Construction engineering quality acceptance procedures and organization?

Construction project quality acceptance procedures and organization summary: the investigation of sub-projects of foundation and foundation and main structure, the project leader of the design unit and the head of the technical and quality department of the construction unit should also participate in the acceptance of relevant sub-projects.

Procedures and organizations for quality acceptance of construction projects

1. The inspection lot and subdivisional work shall be accepted by the supervision engineer (project technical director of the construction unit), and the project professional quality (technical) director of the construction unit shall organize the acceptance.

2. The chief supervision engineer (the project leader of the construction unit) shall organize the project leader of the construction unit and the technical and quality leaders to carry out the acceptance of the partial project.

3. The person in charge of the project of the survey and design unit and the person in charge of the technical quality department of the construction unit of the sub-project of foundation and main structure should also participate in the acceptance of the relevant sub-project.

4. After the completion of the unit project, the construction unit shall organize relevant personnel to carry out inspection and evaluation, and submit the project acceptance report to the construction unit.

5. After the construction unit receives the project acceptance report, the person in charge of the construction unit (project) shall organize the design, supervision and other construction units (including subcontractors) to carry out the project acceptance of the unit (sub-unit).

6. When the unit project is constructed by subcontractors, subcontractors shall inspect and evaluate the contracted projects according to the procedures specified in this standard, and the general contractor shall send people to attend. After the completion of the subcontracted project, the relevant information of the project shall be submitted to the general contractor.

7. When the parties involved in the acceptance have objections to the project quality acceptance, they may request the local construction administrative department or the project quality supervision institution to coordinate the handling.

8. After the unit project quality acceptance, the construction unit shall submit the project completion acceptance report and related documents to the construction administrative department for the record within the specified time.

The above information was collected and sorted by Zhong Da Consulting Company. For more information about "Procedures and Organization of Quality Acceptance of Construction Projects", please pay attention to the column of Zhong Da Consulting Industry. "It is easy to win the bid with a little construction." For information about construction enterprises, award-winning achievements, builders under construction, enterprise honors, qualification grades, industrial and commercial information, legal proceedings, etc., please visit Zhong Da Consulting, Construction Link or follow the official account of Zhong Da Consulting WeChat for enquiries.