Difference between filing and approval of feasibility study report

What is the sequence of project initiation and feasibility study?

The feasibility study report should be made for the informatization project first.

The establishment of the project is after the feasibility study. Only when your project is proved to be feasible will the NDRC department approve the implementation of the project.

Project establishment is actually an old saying. At present, the state has reformed the investment system, and projects are divided into three ways: examination and approval, approval and filing according to investors and sources of funds. State-invested projects and projects invested with state-owned funds are subject to the examination and approval system, and the projects subject to the examination and approval system need to submit feasibility study reports to the development and reform department, such as municipal road projects. The approved projects are mainly private investment, and the projects in the accurate catalogue issued by the state are accurately implemented. This kind of project does not need to submit feasibility study, but only needs to submit project application report, such as real estate project; Filing projects do not need feasibility studies or application reports, and are the most relaxed projects, such as some industrial projects.

A project is not completed until it has been approved, approved or put on record according to the above three types.

If it is a government-invested project, it is necessary to prepare a feasibility study report first, plus some other attachments, such as land pre-examination, environmental assessment, energy evaluation, site selection and so on. And report to the development and reform department for approval. After the approval document is issued, your project can be called completed. Without a feasibility study report, the development and reform department will not approve it.

Should the informatization project be established first or the feasibility study report first?

The feasibility study report should be made for the informatization project first.

The establishment of the project is after the feasibility study. Only when your project is proved to be feasible will the NDRC department approve the implementation of the project.

Project establishment is actually an old saying. At present, the state has reformed the investment system, and projects are divided into three ways: examination and approval, approval and filing according to investors and sources of funds. State-invested projects and projects invested with state-owned funds are subject to the examination and approval system, and the projects subject to the examination and approval system need to submit feasibility study reports to the development and reform department, such as municipal road projects. The approved projects are mainly private investment, and the projects in the accurate catalogue issued by the state are accurately implemented. This kind of project does not need to submit feasibility study, but only needs to submit project application report, such as real estate project; Filing projects do not need feasibility studies or application reports, and are the most relaxed projects, such as some industrial projects.

A project is not completed until it has been approved, approved or put on record according to the above three types.

If it is a government-invested project, it is necessary to prepare a feasibility study report first, plus some other attachments, such as land pre-examination, environmental assessment, energy evaluation, site selection and so on. And report to the development and reform department for approval. After the approval document is issued, your project can be called completed. Without a feasibility study report, the development and reform department will not approve it.

How to prove the collective industrial land?

1. Prepare environmental assessment report, feasibility study report, project filing, planning and positioning map, etc.

2. Bring the business license of the enterprise, organization code certificate, legal person ID card, planning location map, clan map, cadastral questionnaire and land transfer fee receipt to the municipal government to handle the land transfer contract and land approval documents.

3. Bring the deed tax receipt, planning permit and application form to the Cadastral Section of the Land Bureau.

4.30 working days later, issue a bill of payment and go to the Land and Resources Bureau to get the certificate.

General contracting contract filing process?

The filing process of construction projects includes the following aspects: preparing the feasibility study report and obtaining the Project Approval from the National Development and Reform Commission. Obtained the Land Pre-trial Opinion from the Bureau of Land and Resources. Obtain the "EIA review opinion" from the Environmental Protection Agency. Obtained the "Reply of Planning Opinions" from the Planning Commission to the National Development and Reform Commission. Obtained the "Reply of Planning Opinions" from the Planning Commission to the Construction Committee. Obtain the "Notice of Site Selection Opinions" from the Construction Committee. Obtained the Notice of Bidding Measures from the National Development and Reform Commission.

New energy project filing process?

Take photovoltaic power generation as an example

A, supporting projects (line project, examination and approval system)

Prepare the "Project Approval Application Report" and apply to the Provincial Energy Bureau for approval. Relevant departments at the county level can issue supporting documents. The following documents must be submitted:

(a) the preliminary design of the transmission line project (on behalf of the feasibility study) review opinions;

(2) land use pre-trial opinions issued by the land and resources department;

(3) Environmental impact assessment opinions issued by the environmental protection department;

(four) the construction project site submissions.

Second, the photovoltaic power generation project (filing system)

(1) photovoltaic power station

1. Preparation

To apply for preliminary work to the Provincial Energy Bureau, the following materials shall be submitted:

(1) Development agreement signed by the project owner and the local county government;

(2) An assessment report on optical resources;

(three) the competent department at the county level (the municipal competent department with districts) issued a report document.

2. Project archiving

By the provincial energy bureau for the record, before the record must strive for national quotas. The following materials shall be submitted for the record:

(1) Report document issued by county-level competent department (municipal competent department with districts);

(2) the light resources assessment report (generally issued by the Provincial Meteorological Bureau);

(three) the land use instructions issued by the land and resources management department;

(4) The power grid company issues a power grid access scheme;

(five) the project feasibility study report review opinions.

(2) Distributed photovoltaic power generation

The record management shall be implemented by the competent department at the county level. Before filing, you need to consult the Provincial Energy Bureau and apply for indicators before filing. The project filing work should simplify the procedures as much as possible, and avoid supporting documents such as power generation business license, planning and site selection, land pre-examination, soil and water conservation, environmental impact assessment, energy conservation assessment and social risk assessment.

To apply for quotas to the Provincial Energy Bureau, the following materials shall be submitted;

1. The development agreement signed by the project owner and the local county government;

2. Optical resource evaluation report;

3. Power grid enterprises issue opinions on grid connection;

4. Review opinions on the feasibility study report of the project.

(3) Natural person distributed photovoltaic power generation

The record shall be filed by the county-level competent department or the power supply department, and the quota and subsidy shall be uniformly declared by the county-level power supply department.