The report website authoritatively released 20 1X "Acceptance Report of Hospital Preparations Project". For more information about the acceptance report of the 20 18 hospital preparation project, please visit the report website.
Xx Municipal Health Bureau:
After nearly two years of preparation, xxxx Hospital has been basically completed and basically has the conditions for opening. Now, the acceptance report of our hospital is submitted together with all the materials. Please allow acceptance and guidance.
I am here to convey
welcome
Xxxx Hospital Preparatory Team
20 1X year 65438+ February 19.
First, the basic situation of the hospital:
Since April 12, our hospital received the approval document from the Municipal Bureau for setting up medical institutions, with the care and help of leaders at all levels and relevant departments, the work has progressed smoothly and all the work has been completed well. In the early stage, according to the functions and department settings of the hospital, we completed the decoration and matching, recruited all kinds of professionals at all levels, introduced technical talents, and purchased various large and medium-sized medical equipment. Some are gradually entering the stage of installation and debugging. The system construction and on-the-job training for all staff have been completed. According to the current situation of the hospital, the conditions for opening a clinic have basically been met. Please further guide the leaders and experts.
Second, the hospital department settings:
Third, the hospital personnel composition:
At present, the total number of hospital staff is 12 1. Senior, middle and junior personnel are basically in place, and the structure is reasonable, which can meet the needs of clinical medical work. (Attached with personnel roster)
Fourth, the hospital system construction:
In order to strengthen medical quality management, prevent medical errors and accidents, further improve medical quality and level, and better serve people's health. According to the actual situation of our hospital, we have formulated various medical rules and regulations, administrative management systems, medical technology operating procedures, hospital emergency plans and employee manuals. , and compiled into a book for the convenience of employees. The establishment of the above-mentioned system will undoubtedly provide sufficient guarantee for strengthening and improving the management of our hospital, standardizing medical behavior, further improving medical quality and promoting the healthy development of the hospital. (Attached to the rules and regulations of medical institutions and technical operation procedures)
Verb (abbreviation for verb) Buy basic instruments and equipment:
According to the business needs of the hospital, all kinds of clinical medical equipment have been equipped, which have arrived one after another, and some of them are still being installed and debugged. The basic equipment and infrastructure of outpatient ward are readily available, which can meet the needs of clinical medical work. (Attached with equipment list)
Six, floor staff training:
In order to further improve the quality of employees, fully tap the potential of each employee, constantly enhance the ideological awareness, work awareness, responsibility awareness and service awareness of all employees, and establish the spirit of hardship, professionalism, dedication and team spirit of employees; The hospital attaches great importance to staff training and has conducted various trainings for all staff. We also organized employees to learn different knowledge such as hospital rules and regulations, technical operation procedures, prevention and treatment of infectious diseases, hospital infection knowledge, disinfection and isolation knowledge, and medical waste treatment. We also held a lecture on fire protection knowledge, which made employees enhance their awareness of fire protection, learned fire protection knowledge, avoided and eliminated the occurrence of potential dangerous factors, and ensured the safety of collective and individual lives and property. Hospitals often organize employees to give business lectures, constantly improve their business knowledge and skills, enhance their academic awareness and knowledge level, and thus improve their medical knowledge level. Most importantly, the preparations we made before the outpatient service laid the foundation for the smooth opening of our hospital, and will also play a positive role in promoting the future work of the hospital.
Seven, disinfection supply room basic situation:
Disinfection supply room is an important department of the hospital, which is mainly responsible for the medical disinfection supply of the whole hospital. In this regard, the hospital leaders attached great importance to it, invited professional health technicians to guide the construction, and now it has been debugged, and equipped with senior nursing staff as department heads, which can meet the disinfection supply work of the hospital.
Eight, medical waste treatment:
Hospital leaders attach great importance to the treatment of medical waste. We signed an intention contract with Kang Sheng Company for the incineration of medical wastes, and all the medical wastes in the hospital will be recycled and treated by the company.
There are temporary storage places for medical waste in our hospital, and different storage places for medical waste and domestic garbage are marked separately, and a special person is appointed to take charge of recycling and make a good registration. The temporary storage place of medical waste meets the requirements, the room is sealed, locked, rat-proof and burglarproof, and the safety measures meet the requirements. Indoor lighting, and installation of ultraviolet lamp, do regular disinfection, to prevent the pollution of iatrogenic waste to the environment.
Nine, about the hospital environmental assessment:
Hospitals attach great importance to environmental protection. The Medical Waste Hospital signed an intention contract with Kang Sheng Company for the incineration of medical wastes, and all the medical wastes in the hospital were recycled and treated by the company, becoming an infection department, and the relevant rules and regulations on hospital infection, disinfection supply, garbage disposal and hospital infection team were established, which has positive significance for protecting the environment and reducing pollution.
In view of the preparatory work of our hospital, we hereby apply for the superior to arrange experts to come to our hospital for acceptance guidance.
Equipment acceptance report template
Equipment unpacking acceptance record
Xxxxxx unit xx October
First, the appearance inspection
1. Take photos of the equipment and the outer packaging, and check whether the outer packaging of the equipment is intact, damaged, soaked, damp and deformed. , and check the surface and packaging state of the outer packaging box;
2. Check whether the surfaces of equipment and accessories are damaged, corroded and scratched. , and focus on checking whether the conveying impeller, main components and main working face are damaged;
3. If the packaging is damaged, the equipment and accessories are damaged, rusted, used and other problems are found, detailed records should be made, and photos should be taken for the record, and the return and claim procedures should be handled with the supplier in time.
Second, the quantity inspection
1. Quantity inspection is based on the supply contract and packing list, and the specifications, models, configurations and quantities of the main engine, accessories and other equipment are inspected one by one;
2. Carefully check whether the random materials are complete, such as instruction manual, product inspection certificate, warranty, etc. ;
3. Pay attention to check the serial number and factory number of the equipment, and check it online when necessary;
4. Carefully record the unpacking inventory, indicating the location, time, participants, case number, product name, arrival and actual arrival quantity. In case of any shortage, mistake, etc., make records in time and keep relevant information.
Third, fill in the acceptance record form
1. After unpacking acceptance, if any item is found not to meet the requirements of the contract documents, it must be approved (signed and sealed) by the supplier's representative.
2. Take the unpacking inspection records, serial numbers, factory numbers and site photos of the equipment as part of the equipment acceptance documents.
Equipment unpacking acceptance record form
Number:
House decoration completion acceptance report
The report website authoritatively publishes the house decoration completion acceptance report. For more information about the house decoration completion acceptance report, please visit the report website.
Customer:
Customer phone number:
Entrusted project acceptance unit:
Project acceptance inspector:
Supervisor:
Engineering acceptance address:
Basis for project completion acceptance: Standard for Quality Acceptance of Family Room Decoration Project
Engineering overview:
This project has two rooms, two halls and one bathroom, with a building area of 37 square meters and a floor height of 2.8 meters.
House decoration completion acceptance conclusion:
First, the decoration surface of the project is cracked in many places (see the schematic diagram of the entrustment order ③ ⑧ ⑨ ⑾), and the acceptance is unqualified.
Basis: Standard 9.0.2 Putty should be water-resistant, and the putty should be firmly combined with the matrix, without peeling, pulverization and cracking.
Second, the hall door and door frame paint brush lines, falling (see the ordering schematic ⑿), the acceptance is unqualified.
Basis: Standard 9.0.3 Paint surface should be smooth and smooth, free of brush leakage, peeling and spots, clear wood grain of varnish, no edges and corners, sagging and wrinkle on the large surface, basically the same color and no brush lines. The hardware and glass are clean.
Three, a hall floor tile hollowing rate is 20.8%, two hall floor tile hollowing rate is 65438 02.5%, toilet wall brick hollowing rate is 5.98% (see the entrusted schematic diagram (2) attending (13)), the acceptance is unqualified.
Basis: Standard 8. 1.4 Wall and floor tile paving should be smooth and firm, with clear patterns, no dirt and slurry marks, basically the same surface color, even joints, no cracks, corners and missing edges, and the hollowing rate of veneer corners should not exceed 5% of the quantity.
Fourth, the wall power cord is not directly buried with plaster layer, and the joint at the branch of the top power cord is not put into the box (see the schematic diagram of the entrustment sheet ⑦), and the acceptance is unqualified.
Basis: Standard 3.0.2 Electrical wiring should be laid with concealed pipes. There should be no knots and kinks in the pipeline. The distance between wires and telephone lines and closed-circuit television lines should not be less than 50 cm. Bare wires are not allowed on the ceiling. It is forbidden to directly bury the wires in the plastering layer.
Five, the water supply pipeline is not fixed, the pipeline is bent (see the schematic diagram of the order), and the acceptance is unqualified.
According to standard 2.0.2, the pipeline installation should be horizontal, firm and straight, the laying should be firm, the slope should meet the requirements, the valves and faucets should be installed upright, and the use should be flexible and convenient. Exposed piping shall be painted with antirust paint, while concealed piping shall be painted with antirust paint.
Six, the bathroom, there are signs of water seepage around the drain (see the intention of the power of attorney). Because there is no water source, it is impossible to do water quality testing (to be determined after the results have water source).
Reporter: