What are the budget items for general street lighting projects?

1. Mainly includes: transformer installation, combined box-type substation installation; power capacitor installation; production and installation of high and low voltage distribution cabinets, distribution boxes, and covers; fuses, controllers, and starters , shunt installation; terminal welding and pressure installation.

2. The sleepers, insulated wires and asbestos cloth used for transformer installation are amortized according to a certain depreciation rate. If the actual amortized amount does not match the quota, no conversion will be made.

3. Transformer oil is considered based on equipment, but the filtration loss and operating loss of the transformer oil during construction have been included in the relevant quota. 4. The installation quotas for high-voltage complete sets of power distribution cabinets are compiled with comprehensive considerations, and no conversion will be made during implementation.

5. The installation of power distribution and control equipment does not include the production and installation of brackets and basic steel sections, nor does it include the installation of equipment components and external wiring of terminal boards. Corresponding quotas should be implemented separately.

6. The production and installation of iron components is applicable to the production and installation of various brackets within the scope of this division, but the production and installation of iron components does not include galvanizing. Light iron components refer to components with a thickness within 3mm.

7. Each equipment installation does not include terminal blocks and secondary wiring. 6. Overhead line engineering:

2. Terrain division:

(1) Plain area: refers to an area with relatively flat terrain and relatively dry ground. (2) Hilly areas: refers to areas with undulating terrain such as low hills and mounds. (3) General mountainous areas: refers to general mountains, valleys, plateaus, etc.

3. The amount of one-time line construction work is considered based on more than 5 poles, and the quota of man-days and machinery within 5 poles is multiplied by a factor of 1.2. 4. Conductor crossing:

(1) When there are two or more crossing objects in the same span, each crossing object will be regarded as "one" crossing, and the quota will be applied respectively. (2) Single-line broadcast lines are not considered crossing objects.

5. The cross arm installation quota includes labor for installing hardware and insulators.

6. The foundation sub-item is applicable to the foundation projects for street light pole towers, metal lamp posts, and control boxes. The relevant quotas apply to other concrete projects. 7. Excavation and filling of light pole pits will be charged separately. 7. Cable engineering:

1. Including commonly used cable laying below 10kV, not considering cable laying in rivers and water areas, underwater, underground and other conditions.

2. When cables are directly buried in mountainous and hilly areas, the fixed working days are multiplied by a coefficient of 1.3. The materials required in this area, such as fixed piles, clamps, etc., are calculated based on actual conditions.

3. The additional length of the waveform and the reserved length are not taken into account in the cable laying setting amount. This length should be included in the engineering quantity. 4. This division does not include the following work contents: (1) Production and installation of thermal insulation layer and protective layer. (2) Winter construction heating work of cables.

5. The fixed man-days and machinery for the production and installation of copper core cable heads are multiplied by a factor of 1.2. 8. Lighting equipment installation project:

1. Mainly includes the installation of various cantilever lights, square lights, high pole lights, garden lights and lighting components. 2. The wiring of various lamp stand components and appliances have been comprehensively considered within the quota and will not be adjusted during use. 3. All lamp posts must be wired with corresponding piping and wiring quotas.

4. The factor of high-altitude operations within 10m has been taken into account. If the installation height exceeds 10m, the labor quota shall be multiplied by a factor of 1.4. 5. Includes the use of instruments to measure insulation and test lighting of general lamps.

6. Does not include the production of cable joints and the soldering and crimping of wire terminals. If actually used, the quota of the relevant segment can be applied.

7. The reserved wires for switches, sockets, buttons, etc. have been integrated into the corresponding quotas and are not calculated separately. 9. Lightning protection and grounding device engineering:

1. Suitable for lightning protection and grounding of high-pole light poles, power transformation and distribution system grounding and lightning rod grounding devices.

2. The setting amount of grounding busbar laying is based on the natural floor and general soil quality, including the excavation, filling and compaction of trenches. The amount of earthwork should not be calculated when implementing the quota in this section. If there are stones, slag, water, obstacles, etc., additional calculations may be made.

3. It does not apply to the laying of grounding wires and the installation of grounding electrodes using blasting methods, nor does it include testing of grounding devices and grounding resistance using soil replacement or chemical treatment in areas with high soil resistivity.

4. The installation of lightning rods and lightning protection down conductors have taken into consideration the factors of high-altitude operations. 5. Lightning rods are considered as finished parts.

10. The production and installation of street lamp lamp holders is mainly suitable for the simmering of shaped steel, uncoiling and straightening of steel plate coils, the production of shaped steel molds, and metal non-destructive testing for lamp holder construction. Engineering quantity calculation rules

1. Transformer installation shall be calculated according to the quantity shown in the design diagram. The relevant regulations are as follows:

1. Transformer drying is generally not required. If it is really necessary, it can be calculated according to the quantity shown in the design diagram.

2. Transformer oil filtration is calculated based on the oil quantity provided by the manufacturer. No matter how many times it is filtered, it will be filtered until it is qualified. 2. Capacitor installation shall be calculated according to the quantity shown in the design diagram.

3. The installation of high-voltage complete sets of power distribution cabinets and combined box-type substations shall be calculated according to the quantity shown in the design diagram. None of them include the configuration and installation of basic channel steel, busbars and down conductors.

4. The installation of various distribution boxes, cabinets and screens are calculated according to the quantity shown in the design diagram. 5. The strip busbar installation shall be calculated based on the single wire length according to the dimensions shown in the design diagram. 6. The installation of insulators is calculated according to the quantity shown in the design diagram.

7. The installation of low-voltage fuses, switches, controllers, contactors, starters, shunts, small electrical appliances, control cabinet accessories, and terminal blocks are calculated according to the quantity shown in the design diagram.

8. The installation of small busbars shall be calculated in terms of extension meters according to the dimensions shown in the design diagram.