Minutes of highway handover acceptance meeting

Project Name: Machang Road Primary School Teaching Building, Jianghan District, Wuhan City

Meeting place: field office.

Meeting time: 20xx65438+February 10.

Construction units: Wuhan Jianghan Education Bureau, Zhang Jiujian and Liu Ping.

Designers: Wuhan Dongyi Architectural Design Co., Ltd., Chen Xiaodong,,, Wang.

Survey unit: Wuhan Survey and Design Institute, Peng Huazhong.

Supervisors: Wuhan Construction Technology Development Co., Ltd.,, Duan,, Bai Xiong.

Construction units: Hubei Zhong Da Construction Co., Ltd., Lin Bin and Zhang Xiaoting.

Supervisors: Jianguan Station, Jianghan District, Wuhan, qi zhou, Yu Cong.

Meeting contents:

Organized by Party A, the comprehensive teaching building project of Machang Road Primary School in Jianghan District, Wuhan was completed and accepted on 20xx 65438+2 10, and the summary opinions are as follows:

Construction unit: Since the project started, the construction has been carried out in strict accordance with the design drawings, design changes and specifications. The construction of each division shall be supervised by the supervision engineer. After each working procedure is completed, we shall conduct self-inspection first, and then report it to the supervision engineer for acceptance. After the supervision engineer has passed the acceptance, the next working procedure can be carried out. In the control of raw materials, all incoming materials have product certificates and re-inspection reports, and can only be put into use after inspection. The design, survey, construction, supervision and pipe construction station of the foundation and main branch of this project have passed the acceptance, and now it is reported to the completion acceptance of this project.

Supervision unit: The project started on May 8, 20xx and was completed by the end of August, with tight construction period and fast construction progress. Our supervision engineer carries out the whole process of tracking supervision and quality control, and strictly requires the construction unit to carry out the construction according to the contract requirements, design drawings and specifications. Engineering materials shall strictly implement the system of on-site witness sampling and inspection, and shall be used in this project after passing the re-inspection. The technical data of this project is basically complete, and the engineering data file is true, complete and effective. The quality of each sub-division and sub-division project meets the requirements of design and construction specifications, contractual requirements, mandatory standards for engineering construction and relevant national laws and regulations, and it is agreed to be completed and accepted.

Survey unit: The geological conditions of this project are surveyed by our unit, and the foundation adopts prestressed static pressure pipe pile foundation and reinforced concrete cap foundation. According to the foundation acceptance and settlement observation results of this project meet the requirements of the specification, the completion acceptance of this project is agreed.

Design unit: The overall construction of this project is very good, which is consistent with the design drawings, but the interior of the water retaining line of the outer balcony needs to be re-treated, and it is hoped that the settlement observation work in the later period will be strengthened. After participating in the construction and acceptance of the project at various stages, the project meets the requirements of design and construction specifications, meets the requirements of mandatory standards for engineering construction, and the project structure is safe and reliable, and the completion acceptance is agreed.

Construction unit: the overall construction quality of this project is good, and it meets the completion acceptance conditions as a whole. We agree with the opinions of all parties and carry out the completion acceptance of the project. But if there are some minor problems, please ask the construction unit to rectify as soon as possible. Outdoor fire hydrants need to move towards the wall, the installation of steel door peephole needs to be improved, the leaking part of bridge hanger needs to be painted with antirust paint and topcoat, and the bridge and fire pipe nodes need to be cleaned well.

Housing management station: According to the on-site acceptance, the overall construction quality of the project is good and the structural safety is good. What needs to be put forward is that, for safety reasons, pvc pipes leaving the roof should be clamped, rainwater grates should be added to the roof outlet, and protective measures should be taken for the height difference between the overhead ground on the first floor and the outdoor ground. There is a small amount of stagnant water in the balcony floor drain outside the library, which needs to be adjusted. Agree to the completion acceptance of this project, and require the construction party to deal with and improve the places that need rectification as soon as possible, collect and sort out the data, and complete the completion record.

Minutes of highway handover acceptance meeting [2]

Project Name: * * * * * * Reconstruction Project

Meeting time: * * * * * * *

Meeting place: * * Meeting room

Participants: See the meeting sign-in form (attached) for details.

Moderator: * * *

Meeting minutes text

* * * Presided over the meeting, first introduced the participants of each unit, announced the agenda of the meeting, and spoke on behalf of the * * * working group; He introduced the whole process of the project from project initiation to implementation to completion, and thanked the participating units for their hard work and the strong support of the local government and various functional departments. Then the construction unit, supervision unit and design unit make quality report and evaluation, then conduct on-site quality inspection, and finally make the project acceptance summary.

A, the construction unit of the project introduction and acceptance report:

The main contents of this project include road engineering, traffic engineering, rain and sewage pipeline engineering, road lighting, electric power and telecommunications engineering. The total length of the road is * * * meters, the width of the road is * *-* * meters, and the cross-sectional layout is: (riverside) * meters sidewalk+* meters driveway+* meters sidewalk; Asphalt concrete pavement. The total investment is about * * * ten thousand yuan.

Second, adjourn temporarily, and the engineering entity quality inspection team and the engineering data inspection team will inspect the on-site engineering entities and engineering data respectively;

Three, the end of the inspection, inspection team report inspection:

1, the engineering entity meets the design requirements and acceptance specifications, with complete facilities and functions, meeting the use requirements, and meeting the acceptance conditions in all aspects, and agrees to accept;

2. The raw materials used in all divisions and subdivisions of this project have passed the inspection, the test results of concrete and mortar specimens meet the design requirements, the relevant engineering data are complete, and the acceptance specifications are met, so acceptance is agreed.

Four, the construction unit of the project quality and safety self-evaluation report; The representative of the construction unit introduced the general situation of the project and the implementation of the project, and thanked the participating units and relevant departments for their support and help. If the project self-evaluation is qualified, please accept it.

Five, the supervision unit of the project supervision and management evaluation report, that the quality of the project is qualified, in line with the acceptance conditions, agreed to acceptance;

Six, the design unit of engineering design management evaluation report, that the quality of the project is qualified, in line with the acceptance conditions, agreed to acceptance;

Seven, the survey unit of engineering survey management evaluation report, that the building did not appear obvious uneven settlement, the overall quality of the structure is good, the project meets the acceptance conditions, agreed to acceptance;

Eight, the cost unit of the project cost management evaluation report, that the use of project funds is good, in line with the acceptance conditions, agreed to acceptance;

Nine, Foshan counterpart aid Shuimo Town Agency Management Center believes that the reconstruction project of Shuimo Town Section of Laosanxuan Highway is qualified and agrees to the completion acceptance;

Ten, Wenchuan county quality supervision station to explain the project acceptance procedures, explain the relevant responsibilities.

As the main body, the completion acceptance documents are fully prepared, the members of the acceptance team meet the requirements, the acceptance scheme is feasible, the project does not violate the mandatory standards, the project completion acceptance is organized in an orderly manner, the procedures are legal, the quality spot check and visual quality of the project entity meet the design requirements, and meet the requirements of the engineering inspection and evaluation standards, so the acceptance is agreed.

XI。 Summary of the completion acceptance of the construction unit: All units agree that the quality of each sub-project of this project meets the requirements and agree to the completion acceptance.

Attachment: * * * Sign-in Form for Project Completion Acceptance Meeting

* * * * * * * Engineering Supervision Department

* * * * Year * * Month * * Day

Copy: construction unit

Cc: all relevant units

Minutes of highway handover acceptance meeting [3]

Yong gang Jian hui Ji [20 1 1]

Minutes of Acceptance Meeting of Zhongzhai Coal Wharf Foundation Treatment Project (Phase III) in Chuanshan Port Area of Ningbo-Zhoushan Port

201111On October 7th, Ningbo Port Construction and Development Co., Ltd. organized a handover acceptance meeting for the foundation treatment project (Phase III) of Zhongzhai Coal Terminal in Chuanshan Port Area of Ningbo-Zhoushan Port. The meeting was presided over by Comrade Zhang Tiefeng, and the participants were Ningbo Port Engineering Co., Ltd. and Ningbo Port Engineering Project Management Co., Ltd.

The meeting first introduced the project: the foundation treatment project of Zhongzhai Coal Wharf in Chuanshan Port Area of Ningbo-Zhoushan Port (Phase III) is located in Zhongzhai, Baifeng Town, Beilun District, Ningbo City, on the west side of LNG project, about 60 kilometers away from Ningbo City. The construction scale of this project is 4000KN.m for foundation reinforcement of dynamic compaction gravel pile, with an area of about 28000m2;; The sand pile is about 1.5 million, with a total volume of about 58,000, and the gravel pile 1 1.5 million, with a total volume of about 46,000. The total pilot hole of gravel pile is about 80000m, and the project cost is about 22989.9438+000 yuan. The construction unit of this project is Ningbo Port Co., Ltd., the design unit is China Communications Third Harbor Engineering Survey and Design Institute Co., Ltd., the construction unit is Ningbo Port Engineering Co., Ltd., and the supervision unit is Ningbo Port Engineering Project Management Co., Ltd. Second, the data problems found in the acceptance, please rectify them in time and press Ningbo.

Filing requirements of Hong Kong Construction Development Co., Ltd..

Three. Please clean up the personnel and machinery in time.

Four. All parties at the meeting had intensive discussions on the project quality, and reached a consensus that the construction unit had completed all the construction contents as agreed in the contract, the project quality met the design and specification requirements, the project passed the acceptance, and the project had passed the handover acceptance.

20 1 1 year 1 1 month 7

List of participants:

Ningbo Harbor Engineering Co., Ltd.: Zhang Benda, Jason, Chen Genfu,

Zhu Chunjiang

Ningbo Port Engineering Project Management Co., Ltd.:, Zhu, Peng.

Lu Bing

Ningbo Port Construction and Development Co., Ltd.: Zhang Tiefeng, Wu Qingqing.

Keywords:: Minutes of the Handover Acceptance Meeting of Zhongzhai Coal Wharf Foundation Treatment Project (Phase III) in Chuanshan Port Area of Ningbo-Zhoushan Port

Cc: Ningbo Port Engineering Project Management Co., Ltd., Ningbo Port Engineering Co., Ltd. and CCCC Third Harbor Engineering Survey and Design Institute Co., Ltd.

Ningbo Port Construction and Development Co., Ltd. 20111.07