The pile foundation project cannot be contracted separately. The law stipulates that the pile foundation project is a sub-division project of the foundation and foundation division, and the general contractor is allowed to legally subcontract the construction to a professional team with professional qualifications. However, the construction party cannot dismember and issue independent contracts. Therefore, the pile foundation project cannot be contracted separately.
Legal Basis
Article 12 of the "Measures for Bidding and Bidding for Engineering Construction Projects"
Engineering construction projects that must conduct construction bidding according to law have one of the following circumstances Construction bidding is not required:
(1) Special circumstances involving national security, state secrets, emergency rescue and disaster relief, or the use of migrant workers for work-for-relief projects using poverty alleviation funds are not suitable for bidding;
(2) The main construction technology adopts irreplaceable patents or proprietary technologies;
(3) Investors in franchise projects selected through bidding are able to construct by themselves in accordance with the law;
(4) The purchaser is able to construct by himself in accordance with the law;
(5) For additional small-scale auxiliary projects or main layer addition projects to the project under construction, the original winning bidder still has the ability to contract, and The responsibility of others will affect the construction or functional supporting requirements;
(6) Other circumstances stipulated by the state.