3 Sample Essays on Safety Protection Measures Plan

Protective and equipment measures must be taken in every possible way to prevent casualties and serious injury accidents, and give full play to the role of workers. Below I have compiled a safety protection measure plan for your reference.

Safety Protection Measures Plan Sample 1

1. Organizational Guarantee Measures

(1) The project management department is established with the project manager as the first responsible person for production safety The leadership team includes the heads of each business department, and the safety and quality department is equipped with full-time safety engineers.

(2) The construction team shall establish corresponding safety production management departments, staff safety management personnel, and establish networks at all levels to achieve "specialized management of lines and group management of areas."

(3) Establish a regular and irregular inspection system for production safety. Conduct inspections on production safety every month, conduct major inspections every quarter, evaluate and score, and honor rewards and penalties.

(4) Do a good job in safety job training. Before starting work, all employees should be educated on safety knowledge and trained in batches. Each person should participate in safety training no less than twice, and each time should be no less than four hours. , print and distribute the relevant safety operating procedures to all grassroots units, check them, and implement them accordingly. All personnel in special industries must hold certificates to work. (5) Accept the supervision, inspection, and evaluation of safety production from owners and supervisory units at any time, and timely determine and organize the implementation of plans for issues raised to ensure safe production.

2. Guarantee measures for ideological construction

(1) All construction personnel strictly implement the relevant national guidelines, policies, decrees and regulations on production safety, and teach themselves to abide by the management regulations related to production safety.

(2) Enhance the safety awareness of all employees. Conscientiously implement the policy of "safety production, prevention first", lay a good safety foundation, enable all levels to clarify their own safety goals, formulate their own safety plans, achieve the purpose of full participation and full implementation, and embody "safety production, The principle of everyone’s responsibility.

3. Specific guarantee measures

(1) Edge protection measures and plans for operations at high and low locations a. All operating personnel, administrative, visiting, surveying, and supervisory personnel shall enter the site Wear a safety helmet, and those who climb heights must wear safety belts and non-slip boots.

b. Set up a fence in the construction area, strictly prohibit idle personnel from entering, and use partition walls to separate it from the outside world.

(2) Construction electricity protection measures

a. Establish an electrical installation and use management and economic responsibility system. The Safety and Quality Department is the department in charge of electrical safety management and is responsible for electrical installation and Use management work. Full-time safety officers are responsible for patrolling, supervising and inspecting, and professional electricians are responsible for electrical safety at the construction site.

b. After entering the site, professionals will be responsible for preparing the construction power organization design, including the setting of power distribution devices and their capacity, the direction of distribution lines and the setting of on-site lighting, living, Based on the electricity load of production facilities, we should prepare targeted electrical safety technical regulations.

c. A standard power box uniformly stipulated by the construction site equipment industry. After the installation of electrical circuits and electrical equipment is completed, they will be put into use after being inspected and accepted by the competent department.

d. Frequently conduct safety inspections and tests on electrical equipment, test leakage switches and grounding resistance once a week and keep written records. If problems are found, rectify them in a timely manner.

e. Professional electricians must hold certificates to work. Electricians have the right to refuse to execute work instructions that violate electrical safety regulations, and safety officers have the right to stop violations of electrical safety, and illegal instructions and illegal operations are strictly prohibited.

(3) Safety protection measures for mechanical equipment

a. Mechanical equipment operators (or drivers) have received special training and are familiar with the mechanical performance. After passing the examination and obtaining the operating license or driving license Operate on the machine (car).

b. Machinery operators and commanders must strictly abide by safe operating technical regulations, concentrate on work, work carefully, do not leave their posts without authorization, and do not drive under the influence of alcohol.

c. Mechanical equipment should be repaired promptly after failure and never run without failure.

d. Machinery operators should keep various records accurately and timely, strictly implement the routine maintenance system, and conscientiously implement the cross operation method of cleaning, lubrication, anti-corrosion and safety.

(4) Material safety assurance measures

a. Set up a warehouse for materials and accessories at the construction site, manage the materials in a unified manner, and build a warehouse with corresponding functions according to the storage requirements of the materials. They are stored in separate categories, with clear signs in front of the door and complete fire-fighting equipment. b. The warehouse has dedicated personnel responsible for storage and care. (5) Safety production in-house work

Safety production? Five pictures and one sign? Posted on the wall, make safety technical briefings every day, and everyone will sign before starting work.

4. Carry out safety standard competitions and implement reward and punishment measures

In conjunction with safety production competitions, actively participate in safety standard construction site construction and window creation activities organized by owners, and punish those who violate operating procedures or If an accident occurs, a fine of more than three times the economic loss will be imposed, and the relevant personnel and leaders will be held accountable

Safety protection measure plan sample 2

Do a good job in civilized construction, environmental protection, and prevention pollution and maintain ecological balance. During construction, we conscientiously abide by the country's current relevant environmental protection laws, strictly control new pollution and gradually control old pollution, adhere to the principle of "prevention first, combine prevention and control, comprehensive management, and turn harm into benefit", and adopt favorable measures to prevent pollution and Destroy the natural environment.

1. Prevent soil erosion and waste disposal

(1) Waterproofing and drainage: Always maintain good drainage conditions at the construction site during construction, and build temporary drainage with sufficient drainage sections. Drainage channel and connected to permanent drainage facilities to prevent siltation and erosion. The construction layout should utilize the construction site as much as possible to reduce damage to cultivated land, avoid water and soil erosion, and maintain ecological balance.

(2) Waste material and waste disposal: Clean up the waste at the site and the waste from earthworks without affecting the drainage and irrigation system and farmland water conservancy facilities.

2. Prevent and reduce water and air pollution (1) Protect water quality

a. Construction wastewater and domestic sewage shall not be discharged into farmland, cultivated land, drinking water irrigation channels and reservoirs, etc.

B. When flushing aggregates or operating water containing sediments, take measures such as filtration and sedimentation treatment to ensure that the discharge meets standards.

(2) Control dust

a. For dust generated during construction operations, in addition to special labor protection supplies for those working on site, water should be sprinkled at any time to minimize dust pollution. degree.

b. Fine materials or bulk materials that are likely to cause dust should be covered or sprinkled with water appropriately.

Cover with canvas, covers or similar items when transporting. Do not burn all kinds of garbage and waste at the construction site.

(3) Reduce noise and exhaust gas pollution

a. Various temporary facilities, stockpiles, processing plants, etc., shall be constructed according to the standards in the location and form approved by the construction organization design.

b. Reasonably distribute the workplace of power machinery and equipment to avoid running too many power machinery and equipment in one place. Construction noise is controlled within the allowable decibel value stipulated by the state.

Sample three of construction site safety protection measures

1. Technical measures for safe use of electricity

1. All electrical machinery and electrical equipment are protected from zero. Dedicated PE protective wiring is reliably connected to the on-site grounding device. There should be no less than three groups of grounding devices on site with a grounding resistance no greater than 4Ω. The area of ??the protective PE line from the total box to the sub-box shall not be less than 10mm2, and the area from the sub-box to the equipment shall not be less than 2.5mm2. The copper core wire shall be multi-strand insulated wire.

2. The electricity system at the construction site adopts TN-S to meet the safety requirements of three-level power distribution and two-level protection. The main distribution box does not have a leakage protector with an operating current of 150mA/S that meets the requirements. The equipment The switch box device is equipped with an operating current less than 30mA/S, and the equipment switch box is equipped with a safety device with an operating current less than 30mA/S.

3. All power distribution, power switch boxes, and five-core cables use recommended products.

4. Electricians are responsible for the installation, commissioning and maintenance of all electrical equipment lines.

5. Establish a safety inspection and evaluation system, and the competent departments of the enterprise will regularly inspect and evaluate the on-site electricity safety situation of the construction team.

6. Establish a responsibility system for safe electricity use, and separate the operation, supervision and maintenance of temporary power-using parts.

7. Be practical. In detail, the mechanical operators must ensure that the nut protective covers and fuses in the switch box are not lost or damaged, and must be kept correct and intact at all times.

8. Establish a safety education and training system and a safety technical communication system, and conduct regular training and education on safe electricity use for professional electricians and operators of various electrical operations. Those who pass the assessment will be employed with a certificate; those who fail the assessment three times will be transferred from their jobs.

2. Lifting and hoisting safety technical measures

1. Personnel performing hoisting operations must wear safety helmets and safety belts when working at heights. It is strictly prohibited to operate under the influence of alcohol.

2. Make a safety technical briefing before work, formulate a detailed construction plan and construction sequence, and inform all participating workers to understand their own work content and safety areas, and assign a dedicated person to supervise safe production. Non-operators are strictly prohibited Enter the work area.

3. Check the rigging and tools to meet safety technical requirements, unify command signals, divide safety areas, and assign dedicated personnel to supervise safe production. Non-operators are strictly prohibited from entering the operation area.

4. When operating, the mechanical operator must conduct a trial lifting according to the equipment performance, lifting weight, and how much, determine the center of the lifting point, and ensure that the balanced lifting is in place. Overweight lifting is strictly prohibited, and objects of unknown weight should be checked. Only after clearing the weight and reporting to the relevant command personnel for approval can the operation be carried out according to the scheduled plan.

5. When lifting, it is strictly forbidden for unrelated persons to stay or pass under the boom and within the swing range of the hoist and boom. When working across the upper and lower parts, protective isolation measures must be installed in the middle.

6. When hoisting with multiple lifting points, it is necessary to prevent the hanging parts from being damaged due to uneven stress. Hoisting should be carried out according to hoisting technology and hoisting measures.

7. When lifting, it is prohibited to place or hang loose objects on the hanging parts.

8. During the hoisting period, hoisting work is prohibited in case of strong wind, heavy snow, or heavy rain. Sufficient lighting must be provided during night construction.

9. It is strictly forbidden to hang heavy objects in the air for a long time. When taking a break or leaving during operation, the hanging objects should be dropped to the ground.

10. Anti-collision measures should be formulated when multiple lifting equipment are operating at the same time on the construction site.

3. Technical measures for safety and fire protection

1. Electrical fire protection:

⑴ Reasonable configuration and setting, replacement of various protective electrical appliances, and maintenance of circuits and equipment Reliable protection against overload, voltage loss, leakage and short circuit faults.

⑵. Inflammable, explosive and highly corrosive media are not allowed to be piled around electrical devices and circuits, and fire sources are not allowed to be used casually.

⑶ In locations where electrical devices are relatively concentrated, such as substations, distribution rooms, generator rooms, etc., appropriate fire extinguishing equipment should be installed and fireworks should be prohibited.

⑷ Strengthen the insulation between phases and poles of electrical equipment to prevent flickering.

⑸ Set up reasonable lightning protection and lightning protection measures.

⑹ It is strictly prohibited to stop or transmit power under load.

⑺Select explosion-proof electrical equipment in flammable and explosive places.

2. Fire prevention at the construction site

⑴ Divide key fire prevention areas, assign special personnel to take charge of key areas, and configure no less than two foam fire extinguishers, 0.5 cubic sand pool, 1 cubic meter in the carpentry shed Pool and fire barrel milling. Firefighting equipment is not allowed to be used for other purposes.

⑵ The sawdust produced in the carpentry shed every day will be cleared and transported by special personnel to keep it clean.

⑶Hang no fireworks signs and fire prevention responsibility system signs.

⑷The wood drying furnace should be built in a designated location, away from fire sources, and designated personnel should be on duty and supervised.

⑸A smoking room will be set up on site, and smoking and fire are not allowed in the fire prevention area on site.

3. Warehouse fire prevention

⑴No one is allowed to smoke on the bed in the dormitory, and there is a dedicated person in the dormitory responsible for supervising fire prevention.

⑵ Lighting fixtures larger than 60W are not allowed to be installed in the dormitory. Electric stoves and fires are not allowed to be used for cooking, and tungsten lamps are not allowed to be used for lighting.

⑶ Special electricians have to install sockets for using electric mattresses and electric fans.

4. Electrical welding operations

⑴ The cutting and welding operation site must establish safety and fire prevention measures, be equipped with fire-fighting equipment, have dedicated personnel to supervise, and strictly follow the approval procedures for fire operations.

⑵ If there are flammable items under or around the working site, clean them up first or take isolation measures before working.

IV. Safety technical measures against object strikes

1. Personnel entering the construction site must wear safety helmets, and non-staff members are not allowed to enter.

2. Set up double-layer protective partitions for upper and lower crossing operations.

3. Set up a safe passage protective shed for the doorway where pedestrians pass below.

4. The upper and lower items must be pulled up and down with ropes or special containers and are not allowed to be thrown.

5. The garbage cleaned on the floor must be bagged and transported.

6. The floor joints should be sealed tightly with bricks or wooden boards to prevent falling objects from injuring people.

5. Safety technical measures to prevent falls from heights

1. Safety belts must be fastened when working at heights, so that they can be hung high and used low.

2. The first floor of the main masonry building is equipped with a flat anti-fall net, and thereafter an external vertical net is installed every second floor for complete enclosure.

3. Preserve openings for construction, fill in the gaps with cast-in-place floor slabs, and cover them tightly with wooden boards in time to support them firmly.

4. Before the unpoured concrete railings leading to the balcony, set up fixed steel bars or wooden railings at the door to block the door.

5. The elevator shaft door is equipped with a steel or wooden fixed fence, the elevator shaft is equipped with an anti-fall safety net every two floors, and the protective platform on the construction floor is tightly sealed with boards.

6. In front of the unwelded formal railings of the stairs, use 45-diameter steel pipes to set up protective railings and hang safety nets to close them.

7. The eaves and edge work are fully enclosed, and the protective frame is one step higher than the working floor.

8. Set up two protective railings on the steel pipes around the floor of the frame project and seal them with vertical nets.

9. Set up guardrails with a height of not less than 1.3 meters around the unloading platform and seal them with vertical nets.

10. All protective facilities used at the construction site may not be dismantled or misappropriated without the consent of the person in charge.

VI. Safety Technical Measures to Prevent Mechanical Injury

1. When machinery at the construction site is allowed to rotate, the transmission parts must have protective covers that meet the specified requirements.

2. The electric saw must use double-layer steel mesh insurance and protective baffles. Install a toothed wedge cutter 10-15mm away from the teeth behind the saw blade. Cover the saw with a protective cover when not in use.

3. For electric planers, the protective cover must not be smaller than the width of the planer blade.

4. The winch drum must have a device to prevent the wire rope from slipping off. Female workers are not allowed to have long hair when operating machinery. The wire rope must not drag the floor and must be protected when passing.