1) Before the scaffold is erected, the necessary site shall be leveled and compacted to ensure sufficient strength of the foundation and avoid the subsidence and deformation of the scaffold foundation.
2) Strictly control the entry quality of scaffold materials, use steel pipes and fasteners that meet national standards, and be controlled by the technical, quality inspection and material departments. Inferior products are strictly prohibited from entering the construction site.
3) Scaffolding must be completed by professional scaffolder, who must hold relevant certificates and be implemented in strict accordance with technical design requirements and safety technical disclosure.
4) Operators must strictly abide by the safety operation procedures for aerial work, and all kinds of tools and appliances used should have protective measures to prevent falling. It is forbidden to throw all kinds of tools and materials down at will.
5) During erection, bracing must be added to the periphery of the scaffold to ensure that the scaffold is solid and reliable as a whole.
6) Fasteners and bolts must be installed and tightened during construction, especially the quality of fasteners and bolts connected with vertical rods must be firm and reliable, and the quality of use must be checked by special personnel.
7) Scaffolding operation shall not be carried out at night or in bad weather.
8) Anyone who suffers from hypertension, heart disease and is not suitable for aerial work is strictly prohibited.