After the completion of the project, it will form an inner ring of Zhuzhou with Tianyuan Bridge, Jianshe Road in Lusong District and Changjiang Road in Tianyuan District, effectively alleviating the traffic congestion in the urban area and Zhuzhou Bridge, further improving the traffic environment in Zhuzhou City, meeting the needs of perfecting urban functions, and promoting the development and construction of land along the line and Hexi area, truly expanding the urban skeleton and providing favorable guarantee for the sustainable economic development of Zhuzhou City.
brief introduction
After passing through Jiang Yan Middle Road, Cai Yong Road and Jianshe Middle Road, the approach bridge on the east bank of Songlu Bridge passes through Renmin Middle Road and connects Honggang Road. The approach bridge on the west bank of the river crosses Binjiang North Road and Dongping Road in the planning, and then crosses Changjiang North Road to connect Lushan Road. In addition, there is an interchange on the west bank of the river connecting the bridge, Binjiang North Road and Dongping Road. The bridge is an important channel of Zhuzhou Inner Ring Road, connecting Tianyuan District and Lusong District and crossing Xiangjiang River. It connects the core area of Hexi and Hedong, and the direction of Hedong also extends to Yunlong New City and Zhuzhou (National) Automobile City. The length of the bridge is 182 1.6m, in which the length of the main bridge is 330m, the length of the road connection is 9 14m, and the length of the ramp is 690.65m The bridge is 28m wide and has six lanes in both directions. The speed of the bridge is 40km/h, the design vehicle load is -A, and the design navigable clear height is 10m. The bridge type adopts the scheme of arch-beam rigid structure combination system.
Brief introduction of project development
In September, 2007, CCCC Second Waterway Engineering Bureau Co., Ltd. signed the Investment and Construction Contract of the Fifth Xiangjiang Bridge with Zhuzhou Municipal Government, and undertook the investment and construction of this project in BT mode, with a total investment of about 455 million yuan, which is expected to be completed in 2010/year.
On May 6, 2008, the project officially started.
On August 20 10 8 18, Zhuzhou Xiangjiang Fifth Bridge completed the closure of the main bridge.
Engineering construction project
Project overview
The Fifth Xiangjiang Bridge is located in the upper reaches of the Xiangjiang River estuary in Baishi Port, about 1400 meters from the upper reaches of Zhuzhou No.2 Water Plant. It is a super-large bridge across Xiangjiang River and connecting Lusong District and Tianyuan District. The bridge starts from Lusong District in the east, connects with Honggang Road, crosses Xiangjiang River, reaches Tianyuan District in the west and connects with Lushan Road. The approach bridge on the east bank of the Yangtze River is elevated across the middle road along the Yangtze River, Cai Yong Road and Jianshe Road, and meets Renmin Road. The approach bridge on the west bank of the river crosses the planned Binjiang North Road and Dongping Road, and crosses the Yangtze River North Road. In addition, there is an interchange on the west bank of the river, connecting the bridge, Binjiang North Road and Dongping Road under planning. The bridge type is a three-span arch beam steel structure combination system. The length of the bridge is 182 1.6m, in which the main bridge is 330m, the road connection length is 9 14m, the ramp length is 690.65m, and the accessory length is 2352m. The bridge is 28 meters wide and has six lanes in both directions. The total investment of the project is estimated to be 726 million yuan, which will be started in June 2007 +0 1, and it is planned to open to traffic at the end of 20 10/.
progress
On June 22nd, 20 10, the main bridge was closed, the main bridge body, approach bridge and ramp bridge were all completed, and asphalt concrete laying on the bridge deck, pavement railings, bridge body painting, greening, auxiliary roads and ancillary works were under construction. The accumulated investment has reached 599.86 million yuan.
Project characteristics
During the construction of the Fifth Xiangjiang Bridge, in order to respond to the requirements of the "four modernizations" put forward by the municipal party committee and the municipal government, the design schemes of greening, lighting and bridge body painting were adjusted in time to meet the needs of the urban upgrading campaign.
After the completion of the Fifth Xiangjiang Bridge, all the positions on both sides of the main bridge arch, the arch cables and the approach side of the main bridge are illuminated by LED lights, which highlights the outline and outlines the unique shape of the whole bridge, just like a dragon hovering overhead on the Xiangjiang River. The cables in the arch of the bridge present a sense of rhythm of music, which is refreshing. The pier part is illuminated by sodium lamp, which forms a golden light effect, reflecting the sense of stability at the bottom of the bridge, glittering and translucent and soft.
According to the ecological design, the greening landscape project of Xiangjiang Fifth Bridge is based on rich green, and the landscape of plant communities is pursued at both ends of the bridge. Based on the diversity of species, plant landscaping strives to achieve ecological and beautification functions as much as possible in a certain space. In the greening area at the bottom of the bridge, the rough reinforced concrete contours such as climbing plants, small shrubs and turf are softened, making the bridge scenic area more eco-friendly.
The whole bridge painting project has been added to the Fifth Xiangjiang Bridge. The approach bridge box girder and column shall be painted with silver-gray Du Fang paint, and the approach bridge collision wall, main bridge railing and steel box arch shall be painted with white fluorocarbon paint. The whole bridge body is simple and beautiful.
Under the supervision of the owner and the supervision unit, the construction unit CCCC No.2 Navigation Bureau made scientific scheduling and strict management, and the project quality was good, the safe and civilized construction was effectively controlled, and no major safety accidents occurred. By grasping the progress, the contract period was completed six months ahead of schedule.
Project importance
After the completion of the Fifth Xiangjiang Bridge, it will form an "inner ring" of Zhuzhou City with Tianyuan Bridge, Jianshe Road and Changjiang Road, effectively alleviating the traffic congestion in the downtown area and Zhuzhou No.1 Bridge, and further improving the urban traffic environment. Its completion will further improve the traffic environment and investment environment of our city, expand the urban development space and accelerate the economic and social development of Zhuzhou.