General situation of Yangzhou engineering construction information network;
Yangzhou Engineering Construction Information Network is a professional website for bidding management and engineering information of construction projects in Yangzhou area. This website publishes engineering information, policies and regulations information, enterprise information, professional information, etc. Facing the society, we will wholeheartedly provide information services for all parties in engineering construction.
In order to further standardize the contents of various management regulations for bidders of construction enterprises, Yangzhou Bidding Network has formulated relevant guidelines for bidders to help bidders of relevant construction enterprises bid for engineering projects, in which the change of project managers after winning the bid is explained. The main contents are as follows:
1, provided that:
If the change reason belongs to the following circumstances, it shall be applied by the winning bidder and approved by the tenderer.
(1) Due to its own reasons, major quality and safety accidents occur in the project;
(2) suspension or revocation of the qualification as a project manager due to violations of laws, regulations and disciplines;
(3) The Employer requests to replace the project because it is incompetent for the project task undertaken;
(4) Changing the work unit;
(5) Suffering from serious illness and needing treatment or cultivation for more than one month or more than half of the contract period.
2. Filing materials: If the reason for the change belongs to Article 3, a written report on the change of the project manager, signed by the tenderee and its field engineer, and signed by the supervision unit and the director, shall be provided for filing; If the reason for the change belongs to Article 4, a written report that the tenderer agrees to change the project manager shall be provided for the record, and the resignation certificate of the project manager of the winning unit shall be provided; If the reason for the change belongs to Article 5, a written report that the tenderer agrees to change the project manager shall be provided for the record, and a disease diagnosis certificate issued by a medical institution above level 2 and a hospitalization certificate signed by the attending physician shall be provided.
3. If the above conditions are met, the winning bidder must first enter the change information of the project manager online, upload relevant scanned copies and submit them for review. Finally, bring the original scanned copy to the second room of bidding management for review.
Yangzhou Engineering Construction Information Network Website: /yzcetc/
Address of Yangzhou Project Bidding Network: 4th Floor, Building 1 Guangling New Town Citizen Center, No.9 Wenchang East Road.
Contact information of Yangzhou project bidding network: 0514-82087116.
For more information about bid writing and improving the winning rate, click on the bottom customer service for free consultation.