1. Can I apply for a real estate license for a new factory building in Qingdao industrial land?
1. The newly-built factory building in Qingdao industrial land should be able to handle the real estate license. Enterprises should provide the following information when handling the real estate license: an application form for property right registration (an empty form is collected at the application window and filled in and stamped by the applicant);
2, the construction project approval (original or photocopy, the original inspection); Construction land planning permit (original or photocopy and check the original); State-owned land use certificate (original); Construction project planning permit, annex and planning red line map (original or copy and check the original);
3. Construction permit; Construction project planning acceptance certificate; Fire acceptance opinion or registration form (original or copy and check the original); Housing construction project completion acceptance record (original); Acceptance certificate of construction project completion file (original); Real estate surveying and mapping results report and attached drawings (original); Business license of the enterprise and ID card of the legal representative (original or copy and check the original).
2. What is the process of building a real estate license for a new factory in Qingdao industrial land?
1. Obtain the right to use the proposed land, plan the layout of the new building, apply to the competent department for a new project report (project application), and clarify the use purpose, planning layout, construction scale and total cost of the new building. After the project is approved, it will enter the preparation stage of project construction.
2. The preparation of the project is mainly marked by obtaining the construction permit, and the work to be completed before handling the construction permit includes: geological survey (providing information for architectural design). The cost is 300-600 yuan/hole (depending on the engineering quantity and the geology of the plot); Review the geological survey report; Construction drawing design; Fire declaration and review
3. Entrust a qualified surveying and mapping unit to locate the control points and intersections (a legally binding surveying and mapping report will be issued), find out the underground, above-ground buried and overhead pipelines in the construction area, and determine the construction plan before the construction unit carries out step-by-step construction; Formal application for water use; Apply for construction and formal electricity consumption (design, approval, construction, commissioning and acceptance); Building monomer and general floor (including civil engineering, fire protection, purification, process piping, electrical, HVAC, greening, etc.). ).
4. Project acceptance: provided that the contractor has fulfilled the project contract; Formal power supply (power supply bureau completes power distribution acceptance in advance) and water supply. The Bureau of Surveying and Mapping completed the planning acceptance. Construction of living building and factory building is completed. The construction unit shall provide complete construction materials. The fire brigade completed the fire inspection and acceptance. The quality inspection station carries out engineering quality acceptance. Report to the local quality inspection station for completion and acceptance.
5. Submit all acceptance materials to the Housing Authority, and the Housing Authority will issue a certificate after passing the examination.
The above is about the process of handling the real estate license for the new factory building in Qingdao industrial land, and what is the process of handling the real estate license for the new factory building in Qingdao industrial land? To apply for real estate license, certain conditions need to be met, and some industrial land can be converted to other uses, or it can be another way to apply for real estate license.