The differences between the 20 1 1 edition examination books and the 201edition examination books are mainly reflected in two aspects: first, the arrangement system has changed greatly; Second, there are some additions and deletions in the content. These have been clearly pointed out in the comparison between the new and old syllabus. In order to further facilitate students to review exams, the specific changes in each chapter of the new and old exam books are introduced in detail in two parts, one is the addition and deletion of content, and the other is a small change in the position of the original content, that is, the change in the arrangement system.
Chapter 1
1. What minor changes have been made to the contents of chapter 1 in the old and new examination books?
20 1 1 version of the examination book, chapter 1 is Basic Knowledge of Construction Engineering Law. In the 20 10 textbook, this part uses 1Z30 1020 legal system and law, 1Z30 1030 civil law, 1Z30 165438 land management law.
20 1 1 20 10
1z 30 10 10 legal system of construction engineering 1Z30 102 1 legal system
The form of 1Z30 10 12 and the effectiveness of 1Z30 1022.
1Z30 1030 construction project agent system 1Z30 1033 agent system
1Z30 1032 the fifth point in the establishment and termination of agency behavior in construction projects 1Z30 1033
1Z30 1040 property right system of construction project 1Z30 1035 property right system
1Z30 1042 land ownership, construction land use right and easement1z30160 land management law
1Z30 1050 construction project creditor's rights system 1Z30 1034 creditor's rights system
1Z30 1060 intellectual property system of construction projects 1Z30 1036 intellectual property system
1Z30 1070 construction project guarantee system 1Z302080 contract guarantee
1Z30 1080 construction project insurance system1z30190 insurance law
1Z30 1090 legal liability system for construction projects 1Z304000 legal liability for construction projects.
1Z30 1092 types of civil liabilities for construction projects and ways to bear them 1Z30 103 1 civil legal relationship.
1Z30 1032 constitutive requirements of civil juristic act
1Z3040 10 civil liability
1Z30 1093 types and ways of undertaking administrative responsibilities for construction projects 1Z304020 administrative responsibilities.
1Z30 1094 types of criminal responsibility for construction projects and ways to bear it 1Z304030 criminal responsibility
2. What changes have been made to the contents of chapter 1 in the old and new examination books?
(1) New contents in version 20 1 1:
Legal system of construction project 1,1z3010/0.
1Z30 10 12 new knowledge points: specific classification of legal forms.
New purpose: 1Z30 10 13 to construct the relationship between laws, administrative regulations and administrative law.
2. 1Z30 1020 legal person system of the project under construction.
1Z30 102 1 new knowledge point: legal person classification.
New use: 1Z30 1023 Legal relationship between enterprise legal person and project management department.
3. 1Z30 1030 construction project agent system.
1Z30 103 1 new knowledge: legal characteristics of agency.
1Z30 1032 new knowledge point: the establishment of construction agency behavior.
4. 1Z30 1040 in the real right system of construction projects.
1Z30 1042 new knowledge points: construction land use right and easement.
New use: 1Z30 1043 establishment, alteration, transfer, extinction and protection of real right.
New use: 1Z30 1053 Common types of construction debts.
5. 1Z30 1060 intellectual property system for projects under construction
1Z30 1062 new knowledge points: conditions for granting patent rights; Patent application and approval; Trademark right: the subject of copyright; The term of protection of copyright; Legal protection of computer software;
New use: IZ30 1063 Intellectual property protection of construction projects.
New use: IZ30 1064 Legal liability for intellectual property infringement in construction projects.
6. 1Z30 1070 construction project guarantee system
IZ30 1072 New Knowledge Points: Common Guarantee Types in Construction Projects.
7. 1Z30 1080 construction engineering insurance system.
New uses: 1Z30 1082 main types of construction engineering insurance and insurance income.
8. 1Z30 1090 in the legal liability system for construction projects.
IZ30 1092 New Knowledge Points: The Main Ways of Civil Liability of Construction Projects.
(2) Deleted contents in version 2011:
1. Delete purpose: version 20 10 1Z30 103 1 civil legal system.
20 10 version 1Z30 1032 constitutive requirements of civil juristic act
2. Purpose of deletion: 20 10 version 1Z30 1 162 to understand the management system of construction land.
3. Purpose of deletion: 20 10 version 1Z304022 Familiar with administrative penalty procedures.
(3) Extended contents of version 2011:
The basic framework of the legal system 1,1z 30101this part is unfolded.
2, 1Z30 10 12 France's effectiveness grade
3. The initial reference to 1Z30 1033 is now more comprehensive.
4. The content of 1Z30 1040 is expanded.
5. 1Z30 1052 The basis of the construction project debt was originally a small point, and now it is listed separately.
6. Extension of patent right in1z301062
chapter two
1Z302000 legal system of construction permit
What changes have been made in the position of the second chapter of the old and new examination books?
20 1 1 examination book 1Z3020 10 construction permit system This part of the examination book 20 100 is mainly distributed in 1Z30 1040 construction law and/kloc. As shown in the following table:
20 1 1 Edition 201Edition 0
1Z3020 10 construction permit system for construction projects
1Z3020 1 1 Scope of application of construction permit and commencement report
1Z3020 12 applicant and statutory approval conditions
1Z3020 13 Provisions on Delayed Construction, Verification and Re-approval 1Z30 1040 Building Law
1Z30 104 1 construction permit system
1Z3020 14 legal liability for illegal acts.
1L302020 qualification system for construction enterprises
1z 30202 1 statutory conditions and grades of enterprise qualifications 1Z30 1040 building law
1Z30 1042 enterprise qualification grade licensing system
1Z302022 provisions prohibiting unqualified or leapfrog contracting projects.
1Z302023 Provisions prohibiting other enterprises or other enterprises from undertaking projects in the name of their own enterprises 1Z30 1040 Construction Law
1Z30 1045 master the project contracting system.
1Z30 1046 master the subcontracting system.
1Z302024 legal liability for illegal acts
1Z302030 registered practice system of builders
1z 30203 1 professional qualification access management of construction engineering 1Z30 1040 construction law
1Z30 1043 vocational qualification system
1Z302032 regulations on examination and registration of builders1z3010/0 management system of builders.
1z 30101registration management
1Z302033 employer and scope of practice post1z3010/0 constructor management system
1Z30 10 12 internship management
1Z302034 basic rights and obligations of builders1z3010/0 management system of builders.
1Z30 10 12 internship management
1Z30 10 14 supervision and management
1Z302035 legal liability for illegal acts
2. What changes have taken place in the second chapter of the old and new exam books?
New contents in (1)20 1 1
1, 1Z3020 10 construction permit system
New use: 1Z3020 1 1 Scope of application of construction permit and commencement report.
New use: 1Z3020 12 applicant and legal approval conditions.
New use: 1Z3020 13 Provisions on delayed commencement, verification and re-approval.
New uses: 1Z3020 14 legal responsibility for illegal acts.
1Z3020 1 1 new knowledge point: construction projects that do not apply for construction permits repeatedly; The main contents of the review of the commencement report; Difference between commencement report system and commencement report in engineering supervision
1Z3020 12 new knowledge: construction permit applicant; The application conditions for construction permits have been increased.
1Z3020 13 new knowledge point: explanation of stopping construction.
2, 1Z302020 construction enterprise qualification system
New use: 1Z302022 Provisions prohibiting unqualified or leapfrog contracting projects.
New purpose: 1Z302023 Provisions prohibiting other enterprises or other enterprises from undertaking projects in their own name.
New use: 1Z302024 Legal liability for illegal acts.
1Z30202 1 new knowledge point: construction enterprise qualification license; The application, extension and change of the qualification certificate of the construction enterprise; Provisions on foreign-invested construction enterprises
1Z302022 new knowledge point: it is forbidden to undertake projects without qualification or leapfrog, and it is forbidden to undertake projects with other enterprises or other enterprises in the name of this enterprise.
3, 1Z302030 registered practice system of builders
New use: 1Z302032 architect examination and registration regulations.
New use: 1Z302033 construction unit and post within the scope of practice.
New use: 1Z302034 Basic rights and obligations of builders.
New use: 1Z302035 Legal liability for illegal acts.
1Z302032 new knowledge points: related contents of the builder's exam; Second-class construction engineer registration; Acceptance and approval of the registration of the second-level constructor; Examination and determination of professional qualifications
1Z302034 new knowledge point: continuing education of registered architects.
1Z302035 new knowledge point: legal responsibility for illegal acts.
(2) Version 20 1 1 expands the content knowledge points.
1Z3020 14 expand the knowledge point: legal responsibility for illegal acts.
1Z30202 1 Extended knowledge points: legal conditions for enterprise qualification; Qualification categories and grades of construction enterprises
1Z30202 1 Extended knowledge points: qualification sequence of construction general contracting enterprises; Professional contracting enterprise qualification sequence; Qualification sequence of labor subcontracting enterprises;
1Z302024 expand the knowledge point: the legal responsibility of illegal acts.
1Z302033 expanding knowledge points: the practical scope of builders.
(3) Version 20 1 1 deleted part.
Purpose of deletion: 1L30 10 13 Practice the project scale standard.
Purpose of deletion: 1Z30 1044 project contracting system.
Purpose of deletion: 1Z30 1047 project supervision system.
1Z30 1042 delete: qualification management of construction engineering survey and design; Qualification management of engineering supervision enterprises
1Z30 1043 Delete: * * Similarity of professional and technical personnel in construction industry.
1Z30 1045 delete: subcontracting is prohibited in the project contracting system.
1Z30 10 12 Delete: change the employing unit.
1Z30 10 14 Delete: credit file management of builders.
(4) Version change 20 1 1
1Z30 104 1 change: the types of projects that do not need to apply for construction permits are changed from 5 to 2 (excluding items 2, 4 and 5, and Article 5 military buildings are separated into separate articles and changed into separately specified construction projects);
1Z302034 change:
(1) In the Administrative Measures for the Practice of Registered Construction Engineers (Trial), the behavior that registered construction engineers are not allowed to do is changed from 9+03 to 65438.
(two) the supervision and management of the registration authority has been reduced from five measures to four, and the original fifth article shall be deleted when the competent construction departments and relevant departments of the people's governments at or above the county level perform their duties of supervision and inspection.
chapter three
20 1 1 examination book 1Z303000 The legal system of construction project contracting is divided into three sections. It mainly includes 20 1Z30 10000 construction engineering legal system 20 1Z30 1044, 1Z30 1045,1z30/kloc.
1. What changes have been made in the position of the third chapter of the old and new examination books?
20 1 1 20 10
1Z303020 construction contract system 1Z30 1045 project contract system
1Z303023 provisions on subcontracting of construction projects 1Z30 1046 project subcontracting system.
1z 3030 10 construction project bidding system 1Z30 1050 bidding method
1Z3030 1 1 Scope, scale and bidding method of construction projects 1Z30 105 1 Grasp the principles and applicable scope of bidding activities.
1Z3030 12 basic bidding procedures and provisions prohibiting dismemberment of the contract.
Master the bidding procedure
1Z30 1056 master the bid opening procedures.
1Z30 1057 master the relevant regulations and bid evaluation methods of the bid evaluation committee.
IZ3030 13 legal requirements for bidding documents and bid bond 1Z30 1053 mastering the requirements for bidding.
IZ3030 15 Provisions on Consortium Bidding 1Z30 1054 Mastering Consortium Bidding
IZ3030 14 Provisions on Prohibiting Bidders from Engaging in Unfair Competition 1Z30 1055 Master the provisions on Prohibiting Bidders from Engaging in Unfair Competition.
IZ3030 16 Legal bid-winning conditions 1Z30 1058 Grasp the bid-winning requirements.
IZ3030 17 legal liability for illegal acts
IZ304042 familiar with the legal responsibility of the construction unit
IZ304046 Understand the legal responsibility of the tendering agency.
IZ303024 Legal liability for illegal acts Iz 30404 1 Grasp the legal liability of the construction unit.
IZ304042 familiar with the legal responsibility of the construction unit
2. What changes have taken place in the third chapter of the old and new exam books?
(1) New contents in version 20 1 1:
1, IZ3030 10 construction project bidding system
1Z30 10 12 new knowledge points: bid validity, bid bond form and bid bond.
Return, delivery and receipt of bid documents
1Z3030 13 new knowledge points: the trial provisions on (pre-qualification documents for standard construction bidding) and (standard construction bidding documents) clearly stipulate the contents that the bidding documents should include.
1Z3030 15 new knowledge point: bid bond of consortium.
1Z3030 16 new knowledge point: determine the conditions of the winning bidder.
2, IZ303020 construction project contracting system
New use: 1Z30302 1 general contracting regulations for construction projects.
1Z303022 new knowledge points: * * scope of contract application, * * contract qualification requirements, * * contract responsibilities.
1Z303023 new knowledge points: the scope of subcontracting, the definition of subcontracting and illegal subcontracting.
3. New section: 1Z303030 Construction of credit system in construction market.
(2) Deleted contents in version 2011:
1, IZ30 1050 bidding method
1Z30 105 1 Delete knowledge points: principles to be followed in bidding activities.
1Z30 1052 delete knowledge points: tender announcement or invitation letter, mandatory requirements of tender documents, and pre-tender estimate.
1Z30 1057 delete the knowledge points: the selection of bid evaluation experts, the conditions that bid evaluation experts should have, the situation that they should not serve as members of the bid evaluation Committee, the professional ethics requirements and confidentiality obligations for members of the bid evaluation Committee, and the restrictive provisions on the behavior of bidding agencies.
2. Building Law 1Z30 1040
Purpose of deletion: 1Z30 1044 to master the project contracting system.
(3) Changes and expansion of version 2011
1.20 10 version of the standard of the project scope and scale that must be tendered is expanded to three knowledge points in 20 1 1 version.
In version 2.20 10, the project contracting system of 1Z30 1040 construction law 1Z30 1045 was changed to the second section of 2065 438+ 1z 303000 construction project contracting legal system.
3.20 10 version 1Z30 1040 construction law 1Z30 1046 engineering subcontracting system was changed to IZ303020 construction project contracting in 2010 version.
4. In the 20 10 version, 1Z30 1052 mastered the second bidding method in the bidding procedure, and changed it to the fourth bidding method in the 2010 version, that is, Iz30301.
5.20 10 version, 1Z30 1056 master the bid opening procedures. This section has been changed to the basic bidding procedures of IZ3030 12 and the provisions prohibiting dismemberment and contracting out in the 20 10 edition.
6.IZ30 1057 has mastered the relevant provisions and bid evaluation methods of the bid evaluation committee in version 20 1057, and changed it to the provisions on basic bidding procedures and prohibition of dismemberment and contracting in version 2012. 1. Basic bidding procedures for bid evaluation.
7. Compared with 20 1 10, the legal liability of 20 10 has a certain expansion.
chapter four
1. What changes have taken place in the fourth chapter of the old and new exam books?
In the 20 1 1 examination book, 1Z304000 construction project contract and labor contract legal system are mainly distributed in1z30180 labor law and 1Z302000 contract law. As shown in the following table:
20 1 1 20 10
1Z3040 1 1 legal characteristics and principles of contract1z30201/principles and adjustment scope of contract law.
1Z3020 12 contract classification
1Z3040 12 offer and acceptance of the contract 1Z30203 1 effectiveness of the contract
1Z30202 1 quotation
1Z302022 commitment
1Z3040 13 legal form and content of construction contract of construction project 1Z302023 general contract terms.
1Z302024 contract format
1Z3040 16 provisions on invalid contracts and contracts with pending validity 1Z302032 invalid contracts.
1Z302034 the entry into force of the contract is pending.
1Z3040 17 contract performance, alteration, transfer, dissolution and termination 1Z30204 1 contract performance agreement
1Z30205 1 contract change
1Z302052 contract assignment
1Z302033 changeable and revocable contract
1Z30206 1 termination of the contract
1Z3040 18 liability for breach of contract and exemption of liability for breach of contract 1Z30207 1 ways of assuming liability for breach of contract.
1Z302072 exemption from force majeure and liability for breach of contract
1Z30402 1 Provisions for concluding labor contracts
1Z304022 performance, alteration, dissolution and termination of the labor contract
1z 301181labor contract system
1Z304024 labor protection regulations 1Z30 1 182 labor protection regulations
1Z304025 labor dispute handling 1Z30 1 183 labor dispute handling.
1z 30403 1 legal provisions of the contract 1Z302 102.
1Z304032 legal provisions of the sales contract
1Z304033 legal provisions of loan contract
1Z304034 legal provisions of lease contract
1Z302 10 1 property right transfer contract
1Z304036 legal provisions of transport contract
1Z304037 legal provisions of warehousing contract
1Z304038 legal terms of entrustment contract
1Z302 103 service contract
2. What changes have taken place in the fourth chapter of the old and new exam books?
(1) New contents in version 20 1 1:
1, 1Z3040 10 construction project contract system
New use: 1Z3040 14 agreement on construction period and payment price.
New use: 1Z3040 15 provisions on compensation for losses in construction projects.
New use: 1Z3040 19 the use and legal status of the model text of the construction project contract.
1Z3040 1 1 new knowledge point: point 4 of construction contract.
1Z3040 13 new knowledge points: point 4: the main obligations of both parties to the construction contract.
2. 1Z304020 labor contract and labor relations system
New use: 1Z304023 regulations on legal employment mode and illegal employment mode.
New use: 1Z304026 Regulations on treatment of industrial injuries.
New use: 1Z304027 Legal liability for illegal acts.
1Z304024 new knowledge points: the first point is the working hours and rest and vacation of workers.
The second point is the wages of workers.
Fifth, workers' social insurance and welfare.
3. In the legal provisions of the relevant contract of 1Z304030,
New use: 1Z304035 legal provisions of financial lease contract.
1z 30403 1 new knowledge: financial lease contract
(2) Deleted contents in version 2011:
1. Delete purpose: 20 10 version 1Z302025 to grasp the responsibility of contracting fault.
Purpose of deletion: 20 10 version 1Z302035 Understanding conditional and conditional contracts.
Purpose of deletion: 20 10 version 1Z302042 mastering the right of defense.
Purpose of deletion: 20 10 version 1Z302043 Familiar with subrogation.
Purpose of deletion: 20 10 version 1Z302044 Understanding the cancellation right.
Purpose of deletion: 2010 edition1z302062 Familiar with other circumstances of termination of rights and obligations.
Purpose of deletion: 20 10 version 1Z30208 1 master the contract guarantee clauses.
Purpose of deletion: 2065438+00Edition1Z302082 Master the format of contract guarantee.
Purpose of deletion: 20 10 version 1z 30209 1 mastering the conclusion of construction project contracts.
Purpose of deletion: version 2065 438+00 1Z302092 grasps the performance of construction project contracts.
2. Delete knowledge points: version 20 101z302011The second point is the adjustment scope of contract law.
Delete knowledge points: version 20 10 1Z302023 third point format clause.
Delete knowledge points: 20 10 version 1Z302033 The fourth point is the difference between a changeable and revocable contract and an invalid contract.
Delete knowledge points: 20 10 version 1Z30403 1 construction engineering survey contract and design contract.
(3) Extended contents of version 2011:
1, 1Z3040 1 1: the legal characteristics of the contract and the classification and category expansion of Article 3 in the conclusion principles.
chapter five
What changes have taken place in the content and position of the fifth chapter of the old and new examination books?
20 1 1000 examination book 1Z305000 legal system of environmental protection, energy conservation and cultural relics protection of construction projects. This part is mainly distributed in 1Z30 1000 legal system of construction projects 1Z3065438+. As shown in the following table:
20 1 1 20 10
1Z3050 1 1 noise pollution prevention and control regulations on construction site
1Z3050 12 regulations on prevention and control of waste gas and wastewater pollution in construction site
1Z3050 13 regulations on prevention and control of solid waste pollution in construction site 1Z30 1 123 be familiar with prevention and control of water, atmosphere, noise and solid waste environmental pollution.
1z 30502 1 regulations on rational energy use and energy saving in buildings1z30130, focusing on energy saving management in construction projects.
1Z30 1 130 familiar with the provisions of energy saving in construction projects.
2. What changes have taken place in the fifth chapter of the old and new exam books?
(1) New contents in version 20 1 1:
1, 1Z3050 10 construction site environmental protection system,
New use: 1Z3050 1 1 noise pollution prevention and control regulations on construction site.
New use: 1Z3050 12 regulations on prevention and control of waste gas and wastewater pollution in construction site.
New use: 1Z3050 13 regulations on prevention and control of solid waste pollution in construction site.
1Z3050 14 new knowledge point: legal responsibility for illegal acts.
2. 1Z305020 building energy-saving system
1Z30502 1 new knowledge points: general provisions on rational use and provisions on building energy conservation.
New uses: 1Z305022 technical progress and incentive measures for building energy conservation.
1Z305023 new knowledge point: legal responsibility for illegal acts.
3. 1Z305030 Cultural Relics Protection System in Buildings
1Z305030 new knowledge point: building cultural relics protection system
1z 30503 1 new knowledge point: the scope of cultural relics under state protection.
1Z305032 new knowledge points: regulations on construction within the protection scope and construction control zone of cultural relics protection units.
1Z305033 new knowledge point: regulations on reporting and protection of cultural relics found during construction.
1Z305034 new knowledge point: legal responsibility for illegal acts.
(2) Deleted contents in version 2011:
1. Delete purpose: version 20 101z 3011construction project environmental impact assessment system.
Purpose of deletion: 20 10 version 1Z30 1 122 "three simultaneities" system of environmental protection.
(3) Extended contents of version 2011:
1, 1Z3050 1 1: extended description of environmental noise pollution prevention and control of construction projects.
1Z3050 12: the extension of dust control in the prevention and control of air pollution on the construction site.
1Z3050 12: extension of water pollution prevention and control regulations on construction site
2. 1Z30502 1: classification expansion of building energy efficiency regulations
Chapter vi
What changes have taken place in the position of Chapter 6 of the old and new examination books?
20 1 1000 examination book 1Z306000 the legal system of construction project safety production is mainly distributed in 1Z30 1000 construction project 1060 safety production law legal system. 1Z30 1070 safety management regulations for construction projects, 1Z30 1080 safety production license regulations, 1Z3040 1 China 1Z304000 legal liabilities for construction projects.