and solid and effective work style.
First, careful deployment, clear responsibilities, and comprehensively start the "pollution control" work.
According to the requirements of the municipal party Committee and the municipal government for comprehensive sewage interception, collection and treatment in Dianchi Lake Basin, the District Sewage Office attaches great importance to it, and in accordance with the working idea of "focusing on one goal, implementing two guarantees, highlighting three key points and paying close attention to four measures", strengthens organizational guarantee, decomposes objectives and tasks, clarifies responsibilities, further clarifies work responsibilities, and strictly follows the management system of combining assessment mechanism with the completion of objectives and tasks.
The second is to improve the mechanism, pay close attention to quality and strengthen safe and civilized construction.
(A) in-depth investigation, brainstorming, optimization design
In order to better make the planning and design scheme close to reality, reduce the design changes in the project implementation process, and realize the smooth implementation of the optimized design scheme and project, engineers and technicians are sent together with the planning and design units to conduct field visits one by one, listen carefully to the opinions of the people in the districts (units) involved in the project, understand the difficulties that may be encountered in the project promotion process, brainstorm, and urge the planning and design units to integrate reasonable public suggestions into the design scheme, so as to maximize the realization of community. Adhering to the principle of "unified design and step-by-step implementation", the District Water Affairs Bureau organized professional design units to design the courtyards of various residential quarters, put forward practical technical schemes for rain and sewage diversion, and then submitted the transformation scheme to the office for implementation, mobilizing units and residential quarters to implement the internal rain and sewage diversion transformation to the maximum extent, which laid a good foundation for the smooth development of the next work.
(two) to build a mechanism to supervise the implementation and standardize management.
In order to strengthen the implementation and management of rainwater and sewage diversion and reclaimed water utilization facilities in Wuhua District, the comprehensive management guarantee mechanism of the project is strictly implemented: First, the first batch of promotion mechanisms are strictly implemented. Start the 5 1 unit (community) courtyard rain and sewage diversion reconstruction project from point to area, sum up experience, improve the work and popularize it in an all-round way on the basis of the completion of the previous pilot; The second is to strictly implement the construction management mechanism. Implement the management mechanism of weekly regular meeting, weekly report, weekly supervision and semi-monthly summary. In addition to the weekly meeting, special meetings and on-site supervision should be held to solve the problems existing in the promotion in time. The third is to strictly implement the comprehensive coordination mechanism, set up a comprehensive law enforcement agency to enforce the law, strictly enforce the law, and investigate and deal with some illegal sewage units according to law. Fourth, strictly implement the supervision mechanism, and increase the management and follow-up inspection of processes and links in accordance with the accountability regulations for domestic sewage collection and treatment; Fifth, strictly implement the acceptance mechanism, and comprehensively promote the completion and acceptance of the courtyard rain and sewage diversion project in our district in accordance with the principle of completing a batch of acceptance.
In order to make the whole process of the project from project establishment to implementation open and fair, the project cost budget and public bidding procedures are carried out in strict accordance with the relevant requirements of national project management, and the whole process is open, fair, legal and reasonable in strict accordance with the project management and administrative examination and approval authority.
(three) strict requirements, rectification within a time limit to ensure quality.
In order to conscientiously implement the requirements of the municipal party committee and municipal government on "three highs, three modernizations and three refinements" in municipal infrastructure construction, strengthen supervision and inspection, and establish a quality inspection mechanism. The daily quality is inspected and monitored by the technicians and supervisors of the Water Affairs Bureau around the clock, and the next working procedure can only be started after the problems are found and rectified immediately, and the weekly "quality inspection day" is fixed to ensure that the construction is carried out in strict accordance with the quality standards. Through inspection, it was found that some units failed to meet the construction standards, the quality could not meet the requirements, the rain and sewage diversion was not complete, and the road excavation and recovery were unqualified. Check with the construction unit and supervision department at the site, and immediately rectify the specifications that can be rectified at the site, and issue a rectification notice for those that cannot be rectified at the site, and rectify within a time limit according to the specifications.
Through the inspection, the sub-district office is requested to attach great importance to the quality of the courtyard rain and sewage diversion reconstruction project and the principle of safe and civilized construction, strengthen the management of the design, construction and supervision units, give feedback and notification to the units (communities) that need rectification in the inspection of various construction departments, and strengthen the supervision and rectification. For the recently completed and under construction projects, it is necessary to do a good job of self-examination and filing, and report the rectification to the office of the leading group for urban domestic sewage collection and treatment in Wuhua District according to the time limit to ensure that the project meets the specification requirements.
(four) to speed up the progress, safe construction, civilized construction.
In order to speed up the progress of the project and ensure the smooth completion of the courtyard rain and sewage diversion and the construction of reclaimed water utilization facilities in Wuhua District, the District Sewage Office carefully organized and paid close attention to the progress, urged the construction unit to strengthen on-site management, improve work efficiency, complete the task within a time limit, earnestly implement the rectification measures, track the rectification effect in time, and ensure the realization of the objectives and tasks set by the municipal party committee and government on the premise of ensuring the quality of the project construction.
In accordance with the requirements of the Law on Work Safety and the Regulations on the Administration of Work Safety in Construction Projects, and the principle that quality is life and safety is the soul of the project, we will constantly improve the quality and safety supervision mechanism, improve the quality supervision system and procedures, implement the responsibility system for project quality and safety, and comprehensively strengthen quality inspection. At the same time, strengthen the propaganda work of safety production, vigorously carry out the training of safety production knowledge, strengthen the supervision and inspection of safety production behavior, carefully investigate the dangerous sources on the construction site, and put an end to all kinds of safety production accidents.
Third, vigorously promote, ensure quality, and fully accomplish the objectives and tasks.
The municipal level issued 643 tasks of rain and sewage diversion and reclaimed water facilities construction in Wuhua District. Through careful organization and close cooperation of all units, the rain and sewage diversion of 643 family houses and the main project construction of reclaimed water facilities were completed by the end of 2010/30. In order to improve the effect of rain and sewage diversion in the hospital and ensure the quality of the project, the inspection team was organized to conduct a comprehensive self-inspection at the end of 65438. The approved investment was 65.438+0.4 billion yuan, and 654.38+035.4 km of sewage pipes and 654.38+028.6 km of rainwater pipes were newly built and renovated, with a completion rate of 654.38+0.00%. During the construction of courtyard rain and sewage diversion and reclaimed water utilization facilities in Wuhua District, our district pays close attention to quality, safe production and the effect of rain and sewage diversion. The construction progress and scale have always been in the forefront of the city and have been well received by city leaders.
Fourth, the existing problems
During the construction of courtyard rain and sewage diversion and reclaimed water utilization facilities in our district, various project management systems and project promotion measures have been implemented. Although the project has been fully completed, there are still some problems that need further coordination and work docking.
(a) the construction of municipal pipe network is incomplete, which affects the effect of rainwater and sewage diversion in the hospital.
The municipal pipe network in the Second Ring Road is not matched, and the pipe network in some sections of the city is not perfect or even has no pipe network. The rainwater and sewage pipe network constructed by some units in our district cannot be discharged smoothly through the municipal pipe network, and only a few places discharge sewage in the form of mixed rainwater and sewage discharge, which affects the implementation effect of rainwater and sewage diversion in our hospital.
(B) Project funds are tight, which affects the progress of project completion and acceptance.
The construction of urban domestic sewage facilities in our district involves many aspects, including old residential areas, restructured bankrupt enterprises and public houses by units. Heavy workload and limited financial support. Near the end of the year, the construction unit asked for the project payment many times, but the project payment payable to the construction unit in the early stage could not be put in place, and the wage problem of migrant workers has not been solved. In order to avoid the occurrence of large-scale abnormal collective wage-seeking events, the higher authorities are being requested to allocate relevant funds as soon as possible, which will affect the completion of the courtyard rain and sewage diversion project in our district.
(3) There are many illegal sewage treatment points, and it is difficult to promote the work.
In order to consolidate the effect of courtyard rain and sewage diversion project in our region, illegal sewage treatment work was carried out in the whole region. Due to the wide coverage and heavy tasks, it is necessary to monitor illegal sewage discharge around the clock, and the pressure on personnel and funds is enormous. For shops and residents who don't understand or support their work, we should patiently persuade them and increase publicity. Illegal sewage treatment is a long-term treatment project, and it is difficult to persist in promoting and improving the comprehensive treatment effect for a long time.
Verb (abbreviation for verb) subsequent steps
In order to complete the completion acceptance of rainwater and sewage diversion and reclaimed water utilization facilities in Wuhua District as soon as possible and consolidate the implementation effect of rainwater and sewage diversion, the work will be carried out from the following aspects:
(a) proactive, strengthen communication, complete the supporting.
Actively connect with Yunnan Investment Company and other municipal units. According to the recent planning arrangement of Kunming municipal rain and sewage pipe network construction, combined with the situation of courtyard rain and sewage diversion and reclaimed water facilities construction in our district, the rain and sewage diversion pipe will be connected to the municipal main pipe network as soon as possible in view of the area where the rain and sewage diversion effect is affected by the mismatch of municipal pipe network system, so as to give full play to the benefits of the rain and sewage diversion reconstruction project and reclaimed water utilization facilities construction project in our district.
(two) to strengthen supervision, ensure quality, strict acceptance.
In the project construction work, we will strictly follow the relevant provisions of the national safe and civilized construction and the requirements of "eight hundred percent", strengthen supervision, realize full coverage of supervision by functional departments, standardize project management, realize full coverage of project quality and safety responsibilities, ensure safe and civilized construction, and put an end to safety accidents. At the same time, actively cooperate with the higher authorities to apply for project funds as soon as possible and allocate them to relevant units, improve the final accounts of completion in time and speed up the progress of project rectification, and conduct acceptance of the projects to be accepted in strict accordance with relevant state regulations.
(3) Vigorously publicize and intensify publicity to ensure actual results.
Vigorously promote the special rectification work of illegal sewage discharge in our district, we must decompose the tasks and objectives layer by layer, implement them item by item, and put the responsibility on people, so as to truly grasp the details, grasp the depth and grasp thoroughly. At the same time, we should intensify publicity, adopt various forms such as media, government and society to publicize the importance of pollution control and water environment protection in Dianchi Lake Basin, give full play to the organizational role of the community, mobilize units and the masses to participate in pollution control, win the support and understanding of the masses, and create a good atmosphere for pollution control and long-term management.