The reason why Luohe Jianye Guiyuan was not completed

There are mainly the following aspects:

1. Planning approval: There are planning approval problems in the development of Guiyuan in Luohe Jianye. Due to the problem of project site selection, some houses failed to obtain planning permits, which led to the inability to continue the development of the project.

2. Financing: There are also financing problems in the development of Guiyuan in Luohe Jianye. Due to the gradual cooling of the real estate market at that time, the project was large in scale and needed a lot of financial support to maintain the construction. However, the developer failed to obtain financing as scheduled, which led to the stagnation of the project.