If there is no agreement, during the delayed delivery of the house, according to the assessment of the relevant competent departments or qualified real estate appraisal agencies, there are several similar housing rent standards.
Some problems on the application of legal interpretation in the trial of disputes over commercial housing sales contracts
Article 17 The amount or amount of liquidated damages agreed in the commercial housing sales contract can be calculated with reference to the following standards:
Overdue payment, according to the total unpaid subscription funds, with reference to the benchmark interest rate of the People's Bank of China, interest on overdue loans shall be collected from financial institutions.
Delayed delivery, according to the announcement of the relevant authorities or the evaluation of qualified real estate appraisal agencies during the delayed delivery, there are many similar housing rent standards.