Question 2: How to write the instructions for the preparation of the tender?
1. Basis and document number of design data of construction project:
1. Design power of attorney and/or superior approval documents, as well as the engineering geological investigation report, the investigation report number is 2004-04-K08.
2. Quote according to the bill of quantities, construction drawings, bidding documents and relevant information and instructions provided by the tendering unit.
3. According to the Code for Valuation with Bill of Quantities of Construction Projects (GB50500-2003), the consumption quota and unified base price table of construction projects in Hubei Province in 2003, the consumption quota and unified base price method of decoration projects in Hubei Province, the consumption quota and unit valuation table of installation projects in Hubei Province, and the cost quota of construction and installation projects in Hubei Province.
2. Quota and cost standards adopted, and the basis for influencing the unit price of labor, materials and machinery:
1. Prepared according to the consumption quota of building decoration engineering and the cost quota of building installation engineering in Hubei Province.
2. The labor, materials and machinery in this quotation will be adjusted according to the annual guidance price of Wuhan project cost management information in 2008.
Three. Main contents of power of attorney, agreement and meeting minutes related to budget:
1.XXX budget power of attorney
2.XXX budget agreement
3. Three minutes. XXX budget meeting
4. Total budget, total labor force, steel, cement, wood and asphalt:
1. Total budget: 547,083.77 yuan.
2. Labor cost: 143462.52 yuan.
3. Cement cost: 1986.438+02 yuan.
Verb (abbreviation for verb) Other matters related to the budget but not reflected in the table:
1. The fire resistance of this project is Grade II.
2. The seismic fortification intensity of this project is 7 degrees.
3. Rails are set at the lower openings of windows, and the height of the railings is less than 0.8m.. ..
4. Indoor doors and windows are milky white.
The handrail of the guardrail outside the window is a wooden handrail.
Something like this can be changed.
Question 3: How to write the comprehensive description of the tender? I'll give you a model essay. . I wrote it the other day.
Bengbu Hebei New District Development Co., Ltd.:
We are deeply honored to participate in the bidding activities of your company's "Road Drainage Project of the Second Bid Section of Huaishang Avenue (X-1KLOC-0/Road ~ Logistics Road)". First of all, thank you for your trust in our company. Our company is full of confidence in the construction of this project and sincerely willing to cooperate with your company. And promise: our company will accept and recognize all the quotations in this "Construction Project Bidding Document". Our guiding ideology is-based on the project, reputation first, loyalty and responsibility, to help the owner achieve the overall goal of scheduled project construction investment, quality and schedule control. Through the construction practice of this project, the company's social reputation will be further improved. Our company will cherish this opportunity to participate in the construction.
After receiving your bidding documents, we carefully organized the team, set up a bidding leading group, and sent relevant professional and technical personnel to survey the project site and analyze the construction difficulties. After careful research and brainstorming, we have completed all the contents stipulated in your tender documents, and made the following comprehensive description of the tender for the consideration of leaders, experts and judges.
Once I am lucky enough to win the bid, I will go all out, equip with sufficient resources, make good preparations before construction and the overall planning and layout of the construction site, give full play to the advantages of our company's construction technology and various management, establish a sound management organization, implement strict responsibility system and implement project management. Through the optimal allocation of labor, equipment, materials, funds, technology, methods and information, the expected goals of construction period, quality and social reputation can be achieved.
This tender is prepared on the basis of carefully reading the tender documents, tender drawings and site survey of this project. Construction organization design, construction period, quality, safety and civilized construction target measures, mechanical equipment entering the site, staffing, bidding quotation, etc. Considering the actual ability of the company, we solemnly promise.
1. If our company wins the bid, our company will guarantee to complete the project construction within the time limit quoted in the tender documents.
2. If our company wins the bid, we will ensure that the engineering quality of this project reaches the qualified and above engineering standards.
3. If our company wins the bid, we will carry out the construction of this project in a safe and civilized way, which is of great significance for establishing a good corporate image of our company and creating our brand. Our company will carry out safe and civilized construction in strict accordance with the requirements to ensure the cleanliness and safety of roads and sites inside and outside the construction area. (See the construction organization design for specific measures and methods. )
Please ask the leaders and experts of the bid evaluation team to consider our sincere wishes.
Tenderer: (seal)
Legal representative: (signature and seal)
Date: May 20 10 12.
Question 4: How to write the explanation of not participating in bidding? 5 points XXX tendering agency (or owner) Our company does not participate in the bidding of this project due to XXXXX reasons (usually written, due to time, personnel, finance and other reasons). "You don't need to explain in detail.
Question 5: How to write 1 general description of project bidding quotation? This quotation is prepared according to the instructions to bidders of this project and the relevant clauses in the contract text.
2. The comprehensive unit price and total price filled in the price list of bill of quantities include labor cost, material cost, machinery cost, management fee, profit, tax and other expenses.
3. The quotation of measure items shall be filled in the price list of measure items. Including the expenses incurred by the measures that must be taken to complete the construction of this project.
4. The prices of other projects filled in the price list of other projects, including other expenses necessary to complete the construction of this project except the price list of bill of quantities and the price list of measures.
5. The unit price and total price shall be filled in for each item in the quotation sheet of this bill of quantities. Engineering expenses without unit price and total price shall be deemed to have been included in other unit prices and total prices in the bill of quantities.
6. The currency of this quotation is RMB.
Question 6: How to write the clarification of bidders in the process of bid evaluation? If you want to ask clarification questions to the tenderer, you should ask them to the tenderer within the specified time before the bid closing, that is, clarification before the bid (just write your bid section, unit, questions and contact information clearly). In the process of bid evaluation, the bidder has no chance to ask for clarification, and only the bid evaluation committee can ask the bidder for clarification. If you are asking how to write a clarification reply in the process of bid evaluation, then press the following. If the bid evaluation committee raises questions that need clarification from bidders, first of all, it depends on whether the tenderer has specific requirements for the format of clarification reply and whether there is a fixed format. If not, then at least a clarification reply should be written according to the following contents:
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Name of bid:
Name of bidder:
1, question: XXXXXXXXXX
Answer:
Signature of authorized representative:
Date:
Stamp: (If there is a stamp, there is no stamp, just sign)
Note: Clarification reply should be in the form of question and answer. If it's just a promise to the original question, just write "We promise".
Question 7: How to fill in the tender statement in the tender list: I mainly promise that my tender is true and authentic, and I will not open it before the deadline for bid opening.
Question 8: How to write the description of tender offer?
1, this quotation is compiled according to the instructions to bidders of this project and the relevant clauses in the contract text.
2. The comprehensive unit price and total price filled in the price list of bill of quantities include all expenses such as labor cost, material cost, machinery cost, management fee, profit, tax and risk fund calculated for fixed-price projects.
3. The quotation of measure items shall be filled in the price list of measure items. Including the expenses incurred by the measures that must be taken to complete the construction of this project.
4. The prices of other projects filled in the price list of other projects, including other expenses necessary to complete the construction of this project except the price list of bill of quantities and the price list of measures.
5. The unit price and total price shall be filled in for each item in the quotation sheet of this bill of quantities. Engineering expenses without unit price and total price shall be deemed to have been included in other unit prices and total prices in the bill of quantities.
6. The currency of this quotation is RMB.
7. The bidder shall submit the matters that need to be explained in the tender offer together with the tender offer form in written form.
Question 9: How to write a good overview of the site situation in the tender? This tender document is a model. When bidding, the bidder shall prepare the bidding documents according to its own actual situation, bidding documents, pre-qualification instructions for bidding applicants and other documents. The tender document consists of three parts: the tender letter part, the commercial part and the technical part.
Bidding documents for engineering construction
Project number:
Project name:
Contents of bidding documents: The letter of tender is a part of the bidding documents.
Bidder: (Seal)
Legal representative or entrusted agent: (signature or seal)
Date: Catalogue, identification of legal representative, signature of bidding documents, power of attorney, bidding letter, appendix to bidding letter and bidding letter.
Other bidding materials required by the bidder in the bid documents of bank guarantee format bid guarantee.
Unit name:
Unit nature:
Time of establishment:
Operation cycle:
Name: gender: age: position: legal representative (name of bidder's company). This is to certify that. Model bidding documents for building construction and municipal infrastructure construction.
Second, the bidding documents signed a power of attorney
This power of attorney states: I (name) am the legal representative of (name of authorizer), and I hereby authorize (name of our company) to sign the bidding documents of this project as the legal representative, and I acknowledge that the agent has full authority to sign the contents of the bidding documents of this project on my behalf.
The agent has no right to entrust, and hereby entrusts.
Agent: (signature) Gender: Age:
ID number: Job title:
Legal representative: (signature or seal)
Authorization date:
To: (Name of Tenderee)
1, according to the project bidding document with the number of your project subject to tender, in accordance with other relevant regulations, and by surveying the project site, we study the bidding instructions, contract terms, drawings, engineering construction standards, bill of quantities and other related documents of the above bidding document. We are willing to bid in (currency, amount, unit) (in figures) according to the requirements of the above drawings, contract terms, engineering construction standards and bill of quantities.
2. We have carefully reviewed all the bidding documents, including the revised documents (if any) and relevant attachments.
3. We acknowledge that the appendix to the tender letter is an integral part of our tender letter.
Once we win the bid, we promise to complete and hand over all the projects within calendar days according to the time limit stipulated in the contract agreement.
If we win the bid, we will submit a bank guarantee with a total price of% or a performance guarantee with a total price of% as the performance guarantee.
6. We agree that the submitted bid documents are valid within the bid validity period specified in Article 15 of the Instructions to Bidders. If we win the bid during this period, we will be bound by this.
7. Unless another agreement is reached and takes effect, your letter of acceptance and this tender document will become an integral part of the contract document binding both parties.
8. Together with this tender letter, we will submit (currency, amount and unit) as a tender guarantee.
Legal representative or agent: (signature or seal)
Bank name:
Bank account number: date
Four. AppendixNo. Tender Letter Project Content Contract Terms No. Remarks on the agreed contents: performance bond Bank guarantee performance guarantee amount% of the contract price; construction preparation time; number of days after signing the contract; default amount; number of days; delay compensation limit; early construction period; total construction period; calendar days; quality standard of engineering quality; prepayment amount; prepayment guarantee amount; progress payment time; issuance of monthly payment voucher; completion settlement payment time; issuance of completion settlement payment voucher; and the warranty period of the day after tomorrow shall be subject to the period agreed in the warranty.
Four. bid document
Five, bid guarantee bank guarantee format (specific format provided by the guarantee bank)
Intransitive verb bid security
To: (name of bidder)
According to this letter of guarantee, (name of bidder), as the principal (hereinafter referred to as the bidder) and (the bid guarantee institution) and as the guarantor (hereinafter referred to as the guarantor), shall bear the responsibility of paying (in figures) to (name of tenderer) (hereinafter referred to as the tenderer) in the same direction, and both the bidder and the guarantor shall be bound by this letter of guarantee.
In view of the bidder's participation in the tenderer's bid, this guarantor is willing to provide bid guarantee for the bidder.
The conditions of this letter of guarantee are as follows: if the bidder fails or refuses to sign the contract agreement according to the requirements of the instructions to bidders after receiving your letter of acceptance within the validity period of bidding; Unable or refusing to submit the performance bond as instructed; Withdraw the bid documents within the validity period of the bid. As long as you specify the conditions of any of the above situations, this guarantor will receive your ... & gt
Question 10: How to write the cover of 1 in the bid evaluation report?
2 sign-in form 1 (owner and supervisor)
3. Sign-in Form (Bidder Sign-in)
Record of bid opening (bid quotation, etc.). )
5. Judge sign-in form
6. Qualification form
7. Compliance Review Form
8. Detailed review form