6. Paint the walls -7. Ceiling in kitchen and bathroom -8. Installation of cabinets -9. Wooden door installation-
10. Floor installation-1 1. Paving wallpaper-12. Radiator installation-13. Switch socket installation.
Install-14. Installation of lamps-15. Installation of hardware and sanitary ware-16. Installation of curtain rod-
17. Pioneer Cleaning-18. Furniture comes in-19. Equipment installation -20. Home accessories
Roughly follow these 20 steps to complete the decoration. Now, fight to the death and try your best to keep your eyes open.
Explain the decoration process and many details that need to be paid attention to in the whole process as detailed as possible. ...
I. Analysis of 20 links in the whole decoration process
(1) Pre-design
The same is construction. The difference between people and bees is that the construction of bees is a reflection of instinct, while people are building.
Before you build it, you will form ideas and frameworks in your mind. Therefore, if home improvement is compared to a battle,
Then the preliminary design of home improvement is the "battle plan" of this campaign and the "soul bond" of home improvement.
So again, in the final "Made in Tangliang", the whole story is about the problems that need to be paid attention to in the early design.
I won't repeat the topic here.
In the preliminary design, one thing friends must do is to describe their rooms in detail.
Don't be lazy, you'd better measure yourself. The measurement contents mainly include:
1. Define the areas involved in the renovation process. Especially tile area, wall paint area, wallpaper area and floor.
Area;
2, clear the bearing wall size. Especially it is necessary to design the wall size of furniture in the future.
I remember when my foreman finally settled the total payment for a brick with me according to the "actual amount", he made a calculation.
The area is more than that measured by myself 10 square meter. I was really in distress situation. After re-measurement, work
The dragon turned to reprimand the bricklayer and said, "How did you measure it? ! "So I suggest you test it yourself.
The reason for the quantity. Decoration in many places is the same as being a human being-we may not understand it very well, but we are worried.
There must be a number in the room.
By the way, don't forget to go to the property to go through the construction procedures and pay the decoration deposit before starting work.
(two) the main body is removed or changed.
Entering the construction stage, the main body demolition is the first project, mainly including wall demolition, wall building, wall scraping,
Remove the heating, change the plastic steel window and so on. To put it bluntly, the main body demolition is to put up the framework of the construction site first.
(3) Hydropower transformation
Before the water circuit reform, the main structure should be basically completed. In the hydropower transformation, there are mainly two items: demolition and reconstruction.
Between the links, some friends may know that the initial test of the cabinet should also be carried out. In fact, the so-called cabinets
The first measurement has no actual content, because the walls and floors are not treated, so the cabinet designer will not.
Specific design dimensions can be given, but only in the position of water inlet and lampblack machine socket reserved by the developer.
Give some relevant suggestions. Mainly includes:
1, to see whether the position of the lampblack machine socket affects the installation of lampblack machine in the future;
2. See if the location of the water meter is appropriate;
3. See if the location of the water inlet is convenient for installing the sink in the future.
For the first measurement of cabinets, students with a little experience can do it by themselves. After the waterway reconstruction is completed,
It's best to waterproof the bathroom at once. The kitchen generally doesn't need to be waterproof.
Some friends have always believed that before the renovation, some main materials should enter the site in advance. All I'm saying is, unless it's the theme
Dismantle the main materials to be used, otherwise the main materials such as ceramic tiles and large core boards will enter the site after hydropower transformation.
Because if the circuit transformation involves slotting in the ground, if the tiles and core boards are not properly placed, workers will move in.
Moving is very troublesome. A friend told me the other day that her family met a house full of brick-moving workers.
I want to remind my friend of this problem.
(4) Woodworking
Woodworking, bricklayer and oiler are the "three brothers" in the construction process, and the basic order of appearance is: wood-tile-oil.
The basic entry principle is-whoever is dirty goes first. "Who gets dirty first" is also a basic factor that determines the order of home improvement.
One of the principles, which I will mention later.
In fact, carpentry such as riser, ceiling decoration and plaster line can also be used in a sense.
A detailed consideration: there is no conflict between the main body demolition and waterway modification itself, and sometimes some supporting facilities are needed.
For example, I mentioned in my last post, "If you are going to make a fake wall at home, you should consider whether there is water on the fake wall."
If there are wires, they should be embedded by hydropower transformation personnel. "
(5) Tiling
If the workers are busy, the foreman will usually let the "bricklayer" pass before the "carpenter boss" is over.
It is normal for the second child to enter the field to stick bricks, because there is no conflict between the two.
During the operation of "bricklayer's second child", the installation of the following three links is also involved:
1. Installation of lintels and marble windowsills. The installation of lintel can be completed together with the laying of floor tiles, or it can be
After laying floor tiles, the installation of marble windowsill is generally approved by marble installers after the window cover is completed.
Prepare glass glue, which is convenient for sealing marble and window cover with glass glue.
2. Install the floor drain. Floor drain is the first hardware in home decoration, because it should cooperate with floor tiles.
Installation. Therefore, students should buy a floor drain as soon as possible when they start shopping for building materials.
3. Installation of range hood. The range hood is the first appearance of household appliances. After the kitchen walls and tiles are laid, you can
Consider installing a range hood.
When the "second bricklayer" left the scene, it was possible to measure the cupboard for the second time, precisely on the wall tiles and floor tiles in the kitchen.
After connecting and installing the range hood, you can make a second measurement of the cabinet.
(6) Paint the wall
The "Third Oil Worker" enters the site, mainly completing the basic treatment of the wall surface, painting the top paint for the "First Carpenter" and playing furniture.
Paint, etc. Students who are going to paste wallpaper only need to let the "third oil worker" do it on the wall where wallpaper is planned.
Primary treatment will do. As for whether I left my coat for the last time, I personally don't think this question needs to be taken too seriously.
Son, from my experience in decoration, it is of little significance to leave the top coat, because there is no operation behind.
Dirty than painting.
Write here, fight for breath and chat with you. Be the "boss", "second child" and "third child"
After leaving the scene one after another, many students will think that their renovation is coming to an end. In fact, if you press the number of links, three.
Less than a third. Everyone has this feeling because it is generally understood that decoration is only decoration.
"Construction link", in fact, the "installation link" of decoration is also the focus of decoration.
If the "design link" is to "conceive" what our future home will look like, then the "construction link"
In order to "package" our home, it is really necessary to say "prepare" that almost all furniture is in the "installation process". drink
Sip, go on ...
(7) Ceiling of kitchen and bathroom
As an installation link, the cabinet ceiling is still continuing the "packaging" of the home. At the same time as the ceiling of the kitchen and bathroom,
The kitchen and bathroom moisture-proof ceiling lamp and exhaust fan (Yuba) should have been bought. Students had better put the ceiling lamps in the kitchen and bathroom,
The exhaust fan (Yuba) was installed at the same time, but the thread and hole were left.
By the way, I firmly advocate the "renovation outsourcing theory", even though the foreman promised me that his workers would change their water and electricity.
How to standardize the construction, how to standardize the installation of aluminum gusset plates, how to make wooden doors strong, and how to paste wallpaper.
How to be professional and how to make cabinets practical ... In my opinion, what the decoration team can do is
Woodworking, tiling and painting
Because I believe that professional construction, manufacturers' installation standards and assembly line products are mostly better than.
The handiwork of the workers in the decoration team is slightly better. Decoration is like a game, betting on the skills of workers, just betting on it.
On "My workers are architectural geniuses", I am not practical in my heart.
Many friends let decoration companies and teams undertake a lot of construction tasks, on the one hand, because of themselves.
Time is not plentiful, and another reason is because of the consideration of "project convergence".
In fact, every link of the decoration is very independent. I remember some time ago, a classmate from the south asked questions in the forum and said
When his hometown was renovated, the owner asked specialized workers to do every link. This is the home decoration itself.
There's really no connection at all. On the contrary, students should try their best to play the so-called "contact" in the process of home improvement.
Function ",accurately grasp the choice of materials, master some simple construction technology, and handle the relationship with workers.
Wait, that's the key.
I really want to say that there are problems because of "convergence", such as who will participate in the installation of sanitary ware, lamps and hardware in the later period.
On the one hand, the question of taking responsibility depends on how you get along with the workers, and finally whether anyone is willing to "manage" you; another
On the other hand, when it comes to anyone's "control", I will still say-"Money has existed since God invented it.
There is no problem that cannot be solved. "
Decoration, quality always ranks first, which is the main contradiction and the big principle. Some links are "connected"
This problem is a secondary contradiction. Friends are prepared to make concessions on big contradictions and big principles because of small contradictions.
At the same time, we need to be cautious.
(8) Install the kitchen cabinet
After the ceiling is completed, you can make an appointment to install the cabinet at home. If it goes well, it can be finished in one day. Safe at the same time
There are also sinks (water supply and drainage parts may not be included) and gas stoves. It is best to coordinate the property to put coal before the cabinet is installed.
The gas is ventilated, because the gas stove needs to be tested after installation.
By the way, just talking about the ceiling, there is a problem worth discussing. Many friends choose waterproof gypsum board as kitchen and bathroom ceiling.
With waterproof coating, the quotation of decoration team is generally above 120 yuan per square meter, which is higher than ordinary aluminum gusset plates and PVC gusset plates.
The top is very expensive. The gypsum board ceiling looks flat visually, but once the top water pipe has problems in the future,
Or there is a leak upstairs that needs maintenance downstairs, and so on. Gypsum board ceiling will be removed as a whole, which is more troublesome than gusset ceiling.
Much more. Therefore, everyone should be careful when choosing gypsum board ceiling.
(9) Wooden door installation
The second day after the cabinet was installed, as early as more than a month ago, after the wooden door was measured, it can be installed now. smooth
In other words, it is also a day. At the same time, it is necessary to install hinges, lock doors and suck the floor. Friends should have.
Prepare related hardware.
If you want the wooden door manufacturer to install the window cover, you should also measure it when the wooden door manufacturer measures it.
And install wooden doors at the same time on the same day. At the same time, the installation time of marble windowsill should be considered backwards and arranged in the window.
After installing the sleeve.
Remarks: The production cycle of wooden doors is generally one month, so in order to make the construction period closely connected, it is necessary to dismantle and modify the main body.
As soon as possible after the completion, let the wooden door manufacturer come to measure the size of the door opening. Regarding the handling of doorways, everyone needs to pay attention.
This means that if the height of the door at home is inconsistent, workers need to treat it as the same height-beautiful.
(10) Floor installation
The floor can be installed the day after the wooden door is installed. If all goes well, it will take a day. Floor installation requirements
Please pay attention to the following questions:
1. Before the floor is installed, it is best to let the manufacturer come to investigate whether the ground needs leveling or local leveling. Some people will.
The decoration company or decoration team will advise students to level the ground or partially level it, subject to the actual investigation of the floor manufacturer;
2. Before the floor is installed, the floor paved at home should be cleaned to ensure that the floor is dry, so
Don't use water when cleaning.
3. When installing the floor, if possible, the floor must be cut in the corridor. In the past, the forum was still discussing this issue.
As discussed, some students think it is immoral to cut the floor in the corridor to pollute public areas. My idea is that when it's finished,
Clean it up. It's okay. Cutting the floor indoors pollutes the wall seriously, and there are people in the cupboard.
I believe that the students who have been renovated have some experience in cutting stone tables and countertops.
(1 1) Laying wallpaper
The day after the floor is installed, you can make an appointment to paste wallpaper when the home is cleaned up. If it goes well, it will be the same.
God's time. If possible, the floor should be protected on the day of wallpaper pasting; It doesn't matter if there are no conditions,
It is no problem to leave the wallpaper glue left on the floor to Pioneer for cleaning. Try to put the wallpaper on the wall before it is laid.
Do nothing.
(12) Installation of radiator
The day after the wallpaper is laid, students who have replaced or removed the radiator can put the heat away in a down-to-earth manner.
This device is hung on the wall. It's also a day.
Wooden door-floor-wallpaper-radiator, generally recognized as the correct installation order, wood should be installed first.
The door ensures that the skirting line of the floor can be closely connected with the door cover of the wooden door; The wallpaper after installation is mainly because of the floor.
The installation was dirty and dusty, which seriously polluted the wallpaper. Here, I say again, "Whoever is dirty will go first."
The principle of. Finally, install the radiator, because the radiator can only be installed after the wallpaper is laid on the wall.
The gradual renovation process is also designed under various constraints and restrictions. There are occasional exceptions,
For example, the Holtz door needs to be fitted with the floor first and then the door, but this exception is rare in the decoration process.
In addition, I repeatedly said "one day" earlier, which means that students need to be reminded that "one day" is very important to the whole.
The decoration time is not long, so even if there is no installation conflict, such as cabinets and wooden doors, the students will do their best.
Don't book two installations at the same time in one day, especially these "big pieces" mentioned above, because
For these "big pieces", installation is very important. It's best to focus on one site instead of "doing two things at once". ask
Learn to comfort yourself-we were not bad that day.
(13) switch socket installation
There is only one reminder: friends should have questions about the number and location of switch sockets in various natural rooms at home.
Understand or record in detail, especially the students who paste wallpaper. Sometimes wallpaper workers are irresponsible, wallpaper
Hula was laid at once, and he didn't need wallpaper knife to mark the position of your switch socket. Therefore, we still need the same
Scholars know for themselves.
(14) Installation of lamps and lanterns
Install the lights. There is nothing to say. After the lights were installed, the house lit up and bid farewell to the dazzling intensity of 100 watt incandescent bulbs during the renovation.
Light-it feels good.
(15) Installation of Hardware Sanitary Ware
Before buying pipe fittings, bathroom fittings, toilets, clothes hangers, etc. , are all installed. In front of those "big"
After the installation, the home is still very "cold". When the lamps and hardware sanitary ware are installed, the home will be "alive".
Yes, it's really "alive". It's no exaggeration to say that I opened the dragon water for the first time and watched the water "wow, wow" flow out.
My heart will be beautiful; Convenient, the newly installed toilet at home for the first time will have a great sense of accomplishment. By the way, I returned it.
A good name-"Virgo".
(16) Installation of curtain rod
The installation of curtain rod marks the basic end of home improvement.
(17) development and cleaning
Don't install curtains before the start-up cleaning, remember to remind everyone in the post of "explaining curtains" When developing and cleaning,
Don't have furniture and unnecessary household appliances at home, leave as many "planes" as possible, so as to open up and clean.
A thorough cleaning.
(18) Furniture comes into play
Regarding the purchase time of furniture, my suggestion is to choose a home after the renovation of water circuit is completed at the earliest.
We only have a rough idea of the basic size range of furniture. So some students have already started decorating before decorating.
I am in a hurry to order all the furniture, so I don't think it is necessary.
(19) Home appliances enter the site
At this time, it's time for home appliances to enter the market. It's time to install and prepare to move in!
(20) Home accessories
Home decoration, the last step of home improvement, has changed from decoration to decoration, including the installation of curtains.
Home accessories link. As for buying curtains, it is best to book furniture first to avoid style conflict. Home accessories also include
You can consider buying some green plants, hanging murals, decorative handicrafts, etc ... In short, after you stay, you will
You can play freely.
Second, the two links in the decoration process
Friends who have seen the first section may feel a little confused. In order to facilitate further understanding of these 20 steps and the entrainment between them.
For some links that need attention, 10 is added on the basis of the previous 20 "stars".
"Stars", as follows:
1 Commencement formalities -2. Self-measurement -3. Pre-design -4. Demolition and reconstruction of the main body -5. Wooden door manufacturers come to measure.
Quantity -6 Preliminary Measurement of Cabinets -7 Hydropower Renovation -8 Waterproofing of Toilet -9 Entry of Main Materials-10 Woodworking
-1 1 tiling (installing windowsill and floor drain)-12 installing range hood-13 secondary measurement of cabinet-14 brush
Wall decoration-15 kitchen and bathroom ceiling-16 gas supply-17 cabinet installation (sink and gas stove are installed at the same time)-
-18 wooden door installation-19 floor installation -20 wallpaper laying -2 1 radiator installation -22 switch socket
Installation -23 lamps installation -24 hardware sanitary ware installation -25 curtain rod installation -26 development and cleaning-
27 furniture comes into play -28 home appliances installation -29 home accessories -30 moving.
Things I didn't know until after the renovation (for later use)
Experience makes you take fewer detours.
1. The mattress is too soft.
2. If the cooking frequency at home is high, try to give up the open kitchen, which will cause oil smoke problems.
3. Toilets and kitchens are all small water treasures, and hot water comes quickly and is more convenient to use.
Chinese range hoods are more attractive than European ones.
5. the power socket can be decorated as much as possible, otherwise there are drag boards everywhere in the house.
6. Be sure to reserve a power socket next to the toilet, or even the washing clothes will not be installed.
7. bath PK shower, if you choose one, it is still recommended to take a shower. Many people have never taken a bath.
Shower doesn't mean shower room. The glass in the shower room is still very tired to wipe. You can also choose to hang a shower curtain.
8. If you have two bathrooms, you still need to install a bathtub. There is no need to soak up big clothes and help the baby bathe.
Wrong choice, you don't need a jacuzzi, you can't soak it several times, and it's extremely expensive.
9. If you are not a person who doesn't cook, you'd better install air conditioning in the kitchen.
10. If you like surfing the Internet, at least two Internet ports and more than two sockets should be reserved on each wall of each room. not have
Line routing can really solve the problem, but it is said that it is still unstable sometimes.
1 1. I'm sorry that the kitchen flue is not perforated. Now as long as someone is cooking in the building, they must use my own range hood.
Open it at the same time, or the room will smell of oil smoke.
12. The locations of various sockets in the room are different from the sizes of furniture bought later, which wastes a lot of sockets.
13. If you can't buy it in the mall, don't ask a carpenter to do it! ! ! ! ! Unless this woodworking skill
Very good.
14. The floor color should be a little lighter, so it is not easy to see the ash, but the kitchen and bathroom floor tiles should be a little deeper, so it is not easy to find them everywhere.
It's hair. It's the most resistant to dirt.
15. It is best to install ceiling fans in the restaurant, which is super comfortable.
16. As much storage space as possible, there will be more and more sundries to be stored after check-in.
17. It is better to use ceramic tiles for balcony walls, which are more waterproof than paint.
18. I regret buying so many lamps and installing so many lamps, but in fact I just used those lamps for fixed purposes. . .
19. The dressing table is made of glass, which is easy to get dirty.
20. I forgot to install the switch at the bedside, and I had to get out of bed and turn off the lights every time. Winter is very sad.
2 1. Bathroom hardware, faucets and the like must be paid for.
22. Try not to leave indelible places when decorating, and it is difficult to make a dead corner.
23. Families who plan to have children in the future must calculate the size and reserve the position of the crib at the bedside.
24. It is suggested that all faucets should be equipped with hot and cold water pipes. It won't cost much to install more when decorating, and it's extremely difficult to remedy afterwards.
25. The layout of the room is as impractical as possible. The renminbi will not be torn off if it is posted. Sooner or later, it will be out of date!
26. Pay attention to the size of the door inside your house when you buy anything. Don't buy it and you can't move in.
27. The solid wood floor feels good but needs maintenance, and the composite floor is easy to clean.
28. Invisible doors are useless, and it is also troublesome to open ventilation.
29. The walk-in wardrobe is good, but it is easy to accumulate dust. An open bookshelf, shelf, etc. (There is no door,
It looks good, but it hurts to rub, especially books, which are covered with dust.
30. This lamp must not be washed. Just hang it until the dust accumulates.