The publicity period for winning the bid in project bidding is 3 days. Does Saturday and Sunday count?

There is no clear working day, or it is within the time limit. But in general, according to the law, if the start date or the last day of the period is a legal holiday, it will be postponed to the next working day accordingly.

According to Article 54 of the Regulations for the Implementation of the Bidding Law of People's Republic of China (PRC):

For a project that must be subject to tender according to law, the tenderer shall publicize the successful candidate within 3 days from the date of receiving the bid evaluation report, and the publicity period shall not be less than 3 days.

Bidders or other interested parties who have objections to the bid evaluation results of projects that must be subject to tender according to law shall raise them within the publicity period of the successful candidate. The tenderer shall make a reply within 3 days from the date of receiving the objection; Before giving a reply, the tendering and bidding activities shall be suspended.

Extended data:

According to Article 5 of the Measures for the Administration of Tender Announcement and Publicity Information Release

The pre-qualification announcement and tender announcement of a project that must be subject to tender according to law shall contain the following contents:

(a) the name, content, scope, scale and source of funds of the project subject to tender;

(two) the bidding qualification requirements, and whether to accept the consortium bid;

(three) the time and manner of obtaining the prequalification documents or bidding documents;

(four) the deadline and method for submitting the prequalification documents or bidding documents;

(five) the name, address, contact person and contact information of the tenderer and its procuratorial agency;

(6) Where electronic bidding is adopted, the website and method for potential bidders to visit the electronic bidding trading platform;

(seven) other contents that should be explained according to law.

Article 6 The publicity of the candidate winning the bid for a project subject to tender according to law shall include the following contents:

(a) the ranking, name, tender offer, quality, time limit for a project (delivery date) and bid evaluation of the successful candidate;

(two) the name and number of the person in charge of the project and the relevant documents that meet the requirements of the tender documents promised by the successful candidate;

(3) The qualification and ability of the successful candidate to respond to the requirements of the tender documents;

(four) the channels and methods of raising objections;

(5) Other contents stipulated in the tender documents.

The name of the winning bidder shall be specified in the publicity of the winning result of the project that must be subject to tender according to law.