Article 40 of the Urban and Rural Planning Law of People's Republic of China (PRC) stipulates that if buildings, structures, roads, pipelines and other projects are built in urban and town planning areas, the construction unit or individual shall apply to the competent department of urban and rural planning of the people's government of the city or county or the people's government of the town determined by the people's government of the province, autonomous region or municipality directly under the Central Government for a construction project planning permit.
To apply for a planning permit for a construction project, the relevant certification documents for land use, the design scheme of the construction project and other materials shall be submitted. A detailed construction plan shall also be submitted for a construction project that requires the construction unit to prepare a detailed construction plan.
Extended data:
operation sequence/order
1. The planning window organizes the technical review of the architectural design scheme according to the application of the project owner, and issues the Notice of Handling the Parallel Approval of Architectural Design Scheme to the parallel approval department on the same day.
2. After receiving the Notice of Parallel Approval of Architectural Design Scheme, the parallel examination and approval department shall put forward examination opinions within 3 working days, and sign the Opinions of Parallel Approval of Architectural Design Scheme to feed back to the Municipal Planning Bureau.
3. The central planning window shall complete the plan review and construction drawing review within 5 working days after receiving the parallel examination and approval opinions of the construction planning and architectural design scheme of the parallel examination and approval department. If the scheme needs to be revised, it shall put forward the revision opinions, clarify the reasons for the revision, and the project applicant shall re-apply for construction after revision; If the scheme is approved, the project owner shall apply for the planning permission of the construction project.
4. The central planning window shall apply for the Construction Project Planning Permit, Fire Protection Design Audit, Opinion Review on the Construction of Air Defense Basement of Newly-built Civil Building Project, Meteorological Lightning Protection Design Audit, Urban Construction Waste Disposal Examination and Approval, and Environmental Sanitation Facilities Removal and Migration Examination and Approval according to the application of the project owner.
"Termite Prevention and Control Regulations" and other parallel approval conditions, accept the application for construction project planning permission, inform the project owner to fill in the form and submit relevant materials at one time, and issue the Notice of Parallel Approval of Construction Project Planning Permission to the parallel examination and approval departments of fire protection, civil air defense, meteorology, city appearance and housing management on the same day, and forward the relevant application materials.
5, parallel examination and approval unit for examination and approval within 2 working days, signed the "construction project planning permission parallel examination and approval opinions" feedback to the Municipal Planning Bureau, Chao Gu project owners.
6. The planning window shall complete the on-site inspection within 4 working days and issue the Construction Project Planning Permit according to the Parallel Approval Opinions of the Parallel Approval Unit.