Briefly explain the project completion acceptance report, approved project feasibility study report or plan task book, approved unit and approval number, approved construction investment and project budget (including revised budget), specified construction scale and production capacity, and the main contents of construction project lump sum agreement.
2. Project overview
(1) Preliminary work and implementation of the project;
(2) design, construction, general contracting, construction supervision, equipment suppliers, quality supervision institutions and other units;
(three) the commencement date and completion date of each single project;
(4) The completed workload and the formed production capacity (explain in detail the reasons why the construction period is advanced or postponed, the reasons why the production capacity is inconsistent with the original plan, the completion acceptance report and the countermeasures taken in the construction to ensure the implementation of the original plan).
3. Initial inspection and trial operation
Main conclusions of initial inspection time, initial inspection and trial operation (the initial inspection report and main test indicators of trial operation should be attached, and the trial operation time is generally 3-6 months).
4, engineering and technical documents
The main records of the completion acceptance report in engineering construction, the completion data of individual projects, the acceptance data of concealed projects, design documents and drawings, supervision documents, technical data of main equipment, and correspondence documents in engineering construction, etc.
5. Overview of final accounts of completion
Investment analysis of budget estimate (revised budget estimate), budget implementation and preliminary final accounts, and project completion acceptance report of communication construction project.
6. Economic and technical analysis
(1) Test values and conclusions of main technical indicators;
(2) Analysis of the project completion acceptance report of the project quality, and description of the situation after the quality accident occurred in the construction;
(3) project cost analysis and main economic indicators, as well as the investment benefits obtained by adopting new technologies, new equipment, new materials and new processes;
(4) Analysis of investment benefit completion acceptance report, forming the proportion of fixed assets to investment, direct income analysis of enterprises, investment return period and break-even analysis.
7. Preparation for production
Organization and production personnel of the operation management department. Project completion acceptance report and training of established operating rules and regulations.
8. The finishing touch.
9. Preliminary opinions on the commissioning of the project.
10, experience and lessons of engineering construction and suggestions for future work.
Extended data
The basis for completion acceptance can be summarized as follows:
(1) Various documents approved by the superior for the project;
(two) the feasibility study report, preliminary design documents and approval documents;
(3) Construction drawing design documents and design change negotiation records;
(4) Various standards promulgated by the state and current construction quality acceptance specifications;
(5) Project contract documents;
(6) technical equipment specifications;
(7) Other provisions on project completion acceptance;
(eight) projects that introduce new technologies and complete sets of equipment from abroad, as well as Sino-foreign joint venture construction projects, shall be checked and accepted according to the signed contracts and design documents provided by the importing countries;
(9) For construction projects that use loans from international financial institutions such as the World Bank, a project completion report shall be prepared on time in accordance with the provisions of the World Bank.
Baidu Encyclopedia-Completion Acceptance
Baidu Encyclopedia-Project Completion Acceptance Report